XML 54 R11.htm IDEA: XBRL DOCUMENT v3.8.0.1
Regulatory Matters (All Registrants)
9 Months Ended
Sep. 30, 2017
Regulated Operations [Abstract]  
Regulatory Matters (All Registrants)
Regulatory Matters (All Registrants)
Except for the matters noted below, the disclosures set forth in Note 3 - Regulatory Matters of the Exelon 2016 Form 10-K reflect, in all material respects, the current status of regulatory and legislative proceedings of the Registrants. The following is an update to that discussion.
Illinois Regulatory Matters
Distribution Formula Rate (Exelon and ComEd). On April 13, 2017, ComEd filed its annual distribution formula rate with the ICC pursuant to EIMA. The filing establishes the revenue requirement used to set the rates that will take effect in January 2018 after the ICC’s review and approval, which is due by December 2017. The revenue requirement requested is based on 2016 actual costs plus projected 2017 capital additions as well as an annual reconciliation of the revenue requirement in effect in 2016 to the actual costs incurred that year. ComEd's 2017 filing request includes a total increase to the revenue requirement of $96 million, reflecting an increase of $78 million for the initial revenue requirement for 2017 and an increase of $18 million related to the annual reconciliation for 2016. The revenue requirement for 2017 provides for a weighted average debt and equity return on distribution rate base of 6.47% inclusive of an allowed ROE of 8.40%, reflecting the average rate on 30-year treasury notes plus 580 basis points. The annual reconciliation for 2016 provided for a weighted average debt and equity return on distribution rate base of 6.45% inclusive of an allowed ROE of 8.34%, reflecting the average rate on 30-year treasury notes plus 580 basis points less a performance metrics penalty of 6 basis points. See table below for ComEd's regulatory assets associated with its distribution formula rate. For additional information on ComEd's distribution formula rate filings see Note 3Regulatory Matters of the Exelon 2016 Form 10-K.
On December 6, 2016, the ICC issued a final order approving the 2016 distribution formula rate, which included a total increase to the revenue requirement of $127 million, reflecting an increase of $134 million for the initial revenue requirement for 2016 and a decrease of $7 million related to the annual reconciliation for 2015. On December 20, 2016, the ICC granted ComEd's and other parties' joint application for rehearing on the impact that changing ComEd’s OSHA recordable rate for 2014 and 2015 had on the revenue requirement approved in this order. On March 22, 2017, the ICC issued an order approving ComEd's proposal to reduce the 2016 revenue requirement by $18 million, which was reflected in customer rates beginning in April 2017.
Illinois Future Energy Jobs Act (Exelon, Generation and ComEd)
Background
On December 7, 2016, FEJA was signed into law by the Governor of Illinois. FEJA was effective June 1, 2017, and includes, among other provisions, (1) a Zero Emission Standard (ZES) providing compensation for certain nuclear-powered generating facilities, (2) an extension of and certain adjustments to ComEd’s electric distribution formula rate, (3) new cumulative persisting annual energy efficiency MWh savings goals for ComEd, (4) revisions to the Illinois RPS requirements, (5) provisions for adjustments to or termination of FEJA programs if the average impact on ComEd’s customer rates exceeds specified limits, (6) revisions to the existing net metering statute and (7) support for low income rooftop and community solar programs.
Zero Emission Standard
FEJA includes a ZES that provides compensation through the procurement of ZECs targeted at preserving the environmental attributes of zero-emissions nuclear-powered generating facilities that meet specific eligibility criteria.
On September 11, 2017, the ICC approved the IPA's ZES Procurement Plan filed with the ICC on July 31, 2017. Bidders interested in participating in the procurement process had 14 days following the ICC's approval of the plan to submit the required eligibility information and become qualified bidders. Generation’s Clinton and Quad Cities nuclear plants timely submitted the required eligibility information to the ICC and responded to follow up questions. Winning bidders will contract directly with Illinois utilities, including ComEd, for 10-year terms extending through May 31, 2027. The ZEC price will be based upon the current social cost of carbon as determined by the Federal government and is initially established at $16.50 per MWh of production, subject to annual future adjustments determined by the IPA for specified escalation and pricing adjustment mechanisms designed to lower the ZEC price based on increases in underlying energy and capacity prices. Illinois utilities will be required to purchase all ZECs delivered by the zero-emissions nuclear-powered generating facilities, subject to annual cost caps. For the initial delivery year, June 1, 2017 - May 31, 2018, the ZEC annual cost cap, is set at $235 million (ComEd’s share is approximately $170 million). For subsequent delivery years, the IPA-approved targeted ZEC procurement amounts will change based on forward energy and capacity prices. ZECs delivered to Illinois utilities in excess of the annual cost cap will be paid in subsequent years if the payments do not exceed the prescribed annual cost cap for that year.
On October 27, 2017, the IPA released the schedule for the ZEC procurement event indicating that contracts with zero emission facilities will be fully executed on January 30, 2018. Winning bidders will be entitled to compensation for the sale of ZECs retroactive to the June 1, 2017 effective date of FEJA. To the extent Generation is selected as a winning bidder, revenue retroactive to the effective date of FEJA would be recognized in the period the contracts are executed. Upon the execution of the contracts, ComEd will record an associated obligation and expense for the procurement of ZEC's.
ComEd will recover all costs associated with purchasing ZECs through a new rate rider that provides for an annual reconciliation and true-up to actual costs incurred by ComEd to purchase ZECs, with any difference to be credited to or collected from ComEd’s retail customers in subsequent periods with interest. ComEd began billing its retail customers under its new ZEC rate rider on June 1, 2017 and recorded a regulatory liability of $71 million as of September 30, 2017 for revenues recorded in advance of incurring expenses.
On February 14, 2017, two lawsuits were filed in the Northern District of Illinois against the IPA alleging that the state’s ZEC program violates certain provisions of the U.S. Constitution.  One lawsuit was filed by customers of ComEd, led by the Village of Old Mill Creek, and the other was brought by the EPSA and three other electric suppliers. Both lawsuits argue that the Illinois ZEC program will distort PJM's FERC-approved energy and capacity market auction system of setting wholesale prices, and seek a permanent injunction preventing the implementation of the program.  Exelon intervened and filed motions to dismiss in both lawsuits. In addition, on March 31, 2017, plaintiffs in both lawsuits filed motions for preliminary injunction with the court; the court stayed briefing on the motions for preliminary injunction until the resolution of the motions to dismiss. On July 14, 2017, the district court granted the motions to dismiss. On July 17, 2017, the plaintiffs appealed the decision to the Seventh Circuit. Plaintiffs-Appellants initial brief was filed on August 28, 2017 and the state’s and Exelon’s briefs were filed on October 27, 2017. Reply briefs are due on December 12, 2017. Exelon cannot predict the outcome of these lawsuits. It is possible that resolution of these matters could have a material, unfavorable impact on Exelon’s and Generation’s results of operations, financial positions and cash flows.
See Note 7 - Early Nuclear Plant Retirements for additional information regarding the economic challenges facing Generation’s Clinton and Quad Cities nuclear plants and the expected benefits of the ZES.
ComEd Electric Distribution Rates
FEJA extends the sunset date for ComEd’s performance-based electric distribution formula rate from 2019 to the end of 2022, allows ComEd to revise the electric distribution formula rate to eliminate the ROE collar, and allows ComEd to implement a decoupling tariff if the electric distribution formula rate is terminated at any time. ComEd will revise its electric distribution formula rate to eliminate the ROE collar beginning with the reconciliation filed in 2018 for the 2017 calendar year. Elimination of the ROE collar effectively offsets the favorable or unfavorable impacts to ComEd's electric distribution formula rate revenues associated with variations in delivery volumes associated with above or below normal weather, numbers of customers or usage per customer. ComEd began reflecting the impacts of this change in its electric distribution services costs regulatory asset in first quarter 2017. As of September 30, 2017, ComEd recorded an increase to its electric distribution services costs regulatory asset of approximately $21 million for this change.
FEJA requires ComEd to make non-recoverable contributions to low income energy assistance programs of $10 million per year for 5 years as long as the electric distribution formula rate remains in effect. With the exception of these contributions, ComEd will recover from customers, subject to certain caps explained below, the costs it incurs pursuant to FEJA either through its electric distribution formula rate or other recovery mechanisms.
Energy Efficiency
Prior to FEJA, Illinois law required ComEd to implement cost-effective energy efficiency measures and, for a 10-year period ending May 31, 2018, cost-effective demand response measures to reduce peak demand by 0.1% over the prior year for eligible retail customers.
Beginning January 1, 2018, FEJA provides for new cumulative annual energy efficiency MWh savings goals for ComEd, which are designed to achieve 21.5% of cumulative persisting annual MWh savings by 2030, as compared to the deemed baseline of 88 million MWhs of electric power and energy sales. FEJA deems the cumulative persisting annual MWh savings to be 6.6% from 2012 through the end of 2017. ComEd expects to spend approximately $250 million to $400 million annually from 2017 through 2030 to achieve these energy efficiency MWh savings goals. In addition, FEJA extends the peak demand reduction requirement from 2018 to 2026. Because the new requirements apply beginning in 2018, FEJA extends the existing energy efficiency plans, which were due to end on May 31, 2017, through December 31, 2017. FEJA also exempts customers with demands over 10 MW from energy efficiency plans and requirements beginning June 1, 2017. On September 11, 2017, the ICC approved ComEd's 2018 - 2021 energy efficiency plan with minor modifications filed by ComEd with the ICC on June 30, 2017.
