XML 214 R95.htm IDEA: XBRL DOCUMENT v3.20.4
Lessee - Lessee Future Minimum Operating Lease Maturity Payments (Details) - USD ($)
$ in Millions
Dec. 31, 2020
Dec. 31, 2019
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 $ 239  
2022 177  
2023 146  
2024 141  
2025 140  
Remaining years 834  
Lessee, Operating Lease, Liability, to be Paid 1,677  
Interest 375  
Operating Lease, Liability 1,302 $ 1,532
Exelon Generation Co L L C [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 145  
2022 113  
2023 100  
2024 98  
2025 99  
Remaining years 640  
Lessee, Operating Lease, Liability, to be Paid 1,195  
Interest 288  
Operating Lease, Liability 907 1,082
Commonwealth Edison Co [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 3  
2022 2  
2023 1  
2024 1  
2025 1  
Remaining years 0  
Lessee, Operating Lease, Liability, to be Paid 8  
Interest 0  
Operating Lease, Liability 8 11
PECO Energy Co [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 1  
2022 0  
2023 0  
2024 0  
2025 0  
Remaining years 0  
Lessee, Operating Lease, Liability, to be Paid 1  
Interest 0  
Operating Lease, Liability 1 1
Baltimore Gas and Electric Company [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 46  
2022 16  
2023 1  
2024 0  
2025 0  
Remaining years 18  
Lessee, Operating Lease, Liability, to be Paid 81  
Interest 17  
Operating Lease, Liability 64 82
Pepco Holdings LLC [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 40  
2022 39  
2023 38  
2024 36  
2025 33  
Remaining years 120  
Lessee, Operating Lease, Liability, to be Paid 306  
Interest 51  
Operating Lease, Liability 255 285
Schedule of Lessee, Finance Lease, Liability, Maturity [Line Items]    
2021 8  
2022 8  
2023 8  
2024 8  
2025 8  
Remaining years 13  
Finance Lease, Liability, to be Paid 53  
Interest 3  
Finance lease, liability 50  
Potomac Electric Power Company [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 8  
2022 8  
2023 7  
2024 6  
2025 6  
Remaining years 28  
Lessee, Operating Lease, Liability, to be Paid 63  
Interest 11  
Operating Lease, Liability 52 57
Schedule of Lessee, Finance Lease, Liability, Maturity [Line Items]    
2021 3  
2022 3  
2023 3  
2024 3  
2025 3  
Remaining years 3  
Finance Lease, Liability, to be Paid 18  
Interest 1  
Finance lease, liability 17  
Delmarva Power & Light Company [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 11  
2022 10  
2023 9  
2024 8  
2025 7  
Remaining years 35  
Lessee, Operating Lease, Liability, to be Paid 80  
Interest 15  
Operating Lease, Liability 65 74
Schedule of Lessee, Finance Lease, Liability, Maturity [Line Items]    
2021 3  
2022 3  
2023 3  
2024 3  
2025 3  
Remaining years 6  
Finance Lease, Liability, to be Paid 21  
Interest 1  
Finance lease, liability 20  
Atlantic City Electric Company [Member]    
Schedule of Lessee, Operating Lease, Liability, Maturity [Line Items]    
2021 5  
2022 4  
2023 3  
2024 2  
2025 2  
Remaining years 0  
Lessee, Operating Lease, Liability, to be Paid 16  
Interest 1  
Operating Lease, Liability 15 $ 18
Schedule of Lessee, Finance Lease, Liability, Maturity [Line Items]    
2021 2  
2022 2  
2023 2  
2024 2  
2025 2  
Remaining years 4  
Finance Lease, Liability, to be Paid 14  
Interest 1  
Finance lease, liability $ 13