XML 111 R19.htm IDEA: XBRL DOCUMENT v3.2.0.727
Nuclear Decommissioning (Exelon and Generation)
6 Months Ended
Jun. 30, 2015
Environmental Remediation Obligations [Abstract]  
Nuclear Decommissioning (Exelon and Generation)
Nuclear Decommissioning (Exelon and Generation)
Nuclear Decommissioning Asset Retirement Obligations
Generation has a legal obligation to decommission its nuclear power plants following the expiration of their operating licenses. To estimate its decommissioning obligation related to its nuclear generating stations for financial accounting and reporting purposes, Generation uses a probability-weighted, discounted cash flow model which, on a unit-by-unit basis, considers multiple outcome scenarios that include significant estimates and assumptions, and are based on decommissioning cost studies, cost escalation rates, probabilistic cash flow models and discount rates. Generation generally updates its ARO annually during the third quarter, unless circumstances warrant more frequent updates, based on its review of updated cost studies and its annual evaluation of cost escalation factors and probabilities assigned to various scenarios.
The following table provides a rollforward of the nuclear decommissioning ARO reflected on Exelon’s and Generation’s Consolidated Balance Sheets from December 31, 2014 to June 30, 2015:
Nuclear decommissioning ARO at December 31, 2014(a)
$
6,961

Net increase due to changes in, and timing of, estimated future cash flows(b)
55

Accretion expense
189

Costs incurred to decommission retired plants

(1
)
Nuclear decommissioning ARO at June 30, 2015(a)
$
7,204

___________
(a)
Includes $7 million and $8 million as the current portion of the ARO at June 30, 2015 and December 31, 2014 respectively, which is included in Other current liabilities on Exelon’s and Generation’s Consolidated Balance Sheets.
(b)
Represents a purchase accounting adjustment to the fair value of the CENG ARO liability as of April 1, 2014, the date of consolidation. See Note 6Investment in Constellation Energy Nuclear Group, LLC for additional information.

Nuclear Decommissioning Trust Fund Investments

At June 30, 2015 and December 31, 2014, Exelon and Generation had NDT fund investments totaling $10,607 million and $10,537 million, respectively.

The following table provides unrealized gains (losses) on NDT funds for the three and six months ended June 30, 2015 and 2014:
 
Exelon and Generation
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2015
 
2014
 
2015
 
2014
Net unrealized gains (losses) on decommissioning trust
     funds — Regulatory Agreement Units(a)
$
(133
)
 
$
172

 
$
(85
)
 
$
234

Net unrealized gains (losses) on decommissioning trust
     funds — Non-Regulatory Agreement Units(b)(c)
(96
)
 
128

 
(56
)
 
