XML 46 R8.htm IDEA: XBRL DOCUMENT v3.23.1
Regulatory Matters (All Registrants)
3 Months Ended
Mar. 31, 2023
Regulated Operations [Abstract]  
Regulatory Matters (All Registrants) Regulatory Matters (All Registrants)
As discussed in Note 3 — Regulatory Matters of the 2022 Form 10-K, the Registrants are involved in rate and regulatory proceedings at FERC and their state commissions. The following discusses developments in 2023 and updates to the 2022 Form 10-K.
Distribution Base Rate Case Proceedings
The following tables show the completed and pending distribution base rate case proceedings in 2023.
Completed Distribution Base Rate Case Proceedings
Registrant/JurisdictionFiling DateServiceRequested Revenue Requirement IncreaseApproved Revenue Requirement IncreaseApproved ROEApproval DateRate Effective Date
ComEd - Illinois(a)
April 15, 2022Electric$199 $199 7.85 %November 17, 2022January 1, 2023
PECO - PennsylvaniaMarch 31, 2022Natural Gas82 55 
N/A(b)
October 27, 2022January 1, 2023
BGE - Maryland(c)
May 15, 2020 (amended September 11, 2020)Electric203 140 9.50 %December 16, 2020January 1, 2021
Natural Gas108 74 9.65 %
Pepco - Maryland(d)
October 26, 2020 (amended March 31, 2021)Electric104 52 9.55 %June 28, 2021June 28, 2021
DPL - Maryland(e)
May 19, 2022Electric38 29 9.60 %December 14, 2022January 1, 2023
__________
(a)ComEd's 2023 approved revenue requirement above reflects an increase of $144 million for the initial year revenue requirement for 2023 and an increase of $55 million related to the annual reconciliation for 2021. The revenue requirement for 2023 provides for a weighted average debt and equity return on distribution rate base of 5.94%, inclusive of an allowed ROE of 7.85%, reflecting the monthly average yields for 30-year treasury bonds plus 580 basis points. The reconciliation revenue requirement for 2021 provides for a weighted average debt and equity return on distribution rate base of 5.91%, inclusive of an allowed ROE of 7.78%, reflecting the monthly yields on 30-year treasury bonds plus 580 basis points less a performance metrics penalty of 7 basis points. This is ComEd's last performance-based electric distribution formula rate update filing under EIMA. See discussion of CEJA below for details on the transition away from the electric distribution formula rate.
(b)The PECO natural gas base rate case proceeding was resolved through a settlement agreement, which did not specify an approved ROE.
(c)Reflects a three-year cumulative multi-year plan for 2021 through 2023. BGE proposed to use certain tax benefits to fully offset the increases in 2021 and 2022 and partially offset the increase in 2023. The MDPSC awarded BGE electric revenue requirement increases of $59 million, $39 million, and $42 million, before offsets, in 2021, 2022, and 2023, respectively, and natural gas revenue requirement increases of $53 million, $11 million, and $10 million, before offsets, in 2021, 2022, and 2023, respectively. However, the MDPSC utilized the tax benefits to fully offset the increases in 2021 and January 2022 such that customer rates remained unchanged. For the remainder of 2022, the MDPSC chose to offset only 25% of the cumulative 2021 and 2022 electric revenue requirement increases and 50% of the cumulative gas revenue requirement increases. In 2021, the MDPSC deferred a decision on whether to use certain tax benefits to offset the revenue requirement increases in 2023 and directed BGE to make another proposal at the end of 2022. In September 2022 BGE proposed that tax benefits not be used to offset the 2023 revenue requirement increases. On October 26, 2022, the MDPSC accepted BGE's recommendation to not use tax benefits to offset the 2023 revenue requirement increases.
