XML 62 R19.htm IDEA: XBRL DOCUMENT v3.20.2
Commitments and Contingencies (All Registrants)
9 Months Ended
Sep. 30, 2020
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies (All Registrants) Commitments and Contingencies (All Registrants)
The following is an update to the current status of commitments and contingencies set forth in Note 18 of the Exelon 2019 Form 10-K.
Commitments
PHI Merger Commitments (Exelon, PHI, Pepco, DPL and ACE). Approval of the PHI Merger in Delaware, New Jersey, Maryland and the District of Columbia was conditioned upon Exelon and PHI agreeing to certain commitments. The following amounts represent total commitment costs that have been recorded since the acquisition date and the total remaining obligations for Exelon, PHI, Pepco, DPL, and ACE as of September 30, 2020:
DescriptionExelon PHI Pepco DPLACE
Total commitments$513 $320 $120 $89 $111 
Remaining commitments(a)
87 69 57 
__________
(a)Remaining commitments extend through 2026 and include rate credits, energy efficiency programs and delivery system modernization.
In addition, Exelon is committed to develop or to assist in the commercial development of approximately 37 MWs of new solar generation in Maryland, District of Columbia, and Delaware at an estimated cost of approximately $135 million, which will generate future earnings at Exelon and Generation. Investment costs, which are expected to be primarily capital in nature, are recognized as incurred and recorded in Exelon's and Generation's financial statements. As of September 30, 2020, 27 MWs of new generation were developed and Exelon and Generation have incurred costs of $118 million. Exelon has also committed to purchase 100 MWs of wind energy in PJM. DPL has committed to conducting three RFPs to procure up to a total of 120 MWs of wind RECs for the purpose of meeting Delaware's renewable portfolio standards. DPL has conducted two of the three wind REC RFPs. The first 40 MW wind REC tranche was conducted in 2017 and did not result in a purchase agreement. The second 40 MW wind REC tranche was conducted in 2018 and resulted in a proposed REC purchase agreement that was approved by the DPSC in 2019. The third and final 40 MW wind REC tranche will be conducted in 2022.
Commercial Commitments (All Registrants). The Registrants’ commercial commitments as of September 30, 2020, representing commitments potentially triggered by future events were as follows:
Expiration within
Total202020212022202320242025 and beyond
Exelon
Letters of credit$1,462 $224 $1,238 $— $— $— $— 
Surety bonds(a)
1,056 388 641 27 — — — 
Financing trust guarantees378 — — — — — 378 
Guaranteed lease residual values(b)
28 — 14 
Total commercial commitments $2,924 $612 $1,881 $30 $$$392 
Generation
Letters of credit$1,447 $220 $1,227 $— $— $— $— 
Surety bonds(a)
912 374 511 27 — — — 
Total commercial commitments $2,359 $594 $1,738 $27 $— $— $— 
ComEd
Letters of credit$$— $$— $— $— $— 
Surety bonds(a)
16 11 — — — — 
Financing trust guarantees200 — — — — — 200 
Total commercial commitments $223 $$18 $— $— $— $200 
PECO
Surety bonds(a)
$$— $$— $— $— $— 
Financing trust guarantees178 — — — — — 178 
Total commercial commitments $180 $— $$— $— $— $178 
BGE
Letters of credit$$$— $— $— $— $— 
Surety bonds(a)
— — — — 
Total commercial commitments $$$$— $— $— $— 
PHI
Surety bonds(a)
$21 $$18 $— $— $— $— 
Guaranteed lease residual values(b)
28 — 14 
Total commercial commitments $49 $$20 $$$$14 
Pepco
Surety bonds(a)
$14 $— $14 $— $— $— $— 
Guaranteed lease residual values(b)
— — 
Total commercial commitments $23 $— $14 $$$$
DPL
Surety bonds(a)
$$$$— $— $— $— 
Guaranteed lease residual values(b)
12 — 
Total commercial commitments $16 $$$$$$
ACE
Surety bonds(a)
$$$$— $— $— $— 
Guaranteed lease residual values(b)
— 
Total commercial commitments $10 $$$$$$
__________
(a)Surety bonds—Guarantees issued related to contract and commercial agreements, excluding bid bonds.
