XML 201 R76.htm IDEA: XBRL DOCUMENT v3.8.0.1
Regulatory Matters Regulatory Matters - Schedule of Revenue Increases (Decreases) (Details) - Commonwealth Edison Co [Member] - USD ($)
$ in Millions
12 Months Ended
Sep. 11, 2017
Jun. 09, 2017
[1]
Dec. 31, 2017
Dec. 31, 2016
Dec. 31, 2015
Public Utilities, Requested Rate Increase (Decrease), Amount   $ (7) $ 44 [2] $ 90 [2] $ 68 [2]
Public Utilities, Approved Rate Increase (Decrease), Amount $ 12   $ 11 [2] $ 94 [2] $ 86 [2]
Public Utilities, Approved Equity Capital Structure, Percentage 6.47%   8.43% [3] 8.47% [3] 8.61% [3]
Public Utilities, Approved Return on Equity, Percentage 8.40%        
[1] Reflects higher projected PJM capacity revenues compared to projected energy efficiency costs.
[2] The time period for any challenges to the annual transmission formula rate update flings expired with no challenges submitted
[3] Represents to the weighted average debt and equity return on transmission rate bases.