-----BEGIN PRIVACY-ENHANCED MESSAGE----- Proc-Type: 2001,MIC-CLEAR Originator-Name: webmaster@www.sec.gov Originator-Key-Asymmetric: MFgwCgYEVQgBAQICAf8DSgAwRwJAW2sNKK9AVtBzYZmr6aGjlWyK3XmZv3dTINen TWSM7vrzLADbmYQaionwg5sDW3P6oaM5D3tdezXMm7z1T+B+twIDAQAB MIC-Info: RSA-MD5,RSA, FRTJwBLhnbuKTCCMXBslYHV8oT5NMDngPqavfd11R3nq4wyqThL7SE2gAgY3FYcn +rjrqRmUVeEt0Z2/1ASidw== 0001193125-06-063972.txt : 20060327 0001193125-06-063972.hdr.sgml : 20060327 20060327170252 ACCESSION NUMBER: 0001193125-06-063972 CONFORMED SUBMISSION TYPE: 8-K PUBLIC DOCUMENT COUNT: 2 CONFORMED PERIOD OF REPORT: 20060327 ITEM INFORMATION: Other Events FILED AS OF DATE: 20060327 DATE AS OF CHANGE: 20060327 FILER: COMPANY DATA: COMPANY CONFORMED NAME: TEJON RANCH CO CENTRAL INDEX KEY: 0000096869 STANDARD INDUSTRIAL CLASSIFICATION: REAL ESTATE [6500] IRS NUMBER: 770196136 STATE OF INCORPORATION: DE FISCAL YEAR END: 1231 FILING VALUES: FORM TYPE: 8-K SEC ACT: 1934 Act SEC FILE NUMBER: 001-07183 FILM NUMBER: 06712507 BUSINESS ADDRESS: STREET 1: 4436 LEBEC ROAD STREET 2: PO BOX 1000 CITY: LEBEC STATE: CA ZIP: 93243 BUSINESS PHONE: 6612483000 MAIL ADDRESS: STREET 1: 4436 LEBEC RD STREET 2: PO BOX 1000 CITY: LEBEC STATE: CA ZIP: 93243 8-K 1 d8k.htm FORM 8-K Form 8-K
Table of Contents

SECURITIES AND EXCHANGE COMMISSION

WASHINGTON, DC 20509

 


FORM 8-K

CURRENT REPORT

PURSUANT TO SECTION 13 OR 15(D) OF THE

SECURITIES EXCHANGE ACT OF 1934

Date of Report (Date of earliest event reported) March 27, 2006

Tejon Ranch Co.

(Exact Name of Registrant as Specified in Charter)

 

Delaware   1-7183   77-0196136
(State or Other Jurisdiction of Incorporation)   (Commission File Number)   (IRS Employer Identification No.)

 

P. O. Box 1000, Lebec, California   93243
(Address of Principal Executive Offices)   (Zip Code)

Registrant’s telephone number, including area code 661 248-3000

 

 


(Former Name or Former Address, if Changed Since Last Report)

Not applicable

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

 

¨ Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

¨ Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

¨ Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

 

¨ Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

 


 

1


Table of Contents

TABLE OF CONTENTS

 

Item 8.01

   Other Events    3

Signatures

      4

 

2


Table of Contents
Item 8.01 Other Events

On March 27, 2006, the Company issued a press release announcing that Kern County Superior Court Judge Kenneth Twisselman issued a ruling on Friday, March 24, 2006, clearing the way for expansion of the Tejon Industrial Complex – East.

Exhibit

 

99.1    Press Release of the Company dated March 27, 2006, announcing approval of Tejon Industrial Complex – East.

 

3


Table of Contents

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

 

Date:  

March 27, 2006

   

TEJON RANCH CO.

     

By:

  /S/ ALLEN E. LYDA
     

Name:

 

Allen E. Lyda

     

Title:

 

Vice President, and Chief Financial Officer

 

4

EX-99.1 2 dex991.htm PRESS RELEASE Press Release

EXHIBIT 99.1

KERN COUNTY JUDGE OKAYS

EXPANSION OF TEJON INDUSTRIAL COMPLEX

BAKERSFIELD, Calif. (March 27, 2006) – Tejon Ranch Company (NYSE:TRC) is clear to move ahead with Tejon Industrial Complex – East following Kern County Superior Court Judge Kenneth Twisselman’s ruling on Friday dismissing the last legal challenges to the expansion of the commercial/industrial business park community.

The Kern County Board of Supervisors originally approved the 1,109-acre expansion of Tejon Industrial Complex in 2003, but that approval was set aside when Judge Twisselman ordered the County to do additional work on the Environmental Impact Report in response to a lawsuit filed by the Center for Biological Diversity and several other no-growth groups.

In response to the court’s ruling, the County prepared a supplemental analysis to the EIR, and in November 2005, the Board of Supervisors again approved the expansion of Tejon Industrial Complex. In doing so, the Board specifically noted the quality of the development plan and the economic impact of the master planned industrial/commercial center. Tejon Industrial Complex will generate thousands of jobs and millions of dollars in tax revenue for the county.

Judge Twisselman on Friday rejected arguments presented by attorneys for the Center for Biological Diversity and ruled the supplemental analysis prepared by the County satisfied his original court order, which had called for additional air quality analysis and the correction of two minor technical errors in the biological report.

“We congratulate the Kern County Planning Department and the County Counsel’s office. They did an excellent job,” said Robert A. Stine, President and CEO of Tejon Ranch Company. “We are pleased to have this issue behind us so we can move ahead with our vision for Tejon Industrial Complex, a vision that involves preserving California’s legacy and providing for California’s future. We believe Tejon Industrial Complex does both by creating jobs and economic opportunity for thousands, and by helping to improve the air quality in the San Joaquin Valley.”

Stine was referring to Tejon’s voluntary program to reduce air emissions.

Through a contract with the San Joaquin Valley Air Pollution Control District, Tejon Ranch established a fund the district is using to pay for the replacement of older polluting diesel engines. The program is already underway and engines are in the process of being replaced throughout the San Joaquin Valley air basin.

(more)

JUDGE OKAYS EXPANSION OF TEJON INDUSTRIAL COMPLEX

2-2-2-2-2


When they again approved the expansion of Tejon Industrial Complex last November, the supervisors were uniformly complimentary of Tejon Ranch’s efforts to clean the air.

“To have fully offset air quality impacts is something they ought to be commended for,” said 4th District Supervisor and Chairman Ray Watson. “You can’t ask for a higher standard of development, in my opinion.”

“Tejon Ranch should be congratulated for its efforts to clean the air,” added 5th District Supervisor Michael Rubio. “The company is serving as a model that others should follow.”

2nd District Supervisor Don Maben also decried the delay created by the original lawsuit.

“This project has already created a thousand jobs and by now would have likely created another thousand and improved the quality of life for those holding those jobs, if there wasn’t this delay,” Maben said. “It’s a shame this had to take almost three years.”

About Tejon Ranch Company (NYSE: TRC)

Tejon Ranch Company is a diversified real estate development and agribusiness company, whose principal asset is its 270,000-acre land holding located approximately 60 miles north of Los Angeles and 30 miles south of Bakersfield. For more information on the company, please go to www.tejonranch.com.

-----END PRIVACY-ENHANCED MESSAGE-----