Commonwealth Edison Co [Member] | Illinois 2020 Electric Distribution Base Rate Case [Member]              
Regulatory Matters Completed Rate Cases [Line Items]              
Requested Revenue Requirement Increase (Decrease)       $ (11)      
Approved Revenue Requirement Increase (Decrease)   $ (14)          
Approved Return on Equity, Percentage   8.38%          
Public Utilities, Interim Rate Increase (Decrease), Amount   $ 50          
Public Utilities Requested Rate Increase (Decrease), Prior Year Annual Reconciliation   $ (64)          
Public Utilities, Approved Equity Capital Structure, Percentage   6.28%          
Basis points for ComEd's Revenue Requirement   580          
Baltimore Gas and Electric Company [Member] | Maryland 2020 Electric Distribution Base Rate Case [Member]              
Regulatory Matters Completed Rate Cases [Line Items]              
Requested Revenue Requirement Increase (Decrease)     $ 137        
Approved Revenue Requirement Increase (Decrease) $ 81            
Approved Return on Equity, Percentage 9.50%            
Public Utilities, Interim Rate Increase (Decrease), Amount         $ 42 $ 39 $ 59
Baltimore Gas and Electric Company [Member] | Maryland 2020 Gas Distribution Base Rate Case [Member]              
Regulatory Matters Completed Rate Cases [Line Items]              
Requested Revenue Requirement Increase (Decrease)     $ 91        
Approved Revenue Requirement Increase (Decrease) $ 21            
Approved Return on Equity, Percentage 9.65%            