FEJA allows ComEd to cancel its existing energy efficiency rate rider and replace it with an energy efficiency formula rate, and to defer energy efficiency costs (except for any voltage optimization costs which will be recovered through the electric distribution formula rate) as a separate regulatory asset that will be recovered through the energy efficiency formula rate over the weighted average useful life, as approved by the ICC, of the related energy efficiency measures. ComEd will earn a return on the energy efficiency regulatory asset at a rate equal to its weighted average cost of capital, which is based on a year-end capital structure and calculated using the same methodology applicable to ComEd’s electric distribution formula rate.  Beginning January 1, 2018 through December 31, 2030, the return on equity that ComEd earns on its energy efficiency regulatory asset is subject to a maximum downward or upward adjustment of 200 basis points if ComEd’s cumulative persisting annual MWh savings falls short of or exceeds specified percentage benchmarks of its annual incremental savings goal. ComEd will be required to file an update to its energy efficiency formula rate on or before June 1 each year, with resulting rates effective in January of the following year. The annual update will be based on projected current year energy efficiency costs, PJM capacity revenues, and the projected year-end regulatory asset balance less any related deferred income taxes. The update will also include a reconciliation of any differences between the revenue requirement in effect for the prior year and the revenue requirement based on actual prior year costs and actual year-end energy efficiency regulatory asset balances less any related deferred income taxes. ComEd records a regulatory asset or liability and corresponding increase or decrease to Operating revenues for any differences between the revenue requirement in effect and ComEd’s best estimate of the revenue requirement expected to be approved by the ICC for that year’s reconciliation.
ComEd cancelled its existing energy efficiency rate rider effective June 2, 2017. On August 1, 2017, ComEd filed with the ICC a reconciliation of revenues and costs incurred through the cancellation date. On August 30, 2017, the ICC approved ComEd's request, filed on August 1, 2017, to issue an $80 million credit on retail customers' bills in October 2017 for the majority of the over-recoveries with any final adjustment applicable to the over-recoveries to be billed or credited in the future. As of September 30, 2017, ComEd’s over-recoveries associated with its former energy efficiency rate rider were $33 million.
Initial Energy Efficiency Formula Rate Filing
On August 15, 2017, the ICC approved ComEd's new initial energy efficiency formula rate filed with the ICC on June 9, 2017 pursuant to FEJA. The filing establishes the formula under which energy efficiency rates will be calculated going forward and the revenue requirement used to set the initial rates for the period October 1, 2017 through December 31, 2017. The initial revenue requirement is based on projected costs and projected PJM capacity revenues for the period from June 1, 2017 through December 31, 2017, and projected year-end 2017 energy efficiency regulatory asset balances (less any related deferred income taxes). ComEd requested an initial decrease in revenue requirement of $7 million reflecting higher projected PJM capacity revenues compared to projected energy efficiency costs and provides for a weighted average debt and equity return of 6.47% inclusive of an allowed ROE of 8.40%, reflecting the average rate on 30-year treasury notes plus 580 basis points. The annual reconciliation for 2017 will be included in ComEd’s 2018 energy efficiency formula rate filing and reflected in customer rates beginning January 2019. The approved energy efficiency formula rate also provides for revenue decoupling to effectively offset the favorable or unfavorable impacts to ComEd's energy efficiency formula rate revenues associated with variations in delivery volumes associated with above or below normal weather, numbers of customers or usage per customer.
As of September 30, 2017, Exelon and ComEd recorded a regulatory asset of $78 million under the energy efficiency formula, reflecting $83 million of deferred energy efficiency costs partially offset by $5 million of over recoveries for the initial energy efficiency formula rate reconciliation.
2017 Energy Efficiency Formula Rate Filing
On September 11, 2017, the ICC approved ComEd's annual energy efficiency formula rate filed with the ICC on June 30, 2017 pursuant to FEJA. The filing establishes the revenue requirement used to set rates that will take effect in January 2018. The revenue requirement for 2018 is based on projected 2018 energy efficiency costs and PJM capacity revenues, and year-end 2018 energy efficiency regulatory asset balances (less any related deferred income taxes). In its 2017 filing ComEd requested a total increase to the revenue requirement of $12 million and provides for a weighted average debt and equity return of 6.47% inclusive of an allowed ROE of 8.40%, reflecting the average rate on 30-year treasury notes plus 580 basis points. The annual reconciliation for 2018 will be included in ComEd’s 2019 energy efficiency formula rate filing, and reflected in customer rates beginning January 2020.
Renewable Portfolio Standard
Existing Illinois law requires ComEd to purchase each year an increasing percentage of renewable energy resources for the customers for which it supplies electricity. This obligation is satisfied through the procurement of RECs. FEJA revises the Illinois RPS to require ComEd to procure RECs for all retail customers by June 2019, regardless of the customers’ electricity supplier, and provides support for low-income rooftop and community solar programs, which will be funded by the existing Renewable Energy Resources Fund and ongoing RPS collections. FEJA also requires ComEd to use RPS collections to fund utility job training and workforce development programs in the amounts of $10 million in each of the years 2017, 2021, and 2025. ComEd recorded a $10 million and $20 million current and noncurrent liability, respectively, as of September 30, 2017 associated with this obligation. ComEd will recover all costs associated with purchasing RECs and funding utility job training and workforce development programs through a new RPS rate rider that provides for a reconciliation and true-up to actual costs, with any difference between revenues and expenses to be credited to or collected from ComEd’s retail customers in subsequent periods with interest. The first reconciliation and true-up for RECs will occur in 2021 and cover revenues and costs for the four year period beginning June 1, 2017 through May 31, 2021. Subsequently, the RPS rate rider will provide for an annual reconciliation and true-up. ComEd began billing its retail customers under its new RPS rate rider on June 1, 2017 and recorded a related regulatory liability of $7 million as of September 30, 2017. ComEd also recorded a regulatory liability of $38 million for alternative compliance payments received from RES to purchase RECs on behalf of the RES in the future.
As of September 30, 2017, ComEd had received $45 million of over-recovered RPS costs and alternative compliance payments from RES, which are deposited into a separate interest bearing bank account pursuant to FEJA and are classified as Restricted cash on Exelon's and ComEd's Balance Sheets.
Customer Rate Increase Limitations
FEJA includes provisions intended to limit the average impact on ComEd customer rates for recovery of costs incurred under FEJA as follows: (1) for a typical ComEd residential customer, the average impact must be less than $0.25 cents per month, (2) for nonresidential customers with a peak demand less than 10 MW, the average annual impact must be less than 1.3% of the average amount paid per kWh for electric service by Illinois commercial retail customers during 2015, and (3) for nonresidential customers with a peak demand greater than 10 MW, the average annual impact must be less than 1.3% of the average amount paid per kWh for electric service by Illinois industrial retail customers during 2015.
On June 30, 2017, ComEd submitted a 10-year projection to the ICC of customer rate impacts for residential customers and nonresidential customers with a peak demand less than 10 MW. Such projections indicate that customer rate impacts will not exceed the limitations set by FEJA discussed below. Thereafter, beginning in 2018, ComEd must submit a report to the ICC for residential customers and nonresidential customers with a peak demand less than 10 MW by February 15th and June 30th of each year, respectively. For nonresidential customers with a peak demand greater than 10 MW, ComEd must submit a report to the ICC by May 1 of each year if a rate reduction will be necessary in the following year. For residential customers, the reports will include the actual costs incurred under FEJA during the preceding year and a rolling 10-year customer rate impact projection. The reports for nonresidential customers with a peak demand less than 10 MW will also include the actual costs incurred under FEJA during the preceding year, as well as the average annual rate increase from January 1, 2017 through the end of the preceding year and the average annual rate increase projected for the remainder of the 10-year period.
If the projected residential customer or nonresidential customer with a peak demand less than 10 MW rate increase exceeds the limitations during the first four years, ComEd is required to decrease costs associated with FEJA investments, including reductions to ZEC contract quantities. If the projected residential customer or nonresidential customer with a peak demand less than 10 MW rate increase exceeds the limitations during the last six years, ComEd is required to demonstrate how it will reduce FEJA investments to ensure compliance. If the actual residential customer or nonresidential customer with a peak demand less than 10 MW rate increase exceeds the limitations for any one year, ComEd is required to submit a corrective action plan to decrease future year costs to reduce customer rates to ensure future compliance. If the actual residential customer or nonresidential customer rate exceeds the limitations for two consecutive years, ComEd can offer to credit customers for amounts billed in excess of the limitations or ComEd can terminate FEJA investments. If ComEd chooses to terminate FEJA investments, the ICC shall order termination of ZEC contracts and further initiate proceedings to reduce energy efficiency savings goals and terminate support for low-income rooftop and community solar programs. ComEd is allowed to fully recover all costs incurred as of and up to the date of the programs’ termination.