(d)Reflects a three-year cumulative multi-year plan for April 1, 2021 through March 31, 2024. The MDPSC awarded Pepco electric incremental revenue requirement increases of $21 million, $16 million, and $15 million, before offsets, for the 12-month periods ending March 31, 2022, 2023, and 2024, respectively. Pepco proposed to utilize certain tax benefits to fully offset the increase through 2023 and partially offset customer rate increases in 2024. However, the MDPSC only utilized the acceleration of refunds for certain tax benefits to fully offset the increases such that customer rates remain unchanged through March 31, 2022. On February 23, 2022, the MDPSC chose to offset 25% of the cumulative revenue requirement increase for the 12-month period ending March 31, 2023. Whether certain tax benefits will be used to offset the customer rate increases for the 12-month period ending March 31, 2024 has not been decided, and Pepco cannot predict the outcome.
(e)Reflects a three-year cumulative multi-year plan for January 1, 2023 through December 31, 2025. The MDPSC awarded DPL electric incremental revenue requirement increases of $17 million, $6 million, and $6 million for 2023, 2024, and 2025, respectively.
Pending Distribution Base Rate Case Proceedings
Registrant/JurisdictionFiling DateServiceRequested Revenue Requirement IncreaseRequested ROEExpected Approval Timing
ComEd - Illinois(a)
January 17, 2023Electric$1,472 
10.50% to 10.65%
Fourth quarter of 2023
ComEd - Illinois(b)
April 21, 2023Electric247 8.91%Fourth quarter of 2023
BGE - Maryland(c)
February 17, 2023Electric313 10.40%Fourth quarter of 2023
Natural Gas289 10.40%
Pepco - District of Columbia(d)
April 13, 2023Electric191 10.50%First quarter of 2024
DPL - Delaware(e)
December 15, 2022 (amended February 28, 2023)Electric48 10.50%Second quarter of 2024
ACE - New Jersey(f)
February 15, 2023Electric105 10.50%First quarter of 2024
__________
(a)Reflects a four-year cumulative MRP for January 1, 2024 to December 31, 2027 and total requested revenue requirement increases of $877 million effective January 1, 2024, $175 million effective January 1, 2025, $217 million effective January 1, 2026, and $203 million effective January 1, 2027, based on forecasted revenue requirements. The revenue requirement will provide for a weighted average debt and equity return on distribution rate base of 7.43% in 2024, 7.50% in 2025, 7.62% in 2026, and 7.70% in 2027, inclusive of an allowed ROE of 10.50% in 2024, 10.55% in 2025, 10.60% in 2026, and 10.65% in 2027. The requested revenue requirements are based on capital structures that reflect between 50.58% and 51.19% common equity. ComEd’s MRP also includes a proposed rate phase-in to defer approximately $307 million of the $877 million year-over-year increase for 2024 revenue from 2024 to 2026.
(b)On April 21, 2023, ComEd filed its proposed Delivery Reconciliation Amount of $247 million under Rider Delivery Service Pricing Reconciliation (Rider DSPR) which allows for the reconciliation of the revenue requirement in effect in the final years in which formula rates are determined and until such time as new rates are established under ComEd’s approved MRP. The 2023 filing reconciles the delivery service rates in effect in 2022 with the actual delivery service costs incurred in 2022. Final order is expected by December 2023, and the reconciliation amount will be in customer rates beginning January 1, 2024.
(c)Reflects a three-year cumulative multi-year plan for January 1, 2024 through December 31, 2026 submitted to the MDPSC. Inclusive of the proposed acceleration of remaining electric tax benefits in 2024 and 2025, and remaining gas tax benefits in 2024, BGE requested total electric revenue requirement increases of $85 million, $103 million, and $125 million in 2024, 2025, and 2026, respectively, and natural gas revenue requirement increases of $158 million, $77 million, and $54 million in 2024, 2025, and 2026, respectively. Requested revenue requirement increases will be used to recover capital investments designed to increase the resilience of the electric and gas distribution systems and support Maryland’s climate and regulatory initiatives. The 2021 and 2022 reconciliation amounts are not included in the requested revenue requirement increase, as BGE is proposing that these amounts be recovered through the separate electric and gas riders in 2024. The 2021 reconciliation amounts are $11 million and $7 million for electric and gas, respectively, and the 2022 reconciliation amounts are $44 million and $15 million for electric and gas, respectively.