(b)Represents the maximum potential obligation in the event that the fair value of certain leased equipment and fleet vehicles is zero at the end of the maximum lease term. The lease term associated with these assets ranges from 1 to 8 years. The maximum potential obligation at the end of the minimum lease term would be $74 million guaranteed by Exelon and PHI, of which $25 million, $31 million, and $18 million is guaranteed by Pepco, DPL, and ACE, respectively. Historically, payments under the guarantees have not been made and PHI believes the likelihood of payments being required under the guarantees is remote.
Environmental Remediation Matters
General (All Registrants). The Registrants’ operations have in the past, and may in the future, require substantial expenditures to comply with environmental laws. Additionally, under Federal and state environmental laws, the Registrants are generally liable for the costs of remediating environmental contamination of property now or formerly owned by them and of property contaminated by hazardous substances generated by them. The Registrants own or lease a number of real estate parcels, including parcels on which their operations or the operations of others may have resulted in contamination by substances that are considered hazardous under environmental laws. In addition, the Registrants are currently involved in a number of proceedings relating to sites where hazardous substances have been deposited and may be subject to additional proceedings in the future. Unless otherwise disclosed, the Registrants cannot reasonably estimate whether they will incur significant liabilities for additional investigation and remediation costs at these or additional sites identified by the Registrants, environmental agencies or others, or whether such costs will be recoverable from third parties, including customers. Additional costs could have a material, unfavorable impact on the Registrants' financial statements.
MGP Sites (Exelon and the Utility Registrants). ComEd, PECO, BGE, and DPL have identified sites where former MGP or gas purification activities have or may have resulted in actual site contamination. For almost all of these sites, there are additional PRPs that may share responsibility for the ultimate remediation of each location.
ComEd has 21 sites that are currently under some degree of active study and/or remediation. ComEd expects the majority of the remediation at these sites to continue through at least 2025.
PECO has 8 sites that are currently under some degree of active study and/or remediation. PECO expects the majority of the remediation at these sites to continue through at least 2023.
BGE has 4 sites that currently require some level of remediation and/or ongoing activity. BGE expects the majority of the remediation at these sites to continue through at least 2023.
DPL has 1 site that is currently under study and the required cost at the site is not expected to be material.
The historical nature of the MGP and gas purification sites and the fact that many of the sites have been buried and built over, impacts the ability to determine a precise estimate of the ultimate costs prior to initial sampling and determination of the exact scope and method of remedial activity. Management determines its best estimate of remediation costs using all available information at the time of each study, including probabilistic and deterministic modeling for ComEd and PECO, and the remediation standards currently required by the applicable state environmental agency. Prior to completion of any significant clean up, each site remediation plan is approved by the appropriate state environmental agency.
ComEd, pursuant to an ICC order, and PECO, pursuant to settlements of natural gas distribution rate cases with the PAPUC, are currently recovering environmental remediation costs of former MGP facility sites through customer rates. While BGE and DPL do not have riders for MGP clean-up costs, they have historically received recovery of actual clean-up costs in distribution rates.
As of September 30, 2020 and December 31, 2019, the Registrants had accrued the following undiscounted amounts for environmental liabilities in Other current liabilities and Other deferred credits and other liabilities within their respective Consolidated Balance Sheets:
September 30, 2020December 31, 2019
Total environmental
investigation and
remediation liabilities
Portion of total related to
MGP investigation and
remediation
Total environmental
investigation and
remediation liabilities
Portion of total related to
MGP investigation and
remediation
Exelon$494 $320 $478 $320 
Generation125 — 105 — 
ComEd299 298 304 303 
PECO23 22 19 17 
BGE— — 
PHI45 — 48 — 
Pepco43 — 46 — 
DPL— — 
ACE— — 
Cotter Corporation (Exelon and Generation). The EPA has advised Cotter Corporation (Cotter), a former ComEd subsidiary, that it is potentially liable in connection with radiological contamination at a site known as the West Lake Landfill in Missouri. In 2000, ComEd sold Cotter to an unaffiliated third-party. As part of the sale, ComEd agreed to indemnify Cotter for any liability arising in connection with the West Lake Landfill. In connection with Exelon’s 2001 corporate restructuring, this responsibility to indemnify Cotter was transferred to Generation. Including Cotter, there are three PRPs participating in the West Lake Landfill remediation proceeding. Investigation by Generation has identified a number of other parties who also may be PRPs and could be liable to contribute to the final remedy. Further investigation is ongoing.
