Rate Matters
General rate case (Docket No. RP18-1126) On August 31, 2018, we filed a general rate case with the FERC for an overall increase in rates and to comply with the terms of the settlement in our prior rate case to file a rate case no later than August 31, 2018. On September 28, 2018, the FERC issued an order accepting and suspending our general rate filing to be effective March 1, 2019, subject to refund and the outcome of a hearing, except that rates for certain
services that were proposed as overall rate decreases were accepted, without suspension, to be effective October 1, 2018. The decreased rates will not be subject to refund but may be subject to decrease prospectively under Section 5 of the Natural Gas Act of 1938, as amended. On March 18, 2019, the FERC accepted our motion to place the rates that were suspended by the September 28, 2018 order into effect on March 1, 2019, subject to refund. On December 31, 2019, after reaching an agreement in principle with the participants, we filed a stipulation and agreement (“Agreement”) with the FERC that would resolve all issues in this proceeding without the need for a hearing. The Agreement will become effective after a FERC order that approves the Agreement without material modification becomes no longer subject to rehearing. We anticipate FERC approval of the Agreement in the second quarter of 2020. As of December 31, 2019, we have accrued a reserve for rate refunds related to increased rates collected since March 2019 of approximately $188.8 million, which we believe is adequate for any refunds that may be required.
Environmental Matters
We have had studies underway for many years to test some of our facilities for the presence of toxic and hazardous substances such as polychlorinated biphenyls (PCBs) and mercury to determine to what extent, if any, remediation may be necessary. We have also similarly evaluated past on-site disposal of hydrocarbons at a number of our facilities. We have worked closely with and responded to data requests from the U.S. Environmental Protection Agency (EPA) and state agencies regarding such potential contamination of certain of our sites. We are conducting environmental assessments and implementing a variety of remedial measures that may result in increases or decreases in the total estimated costs. At December 31, 2019, we had a balance of approximately $2.5 million for the expense portion of these estimated costs, $1.2 million recorded in Accrued liabilities and $1.3 million recorded in Other Long-Term Liabilities - Other in the Consolidated Balance Sheet. At December 31, 2018, we had a balance of approximately $3.5 million for the expense portion of these estimated costs, $1.5 million recorded in Accrued liabilities and $2.0 million recorded in Other Long-Term Liabilities - Other in the Consolidated Balance Sheet.
We have been identified as a potentially responsible party (PRP) at various Superfund and state waste disposal sites. Based on present volumetric estimates and other factors, our estimated aggregate exposure for remediation of these sites is less than $0.5 million. The estimated remediation costs for all of these sites are included in the environmental liabilities discussed above. Liability under the Comprehensive Environmental Response, Compensation and Liability Act and applicable state law can be joint and several with other PRPs. Although volumetric allocation is a factor in assessing liability, it is not necessarily determinative; thus, the ultimate liability could be substantially greater than the amounts described above.
The EPA and various state regulatory agencies routinely promulgate and propose new rules, and issue updated guidance to existing rules. These rulemakings include, but are not limited to, rules for reciprocating internal combustion engine and combustion turbine maximum achievable control technology, air quality standards for one-hour nitrogen dioxide emissions, and volatile organic compound and methane new source performance standards impacting design and operation of storage vessels, pressure valves, and compressors. The EPA previously issued its rule regarding National Ambient Air Quality Standards for ground-level ozone. We are monitoring the rule’s implementation as it will trigger additional federal and state regulatory actions that may impact our operations. Implementation of the regulations is expected to result in impacts to our operations and increase the cost of additions to Total property, plant and equipment, net in the Consolidated Balance Sheet for both new and existing facilities in affected areas. We are unable to reasonably estimate the cost of additions that may be required to meet the regulations at this time due to uncertainty created by various legal challenges to these regulations and the need for further specific regulatory guidance.
We consider prudently incurred environmental assessment and remediation costs and the costs associated with compliance with environmental standards to be recoverable through rates. To date, we have been permitted recovery of environmental costs, and it is our intent to continue seeking recovery of such costs through future rate filings.
Other Matters
Various other proceedings are pending against us and are considered incidental to our operations.

Summary
We estimate that for all matters for which we are able to reasonably estimate a range of loss, including those noted above and others that are not individually significant, our aggregate reasonably possible losses beyond amounts accrued for all of our contingent liabilities are immaterial to our expected future annual results of operations, liquidity and financial position. These calculations have been made without consideration of any potential recovery from third parties. We have disclosed all significant matters for which we are unable to reasonably estimate a range of possible loss.
Other Commitments
Commitments for construction We have commitments for construction and acquisition of property, plant and equipment of approximately $91 million at December 31, 2019.