(d)Reflects a three-year cumulative multi-year plan for January 1, 2024 through December 31, 2026 submitted to the DCPSC. Pepco requested total electric revenue requirement increases of $117 million, $37 million, and $37 million in 2024, 2025, and 2026, respectively. Requested revenue requirement increases will be used to recover capital investments designed to advance system-readiness and support the District of Columbia’s climate and clean energy goals.
(e)The rates will go into effect on July 15, 2023, subject to refund.
(f)Requested increases are before New Jersey sales and use tax. ACE intends to put rates into effect on November 17, 2023, subject to refund.
Transmission Formula Rates
The Utility Registrants' transmission rates are each established based on a FERC-approved formula. ComEd, BGE, Pepco, DPL, and ACE are required to file an annual update to the FERC-approved formula on or before May 15, and PECO is required to file on or before May 31, with the resulting rates effective on June 1 of the same year. The annual update for BGE is based on prior year actual costs and current year projected capital additions, accumulated depreciation, depreciation and amortization expense, and accumulated deferred income
taxes. The update for BGE also reconciles any differences between the actual costs and actual revenues for the calendar year (annual reconciliation).
For 2023, the following increases/(decreases) were included in BGE's annual electric transmission formula rate updates. ComEd, PECO, Pepco, DPL, and ACE intend to file by the required deadline for the annual update.
Registrant(a)
Initial Revenue Requirement IncreaseAnnual Reconciliation DecreaseTotal Revenue Requirement Increase
Allowed Return on Rate Base(b)
Allowed ROE(c)
BGE$19 $(12)$(d)7.34 %10.50 %
__________
(a)All rates are effective June 1, 2023 - May 31, 2024, subject to review by interested parties pursuant to review protocols of tariffs.
(b)Represents the weighted average debt and equity return on transmission rate bases.
(c)The rate of return on common equity includes a 50-basis-point incentive adder for being a member of a RTO.
(d)The increase in BGE's transmission revenue requirement includes a $3 million reduction related to a FERC-approved dedicated facilities charge to recover the costs of providing transmission service to specifically designated load by BGE.
Other State Regulatory Matters
Illinois Regulatory Matters
CEJA (Exelon and ComEd). On September 15, 2021, the Governor of Illinois signed into law CEJA. CEJA includes, among other features, (1) procurement of CMCs from qualifying nuclear-powered generating facilities, (2) a requirement to file a general rate case or a new four-year MRP no later than January 20, 2023 to establish rates effective after ComEd’s existing performance-based distribution formula rate sunsets, (3) an extension of and certain adjustments to ComEd’s energy efficiency MWh savings goals, (4) revisions to the Illinois RPS requirements, including expanded charges for the procurement of RECs from wind and solar generation, (5) a requirement to accelerate amortization of ComEd’s unprotected excess deferred income taxes (EDIT) that ComEd was previously directed by the ICC to amortize using the average rate assumption method which equates to approximately 39.5 years, and (6) requirements that ComEd and the ICC initiate and conduct various regulatory proceedings on subjects including ethics, spending, grid investments, and performance metrics. Regulatory or legal challenges regarding the validity or implementation of CEJA are possible and Exelon and ComEd cannot reasonably predict the outcome of any such challenges.
ComEd Electric Distribution Rates
ComEd filed, and received approval for, its last performance-based electric distribution formula rate update filing under EIMA in 2022; those rates are in effect throughout 2023.
On February 3, 2022, the ICC approved a tariff that establishes the process under which ComEd will reconcile its 2022 and 2023 rate year revenue requirements with actual costs. Those reconciliation amounts will be determined using the same process as were used for prior reconciliations under the performance-based electric distribution formula rate. Using that process, for the rate years 2022 and 2023 ComEd will ultimately collect revenues from customers reflecting each year’s actual recoverable costs, year-end rate base, and a weighted average debt and equity return on distribution rate base, with the ROE component based on the annual average of the monthly yields of the 30-year U.S. Treasury bonds plus 580 basis points. In April 2023, ComEd filed its first petition with the ICC to reconcile its 2022 actual costs with the approved revenue requirement that was in effect in 2022. The rate year 2023 reconciliation will be filed in 2024.
