Regulatory Matters- Narrative (Details) - USD ($)
7 Months Ended 12 Months Ended 36 Months Ended 48 Months Ended 60 Months Ended 72 Months Ended
Dec. 31, 2017
Dec. 31, 2020
Dec. 31, 2019
Dec. 31, 2018
Dec. 31, 2017
Dec. 31, 2024
Jun. 30, 2023
Dec. 31, 2022
Dec. 31, 2023
Jul. 10, 2023
Aug. 26, 2020
Jul. 21, 2017
Commonwealth Edison Co [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Purchase Obligation                       $ 170,000,000
Atlantic City Electric Company [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Proposed Capital Expenditure                     $ 220,000,000  
Maximum [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Purchase Obligation       $ 14,000,000                
Minimum [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Purchase Obligation       11,000,000                
Illinois Utilities [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Purchase Obligation                       $ 235,000,000
Energy Commodities and Service [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Revenue from Contract with Customer, Including Assessed Tax   $ 16,400,000,000 $ 17,754,000,000 19,168,000,000                
Energy Commodities and Service [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Revenue from Contract with Customer, Including Assessed Tax   16,392,000,000 17,752,000,000 $ 19,169,000,000                
Zero Emission Standard [Member] | Energy Commodities and Service [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Revenue from Contract with Customer, Including Assessed Tax $ 150,000,000                      
Clean Energy Legislation [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Competitive businesses other revenues   69,000,000 $ 53,000,000                  
Conowingo [Member] | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Environmental Costs Recognized, Capitalized   45,000,000                    
Forecast [Member] | Baltimore Gas and Electric Company [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Proposed Capital Expenditure                 $ 732,000,000      
Payments to Acquire Property, Plant, and Equipment                 $ 200,000,000      
Forecast [Member] | Potomac Electric Power Company [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Proposed Capital Expenditure   $ 30,000,000       $ 70,000,000       $ 500,000,000    
Forecast [Member] | Atlantic City Electric Company [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
Proposed Capital Expenditure               $ 338,000,000        
Payments to Acquire Property, Plant, and Equipment             $ 96,000,000          
ILLINOIS | Exelon Generation Co L L C [Member]                        
Regulatory Matters Additional Narrative Information [Line Items]                        
exc_ZECChargeperMWh         $ 16.50