For the energy efficiency formula, ComEd records a regulatory asset or liability and corresponding increase or decrease to Operating revenues for any differences between the revenue requirement in effect and ComEd’s best estimate of the revenue requirement expected to be approved by the ICC for that year’s reconciliation. For the other rate riders established under FEJA, ComEd records a regulatory asset or liability for any differences between revenues and incurred expenses.
Renewable Energy Resources (Exelon and ComEd). In accordance with legislation in effect on December 31, 2016, the IPA's Procurement Plans include the procurement of cost-effective renewable energy resources in amounts that equal or exceed a minimum target percentage of the total electricity that each electric utility supplies to its eligible retail customers. The June 1, 2016 target renewable energy resources obligation for the utilities was at least 11.5%. This obligation increases by at least 1.5% each year thereafter to an ultimate target of at least 25% by June 1, 2025. All goals are subject to rate impact criteria set forth by Illinois legislation. As of September 30, 2017, ComEd had purchased renewable energy resources or equivalents, such as RECs, in accordance with the IPA Procurement Plan. ComEd currently retires all RECs upon transfer and acceptance. ComEd is permitted to recover procurement costs of RECs from retail customers without mark-up through rates.
In accordance with FEJA that took effect on June 1, 2017, beginning with the plan or plans to be implemented in the 2017 delivery year, the IPA shall develop a long term renewable resources procurement plan (LT Plan).  The RPS target percentages for the overall service territory have not changed through June 1, 2025 although FEJA extended the 25% RPS target to delivery years after 2025. Currently, each RES and each utility is responsible for the renewable resource obligation of the customers it supplies power for. Over time, this will change and the utility will procure renewable resources based on the retail load of substantially all customers in its service territory. For the delivery year beginning June 1, 2017, the LT Plan shall include cost effective renewable energy resources procured by the utility for the retail load the utility supplies and for 50% of the retail customer load supplied by Retail Electric Suppliers in the utility service territory on February 28, 2017.  Utility procurement for RES supplied retail customer load will increase to 75% June 1, 2018 and to 100% beginning June 1, 2019.
Pennsylvania Regulatory Matters
Pennsylvania Procurement Proceedings (Exelon and PECO). Through PECO’s PAPUC approved DSP Programs, PECO procures electric supply for its default electric customers through PAPUC approved competitive procurements. 
On March 17, 2016, PECO filed its fourth DSP Program with the PAPUC proposing a 24-month term from June 1, 2017 through May 31, 2019, in compliance with electric generation procurement guidelines set forth in Act 129.  On December 8, 2016, the PAPUC approved the fourth DSP Program for the modified 48-month term and deferred CAP Shopping to another proceeding.  Office of Consumer Advocate and Low Income Advocates subsequently filed a Petition for Reconsideration and Clarification related to CAP Shopping. On March 16, 2017, the PAPUC granted reconsideration and consolidated the proceeding with the DSP II docket, which includes the pending CAP Shopping plan that would allow low-income CAP customers to purchase their generation supply from EGSs. PAPUC referred the consolidated proceedings to the Office of Administrative Law Judge for hearing and decision.
 Pennsylvania Act 11 of 2012 (Exelon and PECO). In February 2012, Act 11 was signed into law, which provided the PAPUC authority to approve the implementation of a distribution system improvement charge (DSIC) in rates designed to recover capital project costs incurred to repair, improve or replace utilities’ aging electric and natural gas distribution systems in Pennsylvania.  Prior to recovering costs pursuant to a DSIC, the PAPUC's implementation order requires a utility to have a Long Term Infrastructure Improvement Plan (LTIIP) approved by the Commission, which outlines how the utility is planning to increase its investment for repairing, improving or replacing aging infrastructure.  The PAPUC approved PECO’s petition for its proposed electric DSIC and LTIIP on October 22, 2015 for spending of $275 million over a 5 year period through 2020.  The PAPUC approved PECO's petition for its proposed modified gas LTIIP on June 14, 2017 for spending of $762 million over a 10 year period through 2022.
Maryland Regulatory Matters
2017 Maryland Electric Distribution Rates (Exelon, PHI and Pepco). On March 24, 2017, Pepco filed an application with the MDPSC to increase its annual electric distribution base rates by $69 million, which was updated to $67 million on August 24, 2017, reflecting a requested ROE of 10.1%.  The application included a request for an income tax adjustment to reflect full normalization of removal costs associated with pre-1981 property, which accounted for $18 million of the requested increase. On October 20, 2017, the MDPSC approved an increase in Pepco electric distribution rates of $34 million, reflecting a ROE of 9.5%. On October 27, 2017, the MDPSC issued an errata order revising the approved increase in Pepco electric distribution rates to $32 million. The errata order corrected a number of computational errors in the original order but did not alter any of the findings.  The new rates became effective for services rendered on or after October 20, 2017.  In its decision, the MDPSC denied Pepco’s request regarding the income tax adjustment without prejudice to Pepco filing another similar proposal with additional information.  Requests for rehearing are due November 20, 2017.
2017 Maryland Electric Distribution Rates (Exelon, PHI and DPL). On July 14, 2017, DPL filed an application with the MDPSC to increase its annual electric distribution base rates by $27 million, which was updated to $22 million on September 28, 2017, reflecting a requested ROE of 10.1%.  DPL expects a decision in the matter in the first quarter of 2018, but cannot predict how much of the requested increase the MDPSC will approve.
2016 Maryland Electric Distribution Rates (Exelon, PHI and DPL). On February 15, 2017, the MDPSC approved an increase in DPL electric distribution rates of $38 million reflecting a ROE of 9.6%.  The new rates became effective for services rendered on or after February 15, 2017.  The MDPSC also denied DPL’s request to continue its Grid Resiliency Program, through which DPL proposed to invest $5 million a year for two years to improve priority feeders and install single-phase reclosing fuse technology. The final order did not result in the recognition of any incremental regulatory assets or liabilities.
Cash Working Capital Order (Exelon and BGE). On November 17, 2016, the MDPSC rendered a decision in the proceeding to review BGE’s request to recover its cash working capital (CWC) requirement for its Provider of Last Resort service, also known as Standard Offer Service (SOS), as well as other components that make up the Administrative Charge, the mechanism that enables BGE to recover all of its SOS-related costs.  The Administrative Charge is now comprised of five components:  CWC, uncollectibles, incremental costs, return, and an administrative adjustment, which is an adder to the utility’s SOS rate to act as a proxy for retail suppliers’ costs.  The Commission accepted BGE's positions on recovery of CWC and pass-through recovery of BGE’s actual uncollectibles and incremental costs.  The order also grants BGE a return on the SOS.  The Commission ruled that the level of the administrative adjustment will be determined in BGE’s next rate case. On December 16, 2016, MDPSC Staff requested clarification concerning the amount of return on the SOS awarded to BGE and on December 19, 2016, the residential consumer advocate sought rehearing of the return awarded. On January 24, 2017, the MDPSC issued an order denying the MDPSC Staff request for clarification and the residential consumer advocate request for rehearing. On February 22, 2017, the residential consumer advocate filed an appeal of the MDPSC's orders with the Circuit Court for Baltimore City. The residential consumer advocate filed its Memorandum on Appeal on June 5, 2017 and subsequent Reply Memoranda were filed by BGE and the MDPSC on July 7, 2017 and July 12, 2017, respectively. On August 7, 2017, following oral argument by the parties, a decision was issued from the Circuit Court affirming the decision of the MDPSC. On September 5, 2017, the residential consumer advocate filed an appeal of the Circuit Court's decision to the Maryland Court of Special Appeals. BGE cannot predict the outcome of this appeal.
Smart Meter and Smart Grid Investments (Exelon and BGE). In August 2010, the MDPSC approved a comprehensive smart grid initiative for BGE that included the planned installation of 2 million residential and commercial electric and natural gas smart meters at an expected total cost of $480 million of which $200 million was funded by SGIG. The MDPSC’s approval ordered BGE to defer the associated incremental costs, depreciation and amortization, and an appropriate return, in a regulatory asset until such time as a cost-effective advanced metering system is implemented. As of September 30, 2017 and December 31, 2016, the balance of BGE's regulatory asset was $219 million and $230 million, respectively, representing incremental program deployment costs. The current quarter balance of $219 million consists of three major components, including $133 million of unamortized incremental deployment costs of the AMI program, $54 million of unamortized costs of the non-AMI meters replaced under the program, and $32 million related to post-test year incremental program deployment costs incurred prior to approval became effective June 2016. The balance as of September 30, 2017 reflects the impact of the cost disallowances and adjustments in BGE's 2015 electric and natural gas distribution rate case. The incremental deployment costs for the AMI program and the non-AMI meter components of the regulatory asset are being recovered through rates and amortized to expense over a 10 year period, while the post-test year incremental program deployment costs have not yet been approved for recovery by the MDPSC. A return on the regulatory asset is currently included in rates, except for the $54 million portion representing the unamortized cost of the retired non-AMI meters and a $32 million portion related to post-test year incremental program deployment costs.