Beginning in 2024, ComEd will recover from retail customers, subject to certain exceptions, the costs it incurs to provide electric delivery services either through its electric distribution rate or other recovery mechanisms authorized by CEJA. On January 17, 2023, ComEd filed a petition with the ICC seeking approval of a MRP for 2024-2027. The MRP supports a multi-year grid plan (Grid Plan), also filed on January 17, covering planned investments on the electric distribution system within ComEd’s service area through 2027. Costs incurred during each year of the MRP are subject to ICC review and the plan’s revenue requirement for each year will be reconciled with the actual costs that the ICC determines are prudently and reasonably incurred for that year. The reconciliation is subject to adjustment for certain costs, including a limitation on recovery of costs that are more than 105% of certain costs in the previously approved MRP revenue requirement, absent a modification of the
rate plan itself. Thus, for example, the rate adjustments necessary to reconcile 2024 revenues to ComEd’s actual 2024 costs incurred would take effect in January 2026 after the ICC’s review during 2025. The ICC must issue its decision on both the MRP and Grid Plan by mid-December 2023, for rates to begin with the January 2024 billing cycle.
In January 2022, ComEd filed a request with the ICC proposing performance metrics that would be used in determining ROE incentives and penalties in the event ComEd filed a MRP in January 2023. On September 27, 2022, the ICC issued a final order approving seven performance metrics that provide symmetrical performance adjustments of 32 total basis points to ComEd’s rate of return on common equity based on the extent to which ComEd achieves the annual performance goals. On November 10, 2022, the ICC granted ComEd's application for rehearing, in part. On April 5, the ICC issued its final order on rehearing for the performance and tracking metrics proceeding, in which the ICC declined to adopt ComEd’s proposed modifications to the reliability and peak load reduction performance metrics. ComEd is determining how to implement the performance metrics, which take effect on January 1, 2024. ComEd will make its initial filing in 2025 to assess performance achieved under the metrics in 2024, and to determine any ROE adjustment, which would take effect in 2026.
Carbon Mitigation Credit
CEJA establishes decarbonization requirements for Illinois as well as programs to support the retention and development of emissions-free sources of electricity. ComEd is required to purchase CMCs from participating nuclear-powered generating facilities between June 1, 2022 and May 31, 2027. The price to be paid for each CMC was established through a competitive bidding process that included consumer-protection measures that capped the maximum acceptable bid amount and a formula that reduces CMC prices by an energy price index, the base residual auction capacity price in the ComEd zone of PJM, and the monetized value of any federal tax credit or other subsidy if applicable. The consumer protection measures contained in CEJA will result in net payments to ComEd ratepayers if the energy index, the capacity price and applicable federal tax credits or subsidy exceed the CMC contract price. ComEd began issuing credits to its retail customers under its new CMC rider in the June 2022 billing period and recorded a regulatory asset of $1,118 million as of March 31, 2023 for the difference between customer credits issued and the credit to be received from the participating nuclear-powered generating facilities.
Under CEJA, the costs of procuring CMCs, including carrying costs, will be recovered through a rider, the Rider Carbon-Free Resource Adjustment (Rider CFRA). The Rider CFRA provides for an annual reconciliation and true-up to actual costs incurred or credits received by ComEd to purchase CMCs, with any difference to be credited to or collected from ComEd’s retail customers in subsequent periods. The difference between the net payments to (or receivables from) ComEd ratepayers and the credits received by ComEd to purchase CMCs is recorded to Purchased Power expense with an offset to the regulatory asset (or regulatory liability). On December 21, 2022, ComEd filed a supplemental statement to the Rider CFRA proposing that the company recover costs or provide credits faster than the tariff allows, implement monthly reconciliations, and allow the Company to adjust Rider CFRA rates based not only on anticipated differences but also past payments or credits. The ICC approved the proposal on January 19, 2023.
