Nuclear Decommissioning (Exelon and Generation)
3 Months Ended
Mar. 31, 2017
Environmental Remediation Obligations [Abstract]  
Nuclear Decommissioning (Exelon and Generation)
Nuclear Decommissioning (Exelon and Generation)

Nuclear Decommissioning Asset Retirement Obligations

Generation has a legal obligation to decommission its nuclear power plants following the expiration of their operating licenses. To estimate its decommissioning obligation related to its nuclear generating stations for financial accounting and reporting purposes, Generation uses a probability-weighted, discounted cash flow model which, on a unit-by-unit basis, considers multiple outcome scenarios that include significant estimates and assumptions, and are based on decommissioning cost studies, cost escalation rates, probabilistic cash flow models and discount rates. Generation updates its ARO annually, unless circumstances warrant more frequent updates, based on its review of updated cost studies and its annual evaluation of cost escalation factors and probabilities assigned to various scenarios.

The following table provides a rollforward of the nuclear decommissioning ARO reflected on Exelon’s and Generation’s Consolidated Balance Sheets from December 31, 2016 to March 31, 2017

Nuclear decommissioning ARO at December 31, 2016(a)
$
8,734

Acquisition of FitzPatrick
417

Accretion expense
109

Costs incurred to decommission retired plants
(1
)
Nuclear decommissioning ARO at March 31, 2017(a)(b)
$
9,259

_________
(a)
Includes $11 million and $10 million for the current portion of the ARO at March 31, 2017 and December 31, 2016, respectively, which is included in Other current liabilities on Exelon’s and Generation’s Consolidated Balance Sheets.
(b)
Includes the fair value of the FitzPatrick ARO liability as of March 31, 2017, the date of the acquisition. See Note 4 - Mergers, Acquisitions and Dispositions.

During the three months ended March 31, 2017, Generation’s nuclear ARO increased by approximately $525 million. The increase is largely driven by the acquisition of FitzPatrick. The fair value of FitzPatrick’s assets and liabilities, including the ARO, was determined based on significant estimates and assumptions that are judgmental in nature. The fair value of the ARO is considered an initial estimate and will be updated with inputs from a third party engineering firm with corresponding adjustments recorded by the end of 2017. For additional details on the acquisition of FitzPatrick, see Note 4 - Mergers, Acquisitions and Dispositions.

Nuclear Decommissioning Trust Fund Investments

NDT funds have been established for each generation station unit to satisfy Generation’s nuclear decommissioning obligations. Generally, NDT funds established for a particular unit may not be used to fund the decommissioning obligations of any other unit.

The NDT funds associated with Generation’s nuclear units have been funded with amounts collected from the previous owners and their respective utility customers. PECO is authorized to collect funds, in revenues, for decommissioning the former PECO nuclear plants through regulated rates, and these collections are scheduled through the operating lives of the former PECO plants. The amounts collected from PECO customers are remitted to Generation and deposited into the NDT funds for the unit for which funds are collected. Every five years, PECO files a rate adjustment with the PAPUC that reflects PECO’s calculations of the estimated amount needed to decommission each of the former PECO units based on updated fund balances and estimated decommissioning costs. The rate adjustment is used to determine the amount collectible from PECO customers. On March 31, 2017, PECO filed its Nuclear Decommissioning Cost Adjustment (NDCA) with the PAPUC proposing an annual recovery from customers of approximately $4 million which, if approved by the PAPUC, will be effective January 1, 2018. This amount reflects a decrease from the current approved annual collection of approximately $24 million primarily due to the removal of the collections for Limerick Units 1 and 2 as a result of the NRC approving the extension of the operating licenses for an additional 20 years. See Note 16 - Asset Retirement Obligations of Exelon's 2016 Form 10-K, for information regarding the amount collected from PECO ratepayers for decommissioning costs.

At March 31, 2017 and December 31, 2016, Exelon and Generation had NDT fund investments totaling $12,362 million and $11,061 million, respectively. The increase is primarily driven by the acquisition of FitzPatrick.

The following table provides unrealized gains on NDT funds for the three months ended March 31, 2017 and 2016:

 
Exelon and Generation
 
Three Months Ended 
 March 31,
 
2017
 
2016
Net unrealized gains on decommissioning trust funds — Regulatory Agreement Units(a)
$
222

 
$
79

Net unrealized gains on decommissioning trust funds — Non-Regulatory Agreement Units(b)(c)
166

 
52

 
_________
(a)
Net unrealized gains related to Generation’s NDT funds associated with Regulatory Agreement Units are included in Regulatory liabilities on Exelon’s Consolidated Balance Sheets and Noncurrent payables to affiliates on Generation’s Consolidated Balance Sheets.
(b)
Excludes $(1) million and $2 million of net unrealized gains (losses) related to the Zion Station pledged assets for the three months ended March 31, 2017 and 2016 respectively. Net unrealized gains related to Zion Station pledged assets are included in the Payable for Zion Station decommissioning on Exelon’s and Generation’s Consolidated Balance Sheets.
(c)
Net unrealized gains related to Generation’s NDT funds with Non-Regulatory Agreement Units are included within Other, net in Exelon’s and Generation’s Consolidated Statements of Operations and Comprehensive Income.