As a combined result of the MDPSC orders in BGE's 2015 electric and natural gas distribution rate case, BGE recorded a $52 million charge in June 2016 to Operating and maintenance expense in Exelon’s and BGE’s Consolidated Statements of Operations and Comprehensive Income reducing certain regulatory assets and other long-lived assets and reclassified $56 million of non-AMI plant costs from Property, plant and equipment, net to Regulatory assets on Exelon's and BGE's Consolidated Balance Sheets. For further information, see Note 3 - Regulatory Matters of the Exelon 2016 Form 10-K.
Delaware Regulatory Matters
2017 Electric and Natural Gas Distribution Rates (Exelon, PHI and DPL). On August 17, 2017, DPL filed applications with the DPSC to increase its annual electric and natural gas distribution base rates by $24 million, which was updated to $31 million on October 18, 2017, and $13 million, respectively, reflecting a requested ROE of 10.1%. DPL expects a decision in the electric proceeding and the gas proceeding in the third quarter of 2018, but cannot predict how much of the requested rate increases the DPSC will approve. While the DPSC is not required to issue a decision on the application within a specified period of time, Delaware law allows DPL to put into effect $2.5 million of the rate increase two months after filing the application and the entire requested rate increase seven months after filing, subject to a cap and a refund obligation based on the final DPSC order.  On October 24, 2017, the Staff of the DPSC and the Public Advocate filed a joint motion to dismiss DPL's electric distribution base rate application without prejudice to refiling, arguing that the amount of the requested increase to $31 million required additional time to review and additional public notice.  The DPSC is expected to decide at its meeting on November 9, 2017. DPL cannot predict the outcome of this matter.
2016 Electric and Natural Gas Distribution Rates (Exelon, PHI and DPL). On May 17, 2016, DPL filed applications with the DPSC to increase its annual electric and natural gas distribution base rates by $63 million, which was updated to $60 million on March 8, 2017, and $22 million, respectively, reflecting a requested ROE of 10.6%. Delaware law allowed DPL to put into effect $2.5 million of each of the rate increases effective July 16, 2016. On December 17, 2016, the DPSC approved an additional $30 million in electric distribution rates and an additional $10 million in natural gas distribution rates effective December 17, 2016, subject to refund based on the final DPSC orders.
On March 8, 2017, DPL entered into a settlement agreement with the Division of the Public Advocate, Delaware Electric Users Group and the DPSC Staff in its electric distribution rate proceeding, which provides for an increase in DPL annual electric distribution base rates of $31.5 million reflecting a ROE of 9.7% compared to the $32 million increase previously put into effect.  On May 23, 2017, the DPSC issued an order approving the settlement agreement, with the new rates effective June 1, 2017. Pursuant to the settlement agreement, no refund of the interim rates put into effect on July 16, 2016 and December 17, 2016 (as discussed above) is required.
On April 6, 2017, DPL entered into a settlement agreement with the Division of the Public Advocate and the DPSC Staff in its natural gas distribution rate proceeding, which provides for an increase in DPL annual natural gas distribution base rates of $4.9 million reflecting a ROE of 9.7%. The settlement agreement also provides that DPL will refund amounts collected under the temporary rates effective July 16, 2016 and December 17, 2016 (as discussed above) in excess of the $4.9 million, and that the new rates will be effective within thirty days of DPSC approval of the settlement agreement. On June 6, 2017, the DPSC issued an order approving the settlement agreement, with the new rates effective July 1, 2017. Pursuant to the settlement agreement, a rate refund plus interest of approximately $5 million was issued to customers beginning in August 2017 for which a regulatory liability has been recorded as of September 30, 2017. This is a one-time refund and was included on customer bills from mid-August through mid-September.
District of Columbia Regulatory Matters
2016 Electric Distribution Rates (Exelon, PHI and Pepco). On June 30, 2016, Pepco filed an application with the DCPSC to increase its annual electric distribution base rates by $86 million, which was updated to $77 million on February 1, 2017, reflecting a requested ROE of 10.6%.
On July 25, 2017, the DCPSC approved an increase in Pepco electric distribution base rates of $37 million reflecting a ROE of 9.5%. The new rates became effective for services rendered on or after August 15, 2017.  In its decision, the DCPSC ordered that the $26 million customer rate credit created as a result of the Exelon and PHI merger will be provided primarily to residential customers and some small commercial customers to offset the impact of this increase until that amount has been exhausted, which is expected to take approximately two years. Additionally, the Commission is holding approximately $6 million to $7 million of the customer rate credit for use toward a possible new class of customers for certain senior citizens and disabled persons.  The DCPSC also held that Pepco's bill stabilization adjustment, which decouples distribution revenues from utility customers from the amount of electricity delivered, will continue to be in place and that no refund of previously collected funds is required.  Several parties filed requests that the DCPSC reconsider the order on various issues, and on October 6, 2017, the Commission issued an order denying each of the requests.
District of Columbia Power Line Undergrounding Initiative (Exelon, PHI and Pepco). The District of Columbia government enacted on an emergency basis (effective May 17, 2017) and thereafter on a permanent basis (effective July 11, 2017) legislation to amend the Electric Company Infrastructure Improvement Financing Act of 2014 (as amended) (the Infrastructure Improvement Financing Act) to authorize the District of Columbia Power Line Undergrounding (DC PLUG) initiative, a projected six year, $500 million project to place underground some of the District of Columbia’s most outage-prone power lines with $250 million of the project costs funded by Pepco and $250 million funded by the District of Columbia.
The $250 million of project costs funded by Pepco will be recovered through a volumetric surcharge on the electric bill of substantially all of Pepco's customers in the District of Columbia. Pepco will earn a return on these project costs.
The $250 million of project costs funded by the District of Columbia will come from two sources. Project costs of $187.5 million will be funded through a charge assessed on Pepco by the District of Columbia; Pepco will recover this charge from customers through a volumetric distribution rider. The remaining costs up to $62.5 million are to be funded by the existing capital projects program of the District Department of Transportation (DDOT). Ownership and responsibility for the operation and maintenance of all the assets funded by the District of Columbia will be transferred to Pepco for a nominal amount upon completion. Pepco will not recover or earn a return on the cost of the assets transferred to it by the District of Columbia.
In accordance with the Infrastructure Improvement Financing Act, Pepco filed an application for approval of the first two-year portion of the DC PLUG initiative (the First Biennial Plan) on July 3, 2017. After the initial application, Pepco will be required to make two updated applications, one every two years until the project is completed. Pepco anticipates that the DCPSC will issue an order approving the First Biennial Plan in early November 2017. Upon the issuance of a DCPSC order approving the First Biennial Plan, Pepco will become obligated to pay $187.5 million to the District of Columbia over the six year project term, at which time it will record an obligation and offsetting regulatory asset.
New Jersey Regulatory Matters
New Jersey Consolidated Tax Adjustment (Exelon, PHI and ACE). The Consolidated Tax Adjustment (CTA) is a New Jersey ratemaking policy that requires utilities that are part of a consolidated tax group to share with customers the tax benefits that came from losses at unregulated affiliates through a reduction in rate base. In 2013, the NJBPU opened a generic proceeding to review the policy. In 2014, the NJBPU issued a decision which retained the CTA, but in a highly modified format that significantly reduced the impact of the CTA to ACE. On September 18, 2017, the Appellate Division of the Superior Court of New Jersey reversed the NJBPU’s decision in adopting the revised CTA policy and held that NJBPU’s actions related to the CTA constituted a rulemaking that should have been undertaken pursuant to the requirements of the Administrative Procedures Act. The Court did not address the merits of the CTA methodology itself. No party filed an appeal of the Court’s decision, and the NJBPU is expected to conduct further proceedings. If the NJBPU were to apply the CTA in its unmodified form, it could have a material prospective impact to ACE through a reduction in rate base in future rate cases.
2017 Electric Distribution Rates (Exelon, PHI and ACE). On March 30, 2017, ACE filed an application with the NJBPU to increase its annual electric distribution rates by $70 million (before New Jersey sales and use tax), which was updated to $73 million on July 14, 2017, reflecting a requested ROE of 10.1%. The application also requests approval of a rate surcharge mechanism called the “System Renewal Recovery Charge,” which would permit more timely recovery of certain costs associated with reliability and system renewal-related capital investments. 
On September 8, 2017, ACE entered into a settlement agreement with the NJBPU staff, the New Jersey Division of Rate Counsel and Wal-Mart Stores, Inc. in its electric distribution rate proceeding, which provides for an increase in ACE annual electric distribution base rates of $43 million (before New Jersey sales and use tax) reflecting a ROE of 9.6%.  In addition, pursuant to the settlement agreement, ACE agreed to withdraw its request for approval of a System Renewal Recovery Charge without prejudice to its right to refile.  On September 22, 2017, the NJBPU issued an order approving the settlement agreement, with the new rates effective on October 1, 2017.