Beneficial Electrification Plan
On July 1, 2022, ComEd filed a proposed plan to promote beneficial electrification efforts in its Northern Illinois service area with the ICC as required by CEJA. ComEd's plan is designed to meaningfully reduce barriers to beneficial electrification, including those related to electric vehicles (EV), such as upfront technology adoption costs, charging costs, and charging availability; promote equity and environmental justice; reduce carbon emissions and surface-level pollutants; and support customer education and awareness of electrification options. As proposed, ComEd could expend approximately $300 million in total over the three-year period 2023 through 2025. The beneficial electrification plan requests recovery of all those costs through a rider mechanism, under which certain of the costs would be amortized over ten years with a return on the unrecovered balance. On November 10, 2022, in responses to a Staff motion, the ICC approved an interim order dismissing from ComEd’s Beneficial Electrification Plan certain rebates (rebates to support residential customers’ purchase of EVs; and rebates to ComEd’s commercial and industrial customers to support the installation of EV chargers). However, the ICC found that building electrification measures were properly within the scope of beneficial electrification, in line with ComEd’s proposal. The ICC also adopted ComEd’s position regarding the rate impact of spending associated with EV related infrastructure. On November 21, 2022, ComEd filed an application for rehearing of the interim order, which the ICC denied. On December 9, 2022, the Office of the Illinois Attorney General (AG) also
sought rehearing. On December 15, 2022, ComEd filed an appeal of the ICC’s interim order and the denial of rehearing with the Illinois Appellate Court. That appeal has been stayed pending the ICC's disposition of the case. Also on December 15, 2022, the ICC denied the AG’s application for rehearing and the AG subsequently filed an appeal.
On March 23, 2023, the ICC issued its final order in the beneficial electrification plan docket. The order adopts the beneficial electrification plan with modifications and directs ComEd to seek cost recovery through the multi-year rate plan filing for 2024 and 2025, and the final formula rate reconciliation docket for 2023, rather than through a new rider beneficial electrification as ComEd had proposed. The order also rejects ComEd’s request for a regulatory asset. The order approves an overall annual budget of $77 million per year for each of the three years in the plan (2023 through 2025), with flexibility to roll forward unused funds to future years within the same plan period. The final order also made specific reductions to the proposed $100 million per year budget, reducing the proposed customer education and awareness budget; the portfolio budget for cross-cutting administrative support; and the light, medium, and heavy-duty EV rebate programs. The order dedicates funds for rebates related to the installation of heat pumps and the promotion of home electrification for low-income customers and those in Environmental Justice and Restore, Reinvest, and Renew designated communities. The order also requires ComEd to propose methods to minimize or exempt low-income ratepayers from the impact of its beneficial electrification plan, possibly through ComEd’s next rate design investigation. On April 18, 2023, ComEd filed an application for rehearing concerning aspects of the ICC’s order, including the approved budgets. The ICC must act on that application by May 8, 2023. On April 21, 2023 the Chicago Transit Authority and city of Chicago jointly filed an application for rehearing requesting the ICC modify the final order so the transit agencies do not pay the cost of make-ready infrastructure and to exempt transit agencies from paying the required deposit or providing a letter of credit to ComEd for the cost of make-ready infrastructure. On April 24, 2023, the AG also filed an application for rehearing on several topics, including the budget, rebate levels, retail rate cap, types of programs included in the beneficial electrification plan, compliance with the EV Act, benefit-to-cost analysis, and rate-related issues. On April 27, 2023, ICC staff filed a motion for clarification of the order’s language regarding the annual budget. The ICC will likely rule on all of the applications for rehearing and staff’s motion at their regularly scheduled May 4, 2023 regular open meeting. If the ICC denies rehearing, parties have 35 days to appeal arguments raised in their rehearing applications.
New Jersey Regulatory Matters
Termination of Energy Procurement Provisions of PPAs (Exelon, PHI, and ACE).

On December 22, 2021, ACE filed with the NJBPU a petition to terminate the provisions in the PPAs to purchase electricity from two coal-powered generation facilities located in the state of New Jersey. The petition was approved by the NJBPU on March 23, 2022. Upon closing of the transaction on March 31, 2022, ACE recognized a liability of $203 million for the contract termination fee, which is to be paid by the end of 2024, and recognized a corresponding regulatory asset of $203 million.
