XML 88 R41.htm IDEA: XBRL DOCUMENT v2.4.0.8
Summary of Current Cost Estimates by Major Type of Cost Associated with 2014 Manufacturing Footprint Realignment Plan (Detail) (2014 Manufacturing Footprint Realignment, USD $)
In Millions, unless otherwise specified
6 Months Ended
Jun. 29, 2014
Minimum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred $ 42.0
Maximum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 53.0
Termination benefits | Minimum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 12.0
Termination benefits | Maximum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 15.0
Facility closure and other exit costs | Minimum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 2.0 [1]
Facility closure and other exit costs | Maximum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 5.0 [1]
Accelerated depreciation charges | Minimum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 10.0
Accelerated depreciation charges | Maximum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 12.0
Other | Minimum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred 18.0 [2]
Other | Maximum
 
Restructuring Cost And Reserve [Line Items]  
Total estimated amount expected to be incurred $ 21.0 [2]
[1] Includes costs to transfer product lines among facilities and outplacement and employee relocation costs.
[2] Consists of other costs directly related to the Plan, including project management, legal and regulatory costs.