2016 Electric Distribution Rates (Exelon, PHI and ACE). On August 24, 2016, the NJBPU issued an order approving a stipulation of settlement among ACE, the New Jersey Division of Rate Counsel, NJBPU Staff and Unimin Corporation, which, among other things, provided that a determination on ACE's grid resiliency program, PowerAhead, would be separated into a phase II of the rate proceeding and decided at a later date. PowerAhead includes capital investments to enhance the resiliency of the system through improvements focused on improving the distribution system's ability to withstand major storm events. A stipulation of settlement with respect to the PowerAhead program (the PowerAhead Stipulation) was approved by the NJBPU on May 31, 2017. As adopted, the PowerAhead program includes an approved investment level of $79 million to be recovered through the cost recovery mechanism described in the PowerAhead Stipulation. The NJBPU order adopting the PowerAhead Stipulation was effective on June 10, 2017.
Update and Reconciliation of Certain Under-Recovered Balances (Exelon, PHI and ACE). On February 1, 2017, ACE submitted its 2017 annual petition with the NJBPU seeking to reconcile and update (i) charges related to the recovery of above-market costs associated with ACE’s long-term power purchase contracts with the non-utility generators and (ii) costs related to surcharges for the New Jersey Societal Benefit Program (a statewide public interest program that is intended to benefit low income customers and address other public policy goals) and ACE’s uncollectible accounts. As filed, the net impact of adjusting the charges as proposed would have been an overall annual rate decrease of approximately $29 million (revised to approximately $32 million in April 2017, based upon an update for actuals through March 2017), including New Jersey sales and use tax. On May 31, 2017, the NJBPU approved a stipulation of settlement entered into by the parties providing for an overall annual rate decrease of approximately $32 million, effective June 1, 2017. The rate decrease was placed into effect provisionally, subject to a review by NJBPU and the Division of Rate Counsel of the final underlying costs for reasonableness and prudence. This rate decrease will have no effect on ACE’s operating income, since these revenues provide for recovery of deferred costs under an approved deferral mechanism. The matter is pending at the NJBPU.
New York Regulatory Matters
New York Clean Energy Standard (Exelon and Generation). On August 1, 2016, the New York Public Service Commission (NYPSC) issued an order establishing the New York CES, a component of which is the Tier 3 ZEC program targeted at preserving the environmental attributes of zero-emissions nuclear-powered generating facilities that meet the criteria demonstrating public necessity as determined by the NYPSC.  The New York State Energy Research and Development Authority (NYSERDA) will centrally procure the ZECs from eligible plants through a 12-year contract, to be administered in six two-year tranches, extending from April 1, 2017 through March 31, 2029. ZEC payments will be made to the eligible resources based upon the number of MWh produced, subject to specified caps and minimum performance requirements.  The price to be paid for the ZECs under each tranche will be administratively determined using a formula based on the social cost of carbon as determined in 2016 by the federal government, subject to pricing adjustments designed to lower the ZEC price based on increase in underlying energy and capacity prices.  The ZEC price for the first tranche has been set at $17.48 per MWh of production. Following the first tranche, the price will be updated bi-annually.  Each Load Serving Entity (LSE) shall be required to purchase an amount of ZECs equivalent to its load ratio share of the total electric energy in the New York Control Area.  Cost recovery from ratepayers shall be incorporated into the commodity charges on customer bills.
The NYPSC initially identified three plants eligible for the ZEC program: the FitzPatrick, Ginna, and Nine Mile Point nuclear facilities. As issued, the order also provided that the duration of the program beyond the first tranche was conditional upon a buyer purchasing the FitzPatrick facility and taking title prior to September 1, 2018. On November 18, 2016, the required contracts with NYSERDA were executed for Ginna and Nine Mile Point, in addition to Entergy’s execution of the required contract for the FitzPatrick facility. On March 31, 2017, Generation closed on the acquisition of FitzPatrick. Generation is currently recognizing revenue for the sale of New York ZECs in the month following generation when the ZECs are transferred to NYSERDA. For the three and nine months ended September 30, 2017, Generation has recognized $118 million and $191 million of ZEC revenue.
Several parties filed with the NYPSC requests for rehearing or reconsideration of the New York CES. Generation and CENG also filed a request for clarification, or in the alternative limited rehearing, that the condition limiting the duration of the program beyond the first tranche be limited to the eligibility of the FitzPatrick plant only and have no bearing on Ginna or Nine Mile Point’s eligibility for the full 12-year duration. On December 15, 2016, the NYPSC approved Generation’s and CENG's petition to clarify this condition and denied all petitions for rehearing of the New York CES. Parties had until mid-April to appeal to New York State court the denials of the requests for rehearing. A Petition seeking to invalidate the ZEC program was filed in New York State court by certain environmental groups and other parties on November 30, 2016, and amended on January 13, 2017, arguing that the NYPSC did not have authority to establish the program and that it violated certain technical provisions of the State Administrative Procedures Act (SAPA) when adopting the ZEC program. On February 15, 2017, Generation and CENG filed a motion to dismiss the state court action. The NYPSC also filed a motion to dismiss the state court action. On March 24, 2017, the plaintiffs filed a memorandum of law opposing the motions to dismiss, and Generation and CENG filed a reply brief on April 28, 2017. Oral argument was held on June 19, 2017. The motions to dismiss are pending.
On October 19, 2016, a coalition of fossil generation companies filed a complaint in federal district court against the NYPSC alleging that the ZEC program violates certain provisions of the U.S. Constitution; specifically that the ZEC program interferes with FERC’s jurisdiction over wholesale rates and that it discriminates against out of state competitors.  On December 9, 2016, Generation and CENG filed a motion to intervene in the case and to dismiss the lawsuit. The State also filed a motion to dismiss. Oral argument was held on March 29, 2017. On July 25, 2017, the court granted both motions to dismiss. On August 24, 2017, plaintiffs appealed the decision to the Second Circuit. Plaintiffs-Appellants’ initial brief was filed on October 13, 2017. The state’s and Exelon’s briefs are due on November 17, 2017. Reply briefs are due on December 1, 2017.
Other legal challenges remain possible, the outcomes of which remain uncertain. See Note 7 - Early Nuclear Plant Retirements for additional information relative to Ginna and Nine Mile Point. See Note 4 - Mergers, Acquisitions and Dispositions for additional information on Generation's acquisition of FitzPatrick.
Ginna Nuclear Power Plant Reliability Support Services Agreement (Exelon and Generation). In November 2014, in response to a petition filed by Ginna Nuclear Power Plant (Ginna) regarding the possible retirement of Ginna, the NYPSC directed Ginna and Rochester Gas & Electric Company (RG&E) to negotiate a Reliability Support Services Agreement (RSSA) to support the continued operation of Ginna to maintain the reliability of the RG&E transmission grid for a specified period of time. During 2015 and 2016, Ginna and RG&E made filings with the NYPSC and FERC for their approval of the proposed RSSA. Although the RSSA was still subject to regulatory approvals, on April 1, 2015, Ginna began delivering the power and capacity from the Ginna plant into the ISO-NY consistent with the technical provisions of the RSSA.
On March 22, 2016, Ginna submitted a compliance filing with FERC with revisions to the RSSA requested by FERC. On April 8, 2016, FERC accepted the compliance filing and on April 20, 2016, the NYPSC accepted the revised RSSA with a term expiring on March 31, 2017. In April 2016, Generation began recognizing revenue based on the final approved pricing contained in the RSSA and also recognized a one-time revenue adjustment of approximately $101 million representing the net cumulative previously unrecognized amount of revenue retroactive from the April 1, 2015 effective date through March 31, 2016. A 49.99% portion of the one-time adjustment was removed from Generation’s results of operations as a result of the noncontrolling interests in CENG.
The RSSA required Ginna to continue operating through the RSSA term. On September 30, 2016, Ginna filed the required notice with the NYPSC of its intent to continue operating beyond the March 31, 2017 expiry of the RSSA, conditioned upon successful execution of an agreement between Ginna and NYSERDA for the sale of ZECs under the New York CES. As stated previously, on November 18, 2016 the required contract with NYSERDA was executed by Generation and CENG for Ginna. Upon the expiry of the RSSA on March 31, 2017, Ginna was required to make refund payments of $20 million to RG&E related to capital expenditures. Ginna paid RG&E the $20 million in June 2017. Additionally, the provisions of the RSSA provided for a one-time payment of $12 million to be paid from RG&E to Ginna at the end of the contract. This $12 million was recognized in revenue as of March 31, 2017. RG&E paid the $12 million to Ginna in May 2017. Subject to prevailing over any administrative or legal challenges, it is expected the New York CES will allow Ginna to continue to operate through the end of its current operating license in 2029. See Note 7-Early Nuclear Plant Retirements for further information regarding the impacts of a decision to early retire one or more nuclear plants.
Federal Regulatory Matters
Transmission Formula Rate (Exelon, ComEd, BGE, Pepco, DPL and ACE). The following total increases/(decreases) were included in ComEd’s, BGE’s, Pepco's, DPL's and ACE's 2017 annual electric transmission formula rate filings:
 