As of March 31, 2023, the $118 million liability for the contract termination fee consists of $87 million and $31 million included in Other current liabilities and Other deferred credits and other liabilities, respectively, in Exelon's Consolidated Balance Sheet. The current and noncurrent liabilities are included in PPA termination obligation and Other deferred credits and other liabilities, respectively, in PHI's and ACE's Consolidated Balance Sheets. For the three months ended March 31, 2023, ACE has paid $19 million of the liability, which is recorded in Changes in Other assets and liabilities in Exelon's, PHI's, and ACE's Consolidated Statements of Cash Flows.
Other Federal Regulatory Matters
FERC Audit (Exelon and ComEd). The Utility Registrants are subject to periodic audits by FERC. FERC’s Division of Audits and Accounting initiated a nonpublic audit of ComEd in May 2021 evaluating ComEd’s compliance with (1) approved terms, rates and conditions of its federally regulated service; (2) accounting requirements of the Uniform System of Accounts; (3) reporting requirements of the FERC Form 1; and (4) the requirements for record retention. The audit covered the period from January 1, 2017 through August 31, 2022. On January 17 and February 21, 2023, ComEd was provided with information on a series of potential findings, including concerning ComEd's methodology regarding the allocation of certain overhead costs to capital under FERC regulations. As of March 31, 2023, ComEd has continued discussions with FERC staff and determined that a loss is probable and has recorded a liability that reflects management's best estimate. The final outcome and resolution of the findings or of the audit itself cannot be predicted and the results could be material to the Exelon and ComEd financial statements.
Regulatory Assets and Liabilities
The Utility Registrants' regulatory assets and liabilities have not changed materially since December 31, 2022, unless noted below. See Note 3 — Regulatory Matters of the 2022 Form 10-K for additional information on the specific regulatory assets and liabilities.
ComEd. Regulatory assets increased $547 million primarily due to increases of $275 million in the CMC regulatory asset, as discussed in CEJA above, and $143 million in the Electric Distribution Formula Rate Annual Reconciliations regulatory asset.
PECO. Regulatory assets increased $44 million primarily due to an increase of $48 million in the Deferred Income Taxes regulatory asset. Regulatory liabilities increased $45 million primarily due to increases of $31 million in the Electric Energy and Natural Gas Costs regulatory liability and $28 million in the Decommissioning the Regulatory Agreement Units regulatory liability.
BGE. Regulatory assets increased $66 million primarily due to an increase of $54 million in the Under-Recovered Revenue Decoupling regulatory asset.
DPL. Regulatory assets decreased $17 million primarily due to a decrease of $18 million in the Electric Energy and Natural Gas Costs regulatory asset.
ACE. Regulatory assets decreased $18 million primarily due to a decrease of $35 million in the Electric Energy Costs regulatory asset as a result of the PPA termination. Regulatory liabilities decreased $19 million primarily due to a $9 million decrease in the Over-Recovered Revenue Decoupling regulatory liability.
Capitalized Ratemaking Amounts Not Recognized
The following table presents authorized amounts capitalized for ratemaking purposes related to earnings on shareholders' investment that are not recognized for financial reporting purposes in the Registrants' Consolidated Balance Sheets. These amounts will be recognized as revenues in the related Consolidated Statements of Operations and Comprehensive Income in the periods they are billable to the Utility Registrants' customers. PECO had no related amounts as of March 31, 2023 and December 31, 2022.
Exelon
ComEd(a)
BGE(b)
PHI
Pepco(c)
DPL(c)
ACE(b)
March 31, 2023$53 $13 $26 $14 $11 $$
December 31, 202257 28 21 18 
__________
(a)Reflects ComEd's unrecognized equity returns earned for ratemaking purposes on its electric distribution formula rate regulatory assets.
(b)BGE's and ACE's authorized amounts capitalized for ratemaking purposes primarily relate to earnings on shareholder's investment on their respective AMI programs.
(c)Pepco's and DPL's authorized amounts capitalized for ratemaking purposes relate to earnings on shareholder's investment on their respective AMI Programs and Energy Efficiency and Demand Response Programs, and for Pepco District of Columbia revenue decoupling program. The earnings on energy efficiency are on Pepco District of Columbia and DPL Delaware programs only.