141

 
___________
(a)
Net unrealized gains (losses) related to Generation’s NDT funds associated with Regulatory Agreement Units are included in Regulatory liabilities on Exelon’s Consolidated Balance Sheets and Noncurrent payables to affiliates on Generation’s Consolidated Balance Sheets.
(b)
Excludes $10 million of net unrealized gains related to the Zion Station pledged assets for the three months ended June 30, 2014 and $9 million and $20 million of net unrealized gains related to the Zion Station pledged assets for the six months ended June 30, 2015 and 2014, respectively. Net unrealized gains related to Zion Station pledged assets are included in the Payable for Zion Station decommissioning on Exelon’s and Generation’s Consolidated Balance Sheets.
(c)
Net unrealized gains (losses) related to Generation’s NDT funds with Non-Regulatory Agreement Units are included within Other, net in Exelon’s and Generation’s Consolidated Statements of Operations and Comprehensive Income.
Interest and dividends on NDT fund investments are recognized when earned and are included in Other, net in Exelon’s and Generation’s Consolidated Statements of Operations and Comprehensive Income. Interest and dividends earned on the NDT fund investments for the Regulatory Agreement Units are eliminated within Other, net in Exelon’s and Generation’s Consolidated Statement of Operations and Comprehensive Income.
Refer to Note 3Regulatory Matters and Note 25Related Party Transactions of the Exelon 2014 Form 10-K for information regarding regulatory liabilities at ComEd and PECO and intercompany balances between Generation, ComEd and PECO reflecting the obligation to refund to customers any decommissioning-related assets in excess of the related decommissioning obligations.
Zion Station Decommissioning    
On September 1, 2010, Generation completed an Asset Sale Agreement (ASA) with EnergySolutions Inc. and its wholly owned subsidiaries, EnergySolutions, LLC (EnergySolutions) and ZionSolutions, under which ZionSolutions has assumed responsibility for completing certain decommissioning activities at Zion Station, which is located in Zion, Illinois and ceased operation in 1998. See Note 15Asset Retirement Obligations of the Exelon 2014 Form 10-K for information regarding the specific treatment of assets, including NDT funds, and decommissioning liabilities transferred in the transaction.
ZionSolutions is subject to certain restrictions on its ability to request reimbursements from the Zion Station NDT funds as defined within the ASA. Therefore, the transfer of the Zion Station assets did not qualify for asset sale accounting treatment and, as a result, the related NDT funds were reclassified to Pledged assets for Zion Station decommissioning within Generation’s and Exelon’s Consolidated Balance Sheets and will continue to be measured in the same manner as prior to the completion of the transaction. Additionally, the transferred ARO for decommissioning was replaced with a Payable for Zion Station decommissioning in Generation’s and Exelon’s Consolidated Balance Sheets. Changes in the value of the Zion Station NDT assets, net of applicable taxes, are recorded as a change in the Payable to ZionSolutions. At no point will the payable to ZionSolutions exceed the project budget of the costs remaining to decommission Zion Station. Generation has retained its obligation for the SNF. Following ZionSolutions’ completion of its contractual obligations and transfer of the NRC license to Generation, Generation will store the SNF at Zion Station until it is transferred to the DOE for ultimate disposal, and will complete all remaining decommissioning activities associated with the SNF dry storage facility. Generation has a liability of approximately $88 million, which is included within the nuclear decommissioning ARO at June 30, 2015. Generation also has retained NDT assets to fund its obligation to maintain the SNF at Zion Station until transfer to the DOE and to complete all remaining decommissioning activities for the SNF storage facility. Any shortage of funds necessary to maintain the SNF and decommission the SNF storage facility is ultimately required to be funded by Generation. Any Zion Station NDT funds remaining after the completion of all decommissioning activities will be returned to ComEd customers in accordance with the applicable orders. The following table provides the pledged assets and payables to ZionSolutions, and withdrawals by ZionSolutions at June 30, 2015 and December 31, 2014:
 
Exelon and Generation
 
June 30, 2015
 
December 31, 2014
Carrying value of Zion Station pledged assets
$
264

 
$
319

Payable to Zion Solutions(a)
241

 
292

Current portion of payable to Zion Solutions(b)
106

 
137

Cumulative withdrawals by Zion Solutions to pay decommissioning costs
731

 
666

___________
(a)
Excludes a liability recorded within Exelon’s and Generation’s Consolidated Balance Sheets related to the tax obligation on the unrealized activity associated with the Zion Station NDT Funds. The NDT Funds will be utilized to satisfy the tax obligations as gains and losses are realized.
(b)
Included in Other current liabilities within Exelon’s and Generation’s Consolidated Balance Sheets.
NRC Minimum Funding Requirements
NRC regulations require that licensees of nuclear generating facilities demonstrate reasonable assurance that funds will be available in specified minimum amounts to decommission the facility at the end of its life. Generation filed its biennial decommissioning funding status report with the NRC on March 31, 2015. This report reflects the status of decommissioning funding assurance as of December 31, 2014. Due to increased cost estimates received in the second half of 2014, Braidwood Unit 1, Braidwood Unit 2, and Byron Unit 2 did not meet the NRC's minimum funding assurance criteria as of December 31, 2014. NRC guidance provides licensees with two years or by the time of submitting the next biennial report (on or before March 31, 2017) to resolve funding assurance shortfalls. During this period, Generation will monitor funding assurance and new developments, including the impact of a 20-year license renewal for Braidwood and Byron, to assess the status of funding assurance and to take steps, if necessary, to address any funding shortfall on these funds on or before March 31, 2017.