2017
Annual Transmission Filings(a)
ComEd
 
BGE
 
Pepco
 
DPL
 
ACE
Initial revenue requirement
    increase
$
44

 
$
31

 
$
5

 
$
6

 
$
20

Annual reconciliation (decrease) increase
(33
)
 
3

 
15

 
8

 
22

Dedicated facilities decrease(b)

 
(8
)
 

 

 

Total revenue requirement increase
$
11

 
$
26

 
$
20

 
$
14

 
$
42

 
 
 
 
 
 
 
 
 
 
Allowed return on rate base(c)
8.43
%
 
7.47
%
 
7.92
%
 
7.16
%
 
8.02
%
Allowed ROE(d)
11.50
%
 
10.50
%
 
10.50
%
 
10.50
%
 
10.50
%
_________
(a)
All rates are effective June 2017, subject to review by the FERC and other parties, which is due by fourth quarter 2017.
(b)
BGE's transmission revenues include a FERC approved dedicated facilities charge to recover the costs of providing transmission service to specifically designated load by BGE.
(c)
Represents the weighted average debt and equity return on transmission rate bases.
(d)
As part of the FERC-approved settlement of ComEd’s 2007 transmission rate case, the rate of return on common equity is 11.50% and the common equity component of the ratio used to calculate the weighted average debt and equity return for the transmission formula rate is currently capped at 55%. As part of the FERC-approved settlement of the ROE complaint against BGE, Pepco, DPL and ACE, the rate of return on common equity is 10.50%, inclusive of a 50 basis point incentive adder for being a member of a regional transmission organization.
For additional information regarding transmission formula rate filings see Note 3Regulatory Matters of the Exelon 2016 Form 10-K.
Transmission Formula Rate (Exelon and PECO). On May 1, 2017, PECO filed a request with FERC seeking approval to update its transmission rates and change the manner in which PECO’s transmission rate is determined from a fixed rate to a formula rate. The formula rate would be updated annually to ensure that under this rate customers pay the actual costs of providing transmission services. The formula rate filing includes a requested increase of $22 million to PECO’s annual transmission revenues and a requested rate of return on common equity of 11%, inclusive of a 50 basis point adder for being a member of a regional transmission organization. PECO requested that the new transmission rate be effective as of July 2017. On June 27, 2017, FERC issued an Order accepting the filing and suspending the proposed rates until December 1, 2017, subject to refund, and set the matter for hearing and settlement judge procedures.  PECO cannot predict the final outcome of the settlement or hearing proceedings, or the transmission formula FERC may approve.
PJM Transmission Rate Design and Operating Agreements (Exelon, Generation, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE). PJM Transmission Rate Design specifies the rates for transmission service charged to customers within PJM. Currently, ComEd, PECO, BGE, Pepco, DPL and ACE incur costs based on the existing rate design, which charges customers based on the cost of the existing transmission facilities within their load zone and the cost of new transmission facilities based on those who benefit from those facilities. In April 2007, FERC issued an order concluding that PJM’s current rate design for existing facilities is just and reasonable and should not be changed. In the same order, FERC held that the costs of new facilities 500 kV and above should be socialized across the entire PJM footprint and that the costs of new facilities less than 500 kV should be allocated to the customers of the new facilities who caused the need for those facilities. A number of parties appealed to the U.S. Court of Appeals for the Seventh Circuit for review of the decision.
In August 2009, the court issued its decision affirming the FERC’s order with regard to the existing facilities, but remanded to FERC the issue of the cost allocation associated with the new facilities 500 kV and above (Cost Allocation Issue) for further consideration by the FERC. On remand, FERC reaffirmed its earlier decision to socialize the costs of new facilities 500 kV and above. A number of parties filed appeals of these orders. In June 2014, the court again remanded the Cost Allocation Issue to FERC. On December 18, 2014, FERC issued an order setting an evidentiary hearing and settlement proceeding regarding the Cost Allocation Issue. On June 15, 2016, a number of parties, including Exelon and the Utility Registrants, filed a proposed Settlement with FERC.  If the Settlement is approved, 50% of the costs of the 500 kV and above facilities approved by the PJM Board on or before February 1, 2013 will be socialized across PJM and 50% will be allocated according to a formula that calculates the flows on the transmission facilities.  Each state that is a party in this proceeding either signed, or did not oppose, the settlement.  The Settlement is opposed by a number of merchant transmission owners and New York load-serving entities. The Settlement includes provisions for monthly credits or charges that are expected to be mostly refunded or recovered through customer rates over a 10-year period based on negotiated numbers for charges prior to January 1, 2016.
Exelon expects that the Settlement will not have a material impact on the results of operations, cash flows and financial position of Generation, ComEd, PECO, BGE, Pepco, DPL or ACE. The Settlement is subject to approval by FERC.
DOE Notice of Proposed Rulemaking (Exelon and Generation).  On August 23, 2017, the DOE released its report on the reliability of the electric grid. One aspect of the wide-ranging report is the DOE’s recognition that the electricity markets do not currently value the resiliency provided by baseload generation, such as nuclear plants. On September, 28, 2017, the DOE issued a Notice of Proposed Rulemaking (NOPR) that would entitle certain eligible resilient generating units (i.e., those located in organized markets, with a 90-day supply of fuel on site, not already subject to state cost of service regulation and satisfying certain other requirements) to recover fully allocated costs and earn a fair return on equity on their investment. The DOE issued the NOPR under an infrequently-used section of the DOE Organization Act under which the FERC has exclusive jurisdiction to consider and take any final action related to NOPRs proposed by the DOE. The DOE NOPR recommended that the FERC take comments for 45 days after publication in the Federal Register and issue a final order 60 days after such publication.  On October 2, 2017, the FERC issued a notice inviting comments regarding the DOE NOPR within 21 days and established a new docket wherein the FERC will consider the matter. On October 23, 2017, Exelon filed comments with the FERC, supporting the goals of the NOPR and urging the agency to take swift action to protect customers from power supply interruptions and ensure resiliency in a way that appropriately balances the value and cost to customers.  Exelon cannot predict the final outcome of the proceeding or its potential impact, if any, on Exelon or Generation.
Complaints at FERC Seeking to Mitigate Illinois and New York Programs Providing ZECs (Exelon and Generation). PJM and NYISO capacity markets include a Minimum Offer Price Rule (MOPR) that is intended to preclude buyers from exercising buyer market power. If a resource is subjected to a MOPR, its offer is adjusted to remove the revenues it receives through a federal, state or other government-provided financial support program - resulting in a higher offer that may not clear the capacity market. Currently, the MOPRs in PJM and NYISO apply only to certain new resources. Exelon has generally opposed policies that require subsidies or give preferential treatment to generation providers or technologies that do not provide superior reliability or environmental benefits, or that would threaten the reliability and value of the integrated electricity grid. Thus, Exelon has supported a MOPR as a means of minimizing the detrimental impact certain subsidized resources could have on capacity markets (such as the New Jersey (LCAPP) and Maryland (CfD) programs). However, in Exelon’s view, MOPRs should not be applied to resources that receive compensation for providing superior reliability or environmental benefits.
On January 9, 2017, the Electric Power Supply Association (EPSA) filed two requests with FERC: one seeking to amend a prior complaint against PJM and another seeking expedited action on a pending NYISO compliance filing in an existing proceeding. Both filings allege that the relevant MOPR should be expanded to also apply to existing resources receiving ZEC compensation under the New York CES and Illinois ZES programs. The EPSA parties have filed motions to expedite both proceedings. Exelon has filed protests at FERC in response to each filing, arguing generally that ZEC payments provide compensation for an environmental attribute that is distinct from the energy and capacity sold in the FERC-jurisdictional markets, and therefore, are no different than other renewable support programs like the PTC and RPS that have generally not been subject to a MOPR. However, if successful, for Generation's facilities in NYISO and PJM expected to receive ZEC compensation (Quad Cities, Ginna, Nine Mile Point and FitzPatrick), an expanded MOPR could require exclusion of ZEC compensation when bidding into future capacity auctions such that these facilities would have an increased risk of not clearing in those auctions and thus no longer receiving capacity revenues during the respective ZEC programs. Any such mitigation of these generating resources could have a material effect on Exelon’s and Generation’s future cash flows and results of operations. On August 30, 2017, EPSA filed motions to lodge the district court decisions dismissing the complaints and urging FERC to act expeditiously on its requests to expand the MOPR. On September 14, 2017, Exelon filed a response in each docket noting that it does not oppose the motions to lodge but arguing that the requests to expedite a decision on the requests to expand the MOPR have no merit. The timing of FERC’s decision with respect to both proceedings is currently unknown and the outcome of these matters is currently uncertain.
Operating License Renewals (Exelon and Generation). On August 29, 2012, Generation submitted a hydroelectric license application to FERC for a 46-year license for the Conowingo Hydroelectric Project (Conowingo). In connection with Generation’s efforts to obtain a water quality certification pursuant to Section 401 of the Clean Water Act with Maryland Department of the Environment (MDE) for Conowingo, Generation continues to work with MDE and other stakeholders to resolve water quality licensing issues, including: (1) water quality, (2) fish habitat, and (3) sediment. In addition, Generation continues to work with MDE and other Federal and Maryland state agencies to conduct and fund an additional sediment and nutrient monitoring study.
On April 21, 2016, Exelon and Interior executed a Settlement Agreement resolving all fish passage issues between the parties. The financial impact of the Settlement Agreement is estimated to be $3 million to $7 million per year, on average, over the 46-year life of the new license, including both capital and operating costs. The actual timing and amount of these costs are not currently fixed and may vary significantly from year to year throughout the life of the new license. Resolution of the remaining issues relating to Conowingo involving various stakeholders may have a material effect on Exelon’s and Generation’s results of operations and financial position through an increase in capital expenditures and operating costs. As of September 30, 2017, $30 million of direct costs associated with Conowingo licensing efforts have been capitalized. See Note 3 - Regulatory Matters of the Exelon 2016 Form 10-K for additional information on Generation's operating license renewal efforts.
Regulatory Assets and Liabilities (Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE)
Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE each prepare their consolidated financial statements in accordance with the authoritative guidance for accounting for certain types of regulation. Under this guidance, regulatory assets represent incurred costs that have been deferred because of their probable future recovery from customers through regulated rates. Regulatory liabilities represent the excess recovery of costs or accrued credits that have been deferred because it is probable such amounts will be returned to customers through future regulated rates or represent billings in advance of expenditures for approved regulatory programs.
As a result of applying the acquisition method of accounting and pushing it down to the consolidated financial statements of PHI, certain regulatory assets and liabilities were established at Exelon and PHI to offset the impacts of fair valuing the acquired assets and liabilities assumed which are subject to regulatory recovery. In total, Exelon and PHI recorded a net $2.4 billion regulatory asset reflecting adjustments recorded as a result of the acquisition method of accounting. See Note 4Mergers, Acquisitions and Dispositions for additional information.
The following tables provide information about the regulatory assets and liabilities of Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE as of September 30, 2017 and December 31, 2016. For additional information on the specific regulatory assets and liabilities, refer to Note 3Regulatory Matters of the Exelon 2016 Form 10-K.
 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
September 30, 2017
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Regulatory assets
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pension and other postretirement benefits(a)
$
4,020

 
$

 
$

 
$

 
$

 
$

 
$

 
$

Deferred income taxes(b)
2,423

 
347

 
1,678

 
100

 
298

 
195

 
45

 
58

AMI programs
660

 
159

 
40

 
219

 
242

 
163

 
79

 