Interest and dividends on NDT fund investments are recognized when earned and are included in Other, net in Exelon’s and Generation’s Consolidated Statements of Operations and Comprehensive Income. Interest and dividends earned on the NDT fund investments for the Regulatory Agreement Units are eliminated within Other, net in Exelon’s and Generation’s Consolidated Statement of Operations and Comprehensive Income.

Refer to Note 3Regulatory Matters and Note 27Related Party Transactions of the Exelon 2016 Form 10-K for information regarding regulatory liabilities at ComEd and PECO and intercompany balances between Generation, ComEd and PECO reflecting the obligation to refund to customers any decommissioning-related assets in excess of the related decommissioning obligations.

Zion Station Decommissioning

On September 1, 2010, Generation completed an Asset Sale Agreement (ASA) with EnergySolutions Inc. and its wholly owned subsidiaries, EnergySolutions, LLC (EnergySolutions) and ZionSolutions, under which ZionSolutions has assumed responsibility for completing certain decommissioning activities at Zion Station, which is located in Zion, Illinois and ceased operation in 1998. See Note 16Asset Retirement Obligations of the Exelon 2016 Form 10-K for information regarding the specific treatment of assets, including NDT funds, and decommissioning liabilities transferred in the transaction.

ZionSolutions is subject to certain restrictions on its ability to request reimbursements from the Zion Station NDT funds as defined within the ASA. Therefore, the transfer of the Zion Station assets did not qualify for asset sale accounting treatment and, as a result, the related NDT funds were reclassified to Pledged assets for Zion Station decommissioning within Generation’s and Exelon’s Consolidated Balance Sheets and will continue to be measured in the same manner as prior to the completion of the transaction. Additionally, the transferred ARO for decommissioning was replaced with a Payable for Zion Station decommissioning in Generation’s and Exelon’s Consolidated Balance Sheets. Changes in the value of the Zion Station NDT assets, net of applicable taxes, are recorded as a change in the Payable to ZionSolutions. At no point will the payable to ZionSolutions exceed the project budget of the costs remaining to decommission Zion Station. Generation has retained its obligation for the SNF. Following ZionSolutions’ completion of its contractual obligations and transfer of the NRC license to Generation, Generation will store the SNF at Zion Station until it is transferred to the DOE for ultimate disposal, and will complete all remaining decommissioning activities associated with the SNF dry storage facility. Generation has a liability of approximately $112 million which is included within the nuclear decommissioning ARO at March 31, 2017. Generation also has retained NDT assets to fund its obligation to maintain the SNF at Zion Station until transfer to the DOE and to complete all remaining decommissioning activities for the SNF storage facility. Any shortage of funds necessary to maintain the SNF and decommission the SNF storage facility is ultimately required to be funded by Generation. Any Zion Station NDT funds remaining after the completion of all decommissioning activities will be returned to ComEd customers in accordance with the applicable orders. The following table provides the pledged assets and payables to ZionSolutions, and withdrawals by ZionSolutions at March 31, 2017 and December 31, 2016:

 
Exelon and Generation
 
March 31, 2017
 
December 31, 2016
Carrying value of Zion Station pledged assets
$
95

 
$
113

Payable to Zion Solutions(a)
88

 
104

Current portion of payable to Zion Solutions(b)
85

 
90

Cumulative withdrawals by Zion Solutions to pay decommissioning costs(c)
895

 
878

_________
(a)
Excludes a liability recorded within Exelon’s and Generation’s Consolidated Balance Sheets related to the tax obligation on the unrealized activity associated with the Zion Station NDT funds. The NDT funds will be utilized to satisfy the tax obligations as gains and losses are realized.
(b)
Included in Other current liabilities within Exelon’s and Generation’s Consolidated Balance Sheets.
(c)
Includes project expenses to decommission Zion Station and estimated tax payments on Zion Station NDT fund earnings.

NRC Minimum Funding Requirements  

NRC regulations require that licensees of nuclear generating facilities demonstrate reasonable assurance that funds will be available in specified minimum amounts to decommission the facility at the end of its life.

Generation filed its biennial decommissioning funding status report with the NRC on March 30, 2017 for all units except for Zion Station which is included in a separate report to the NRC submitted by EnergySolutions (see Zion Station Decommissioning above). The status report demonstrated adequate decommissioning funding assurance for all units except for Peach Bottom Unit 1. As a former PECO plant, financial assurance for decommissioning Peach Bottom Unit 1 is provided by the NDT fund in addition to collections from PECO ratepayers. As discussed under Nuclear Decommissioning Trust Fund Investments above, the amount collected from PECO ratepayers has been adjusted in the March 31, 2017 filing to the PAPUC which, if approved by the PAPUC, will be effective January 1, 2018.