Under-recovered distribution service costs(c)
256

 
256

 

 

 

 

 

 

Energy efficiency costs
78

 
78

 

 

 

 

 

 

Debt costs
120

 
38

 
1

 
12

 
75

 
16

 
8

 
5

Fair value of long-term debt
773

 

 

 

 
632

 

 

 

Fair value of PHI's unamortized energy contracts
830

 

 

 

 
830

 

 

 

Severance
2

 

 

 
2

 

 

 

 

Asset retirement obligations
108

 
73

 
22

 
13

 

 

 

 

MGP remediation costs
300

 
277

 
23

 

 

 

 

 

Under-recovered uncollectible accounts
70

 
60

 

 

 
10

 

 

 
10

Renewable energy
277

 
277

 

 

 

 

 

 

Energy and transmission programs (d)(e)(f)(g)(h)(i)
65

 
3

 

 
26

 
36

 
6

 
9

 
21

Deferred storm costs
31

 

 

 

 
31

 
9

 
5

 
17

Electric generation-related regulatory asset
3

 

 

 
3

 

 

 

 

Energy efficiency and demand response programs
599

 

 
1

 
284

 
314

 
233

 
81

 

Merger integration costs(j)(k)(l)(m)
47

 

 

 
7

 
40

 
20

 
11

 
9

Under-recovered revenue decoupling(n)
72

 

 

 
34

 
38

 
33

 
5

 

COPCO acquisition adjustment
6

 

 

 

 
6

 

 
6

 

Workers compensation and long-term disability cost
33

 

 

 

 
33

 
33

 

 

Vacation accrual
38

 

 
14

 

 
24

 

 
14

 
10

Securitized stranded costs
93

 

 

 

 
93

 

 

 
93

CAP arrearage
9

 

 
9

 

 

 

 

 

Removal costs
518

 

 

 

 
518

 
144

 
98

 
277

Other
71

 
6

 
21

 
5

 
40

 
28

 
8

 
4

Total regulatory assets
11,502

 
1,574

 
1,809

 
705

 
3,260

 
880

 
369

 
504

Less: current portion
1,264

 
187

 
36

 
208

 
568

 
181

 
69

 
87

Total noncurrent regulatory assets
$
10,238

 
$
1,387

 
$
1,773

 
$
497

 
$
2,692

 
$
699

 
$
300

 
$
417

 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
September 30, 2017
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Regulatory liabilities
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Other postretirement benefits
$
41

 
$

 
$

 
$

 
$

 
$

 
$

 
$

Nuclear decommissioning
2,971

 
2,438

 
533

 

 

 

 

 

Removal costs
1,588

 
1,337

 

 
119

 
132

 
22

 
110

 

Deferred rent
37

 

 

 

 
37

 

 

 

Energy efficiency and demand response programs
62

 
33

 
29

 

 

 

 

 

DLC program costs
8

 

 
8

 

 

 

 

 

Electric distribution tax repairs
50

 

 
50

 

 

 

 

 

Gas distribution tax repairs
14

 

 
14

 

 

 

 

 

Energy and transmission programs (d)(e)(f)(g)(h)(i)
139

 
54

 
68

 

 
17

 
3

 
9

 
5

Renewable portfolio standards costs
46

 
46

 

 

 

 

 

 

Zero emission credit costs
71

 
71

 

 

 

 

 

 

Other
75

 
5

 
17

 
28

 
25

 
1

 
9

 
13

Total regulatory liabilities
5,102

 
3,984

 
719

 
147

 
211

 
26

 
128

 
18

Less: current portion
553

 
249

 
159

 
63

 
65

 
5

 
42

 
18

Total noncurrent regulatory liabilities
$
4,549

 
$
3,735

 
$
560

 
$
84

 
$
146

 
$
21

 
$
86

 
$

 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
December 31, 2016
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Regulatory assets
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pension and other postretirement benefits (a)
$
4,162

 
$

 
$

 
$

 
$

 
$

 
$

 
$

Deferred income taxes (b)
2,016

 
75

 
1,583

 
98

 
260

 
171

 
38

 
51

AMI programs
701

 
164

 
49

 
230

 
258

 
174

 
84

 

Under-recovered distribution service costs (c)
188

 
188

 

 

 

 

 

 

Debt costs
124

 
42

 
1

 
7

 
81

 
17

 
9

 
6

Fair value of long-term debt
812

 

 

 

 
671

 

 

 

Fair value of PHI's unamortized energy contracts
1,085

 

 

 

 
1,085

 

 

 

Severance
5

 

 

 
5

 

 

 

 

Asset retirement obligations
111

 
76

 
23

 
12

 

 

 

 

MGP remediation costs
305

 
278

 
26

 
1

 

 

 

 

Under-recovered uncollectible accounts
56

 
56

 

 

 

 

 

 

Renewable energy
260

 
258

 

 

 
2

 

 

 
2

Energy and transmission programs (d)(e)(f)(g)(h)(i)
89

 
23

 

 
38

 
28

 
6

 
5

 
17

Deferred storm costs
36

 

 

 
1

 
35

 
12

 
5

 
18

Electric generation-related regulatory asset
10

 

 

 
10

 

 

 

 

Rate stabilization deferral
7

 

 

 
7

 

 

 

 

Energy efficiency and demand response programs
621

 

 
1

 
285

 
335

 
250

 
85

 

Merger integration costs(j)(k)(l)(m)
25

 

 

 
10

 
15

 
11

 
4

 

Under-recovered revenue decoupling(n)
27

 

 

 
3

 
24

 
21

 
3

 

COPCO acquisition adjustment
8

 

 

 

 
8

 

 
8

 

Workers compensation and long-term disability costs
34

 

 

 

 
34

 
34

 

 

Vacation accrual
31

 

 
7

 

 
24

 

 
14

 
10

Securitized stranded costs
138

 

 

 

 
138

 

 

 
138

CAP arrearage
11

 

 
11

 

 

 

 

 

Removal costs
477

 

 

 

 
477

 
134

 
88

 
255

Other
49

 
7

 
9

 
5

 
29

 
22

 
5

 
4

Total regulatory assets
11,388

 
1,167

 
1,710

 
712

 
3,504

 
852

 
348

 
501

Less: current portion
1,342

 
190

 
29

 
208

 
653

 
162

 
59

 
96

Total noncurrent regulatory assets
$
10,046

 
$
977

 
$
1,681

 
$
504

 
$
2,851

 
$
690

 
$
289

 
$
405

 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
December 31, 2016
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Regulatory liabilities
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Other postretirement benefits
$
47

 
$

 
$

 
$

 
$

 
$

 
$

 
$

Nuclear decommissioning
2,607

 
2,169

 
438

 

 

 

 

 

Removal costs
1,601

 
1,324

 

 
141

 
136

 
18

 
118

 

Deferred rent
39

 

 

 

 
39

 

 

 

Energy efficiency and demand response programs
185

 
141

 
41

 

 
3

 
3

 

 

DLC program costs
8

 

 
8

 

 

 

 

 

Electric distribution tax repairs
76

 

 
76

 

 

 

 

 

Gas distribution tax repairs
20

 

 
20

 

 

 

 

 

Energy and transmission programs (d)(e)(f)(g)(h)(i)
134

 
60

 
56

 

 
18

 
8

 
5

 
5

Other
72

 
4

 
5

 
19

 
41

 
2

 
17

 
20

Total regulatory liabilities
4,789

 
3,698

 
644

 
160

 
237

 
31

 
140

 
25

Less: current portion
602

 
329

 
127

 
50

 
79

 
11

 
43

 
25

Total noncurrent regulatory liabilities
$
4,187

 
$
3,369

 
$
517

 
$
110

 
$
158

 
$
20

 
$
97

 
$

_________
(a)
As of September 30, 2017 and December 31, 2016, the pension and other postretirement benefits regulatory asset at Exelon includes regulatory assets of $969 million and $995 million, respectively, as a result of the PHI Merger related to unrecognized costs that are probable of regulatory recovery. The regulatory assets are amortized over periods from 3 to 15 years, depending on the underlying component. Pepco, DPL and ACE are currently recovering these costs through base rates. Pepco, DPL and ACE are not earning a return on the recovery of these costs in base rates.
(b)
As of September 30, 2017, includes transmission-related income tax regulatory assets that require FERC approval separate from the transmission formula rate of $73 million, $42 million, $34 million, $23 million and $21 million for ComEd, BGE, Pepco, DPL and ACE, respectively. As of December 31, 2016, includes transmission-related regulatory assets that require FERC approval separate from the transmission formula rate of $22 million, $38 million, $31 million, $20 million and $19 million for ComEd, BGE, Pepco, DPL and ACE, respectively. On December 13, 2016, BGE filed with FERC to begin recovering these existing and any similar future regulatory assets through its transmission formula rate. On May 9, 2017, FERC accepted BGE’s filing and made effective BGE’s proposed modifications to its transmission formula rate, subject to refund and further Commission order. ComEd, Pepco, DPL, and ACE are expected to make similar filings with FERC and other parties in subsequent periods.
(c)
As of September 30, 2017, ComEd’s regulatory asset of $256 million was comprised of $200 million for the 2015 - 2017 annual reconciliations and $56 million related to significant one-time events including $11 million of deferred storm costs, $7 million of Constellation and PHI merger and integration related costs, $6 million of emerald ash borer costs, and $32 million of smart meter related costs.  As of December 31, 2016, ComEd’s regulatory asset of $188 million was comprised of $134 million for the 2015 and 2016 annual reconciliations and $54 million related to significant one-time events, including $20 million of deferred storm costs and $11 million of Constellation and PHI merger and integration related costs, and $23 million of smart meter related costs. See Note 4Mergers, Acquisitions and Dispositions of the Exelon 2016 Form 10-K for further information.
(d)
As of September 30, 2017, ComEd’s regulatory liability of $54 million included $22 million related to over-recovered energy costs and $32 million associated with revenues received for renewable energy requirements. As of December 31, 2016, ComEd’s regulatory asset of $23 million included $15 million associated with transmission costs recoverable through its FERC approved formula rate and $8 million of Constellation merger and integration costs to be recovered upon FERC approval. As of December 31, 2016, ComEd’s regulatory liability of $60 million included $30 million related to over-recovered energy costs and $30 million associated with revenues received for renewable energy requirements.
(e)
As of September 30, 2017, PECO's regulatory liability of $68 million included $34 million related to over-recovered costs under the DSP program, $21 million related to the over-recovered natural gas costs under the PGC and $13 million related to over-recovered non-bypassable transmission service charges. As of December 31, 2016, PECO's regulatory liability of $56 million included $34 million related to over-recovered costs under the DSP program, $10 million related to over-recovered non-bypassable transmission service charges, $8 million related to the over-recovered natural gas costs under the PGC and $4 million related to the over-recovered electric transmission costs.
(f)
As of September 30, 2017, BGE's regulatory asset of $26 million included $5 million related to under-recovered electric energy costs, $14 million related to under-recovered natural gas costs, $3 million of costs associated with transmission costs recoverable through its FERC approved formula rate and $4 million of abandonment costs to be recovered upon FERC approval. As of December 31, 2016, BGE’s regulatory asset of $38 million included $4 million of costs associated with transmission costs recoverable through its FERC approved formula rate, $28 million related to under-recovered electric energy costs, $3 million of abandonment costs to be recovered upon FERC approval, and $3 million of under-recovered natural gas costs.
(g)
As of September 30, 2017, Pepco's regulatory asset of $6 million included $3 million of transmission costs recoverable through its FERC approved formula rate and $3 million of under-recovered electric energy costs. As of September 30, 2017, Pepco's regulatory liability of $3 million related to over-recovered electric energy costs. As of December 31, 2016, Pepco's regulatory asset of $6 million related to under-recovered electric energy costs. As of December 31, 2016, Pepco's regulatory liability of $8 million included $5 million of over-recovered transmission costs and $3 million of over-recovered electric energy costs.
(h)
As of September 30, 2017, DPL's regulatory asset of $9 million included $4 million of transmission costs recoverable through its FERC approved formula rate and $5 million related to under-recovered electric energy costs. As of September 30, 2017, DPL's regulatory liability of $9 million related to over-recovered electric energy costs. As of December 31, 2016, DPL's regulatory asset of $5 million included $1 million of transmission costs recoverable through its FERC approved formula rate and $4 million of under-recovered electric energy costs. As of December 31, 2016, DPL's regulatory liability of $5 million included $2 million of over-recovered electric energy costs and $3 million of over-recovered transmission costs.
(i)
As of September 30, 2017, ACE's regulatory asset of $21 million included $11 million of transmission costs recoverable through its FERC approved formula rate and $10 million of under-recovered electric energy costs. As of September 30, 2017, ACE's regulatory liability of $5 million related to over-recovered electric energy costs. As of December 31, 2016, ACE's regulatory asset of $17 million included $6 million of transmission costs recoverable through its FERC approved formula rate and $11 million of under-recovered electric energy costs. As of December 31, 2016, ACE's regulatory liability of $5 million included $4 million of over-recovered transmission costs and $1 million of over-recovered electric energy costs.
(j)
As of September 30, 2017 and December 31, 2016, BGE's regulatory asset of $7 million and $10 million, respectively, included $5 million and $6 million, respectively, of previously incurred PHI acquisition costs as authorized by the June 2016 rate case order.
(k)
As of September 30, 2017, Pepco’s regulatory asset of $20 million represents previously incurred PHI acquisition costs, including $11 million authorized for recovery in Maryland and $9 million expected to be recovered in the District of Columbia service territory. As of December 31, 2016, Pepco's regulatory asset of $11 million represents previously incurred PHI acquisition costs authorized for recovery in Maryland. 
(l)
As of September 30, 2017, DPL’s regulatory asset of $11 million represents previously incurred PHI acquisition costs, including $4 million authorized for recovery in Maryland, $5 million authorized for recovery in Delaware electric rates, and $2 million expected to be recovered in electric and gas rates in the Delaware service territory. As of December 31, 2016, DPL's regulatory asset of $4 million represents previously incurred PHI acquisition costs expected to be recovered in the Maryland service territory.
(m)
As of September 30, 2017, ACE’s regulatory asset of $9 million represents previously incurred PHI acquisition costs expected to be recovered in the New Jersey service territory.
(n)
Represents the electric and natural gas distribution costs recoverable from customers under BGE’s decoupling mechanism. As of September 30, 2017, BGE had a regulatory asset of $24 million related to under-recovered electric revenue decoupling and $10 million related to under-recovered natural gas revenue decoupling. As of December 31, 2016, BGE had a regulatory asset of $2 million related to under-recovered natural gas revenue decoupling and $1 million related to under-recovered electric revenue decoupling.
Capitalized Ratemaking Amounts Not Recognized (Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE)
The following table illustrates our authorized amounts capitalized for ratemaking purposes related to earnings on shareholders’ investment that are not recognized for financial reporting purposes on our Consolidated Balance Sheets. These amounts will be recognized as revenues in our Consolidated Statements of Operations and Comprehensive Income in the periods they are billable to our customers.
 
Exelon
 
ComEd(a)
 
PECO
 
BGE(b)
 
PHI
 
Pepco(c)
 
DPL(c)
 
ACE
September 30, 2017
$
71

 
$
7

 
$

 
$
54

 
$
10

 
$
6

 
$
4

 
$

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Exelon
 
ComEd(a)
 
PECO
 
BGE(b)
 
PHI
 
Pepco(c)
 
DPL(c)
 
ACE
December 31, 2016
$
72

 
$
5

 
$

 
$
57

 
$
10

 
$
6

 
$
4

 
$

_________
(a)
Reflects ComEd's unrecognized equity returns earned for ratemaking purposes on its under-recovered distribution services costs regulatory assets.
(b)
BGE's authorized amounts capitalized for ratemaking purposes primarily relate to earnings on shareholders' investment on its AMI Programs.
(c)
Pepco's and DPL's authorized amounts capitalized for ratemaking purposes relate to earnings on shareholders' investment on their respective AMI Programs and Energy Efficiency and Demand Response Programs. The earnings on energy efficiency are on Pepco DC and DPL DE programs only.
Purchase of Receivables Programs (Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE)
ComEd, PECO, BGE, Pepco, DPL and ACE are required, under separate legislation and regulations in Illinois, Pennsylvania, Maryland, District of Columbia and New Jersey, to purchase certain receivables from retail electric and natural gas suppliers that participate in the utilities' consolidated billing. ComEd, BGE, Pepco and DPL purchase receivables at a discount to recover primarily uncollectible accounts expense from the suppliers. PECO is required to purchase receivables at face value and is permitted to recover uncollectible accounts expense, including those from Third Party Suppliers, from customers through distribution rates. ACE purchases receivables at face value. ACE recovers all uncollectible accounts expense, including those from Third Party Suppliers, through the Societal Benefits Charge (SBC) rider, which includes uncollectible accounts expense as a component.  The SBC is filed annually with the NJBPU. Exelon, ComEd, PECO, BGE, PHI, Pepco, DPL and ACE do not record unbilled commodity receivables under the POR programs. Purchased billed receivables are classified in Other accounts receivable, net on Exelon’s, ComEd’s, PECO’s, BGE’s, PHI's, Pepco's, DPL's and ACE's Consolidated Balance Sheets. The following tables provide information about the purchased receivables of those companies as of September 30, 2017 and December 31, 2016.
 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
As of September 30, 2017
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Purchased receivables
$
312

 
$
89

 
$
68

 
$
55

 
$
100

 
$
66

 
$
10

 
$
24

Allowance for uncollectible accounts(a)
(33
)
 
(13
)
 
(5
)
 
(4
)
 
(11
)
 
(6
)
 
(1
)
 
(4
)
Purchased receivables, net
$
279

 
$
76

 
$
63

 
$
51

 
$
89

 
$
60

 
$
9

 
$
20


 
 
 
 
 
 
 
 
 
Successor
 
 
 
 
 
 
As of December 31, 2016
Exelon
 
ComEd
 
PECO
 
BGE
 
PHI
 
Pepco
 
DPL
 
ACE
Purchased receivables
$
313

 
$
87

 
$
72

 
$
59

 
$
95

 
$
63

 
$
10

 
$
22

Allowance for uncollectible accounts(a)
(37
)
 
(14
)
 
(6
)
 
(4
)
 
(13
)
 
(7
)
 
(2
)
 
(4
)
Purchased receivables, net
$
276

 
$
73

 
$
66

 
$
55

 
$
82

 
$
56

 
$
8

 
$
18

_________
(a)
For ComEd, BGE, Pepco and DPL, reflects the incremental allowance for uncollectible accounts recorded, which is in addition to the purchase discount. For ComEd, the incremental uncollectible accounts expense is recovered through its Purchase of Receivables with Consolidated Billing tariff.