In September 2018, the EPA issued its Record of Decision (ROD) Amendment for the selection of a final remedy. The ROD Amendment modified the remedy previously selected by EPA in its 2008 ROD. While the ROD required only that the radiological materials and other wastes at the site be capped, the ROD Amendment requires partial excavation of the radiological materials in addition to the previously selected capping remedy. The ROD Amendment also allows for variation in depths of excavation depending on radiological concentrations. The EPA and the PRPs have entered into a Consent Agreement to perform the Remedial Design, which is expected to be completed by early 2022. In March 2019 the PRPs received Special Notice Letters from the EPA to perform the Remedial Action work. On October 8, 2019, Cotter (Generation’s indemnitee) provided a non-binding good faith offer to conduct, or finance, a portion of the remedy, subject to certain conditions. The total estimated cost of the remedy, taking into account the current EPA technical requirements and the total costs expected to be incurred collectively by the PRPs in fully executing the remedy, is approximately $280 million, including cost escalation on an undiscounted basis, which would be allocated among the final group of PRPs. Generation has determined that a loss associated with the EPA’s partial excavation and enhanced landfill cover remedy is probable and has recorded a liability included in the table above, that reflects management’s best estimate of Cotter’s allocable share of the ultimate cost. Given the joint and several nature of this liability, the magnitude of Generation’s ultimate liability will depend on the actual costs incurred to implement the required remedy as well as on the nature and terms of any cost-sharing arrangements with the final group of PRPs. Therefore, it is reasonably possible that the ultimate cost and Cotter's associated allocable share could differ significantly once these uncertainties are resolved, which could have a material impact on Exelon's and Generation's future financial statements.
One of the other PRPs has indicated it will be making a contribution claim against Cotter for costs that it has incurred to prevent the subsurface fire from spreading to those areas of the West Lake Landfill where radiological materials are believed to have been disposed. At this time, Exelon and Generation do not possess sufficient information to assess this claim and therefore are unable to estimate a range of loss, if any. As such, no liability has been recorded for the potential contribution claim. It is reasonably possible, however, that resolution of this matter could have a material, unfavorable impact on Exelon’s and Generation's financial statements.
In January 2018, the PRPs were advised by the EPA that it will begin an additional investigation and evaluation of groundwater conditions at the West Lake Landfill. In September 2018, the PRPs agreed to an Administrative Settlement Agreement and Order on Consent for the performance by the PRPs of the groundwater Remedial
Investigation (RI)/Feasibility Study (FS). The purpose of this RI/FS is to define the nature and extent of any groundwater contamination from the West Lake Landfill site and evaluate remedial alternatives. Generation estimates the undiscounted cost for the groundwater RI/FS to be approximately $30 million. Generation determined a loss associated with the RI/FS is probable and has recorded a liability included in the table above that reflects management’s best estimate of Cotter’s allocable share of the cost among the PRPs. At this time Generation cannot predict the likelihood or the extent to which, if any, remediation activities may be required and therefore cannot estimate a reasonably possible range of loss for response costs beyond those associated with the RI/FS component. It is reasonably possible, however, that resolution of this matter could have a material, unfavorable impact on Exelon’s and Generation’s future financial statements.
In August 2011, Cotter was notified by the DOJ that Cotter is considered a PRP with respect to the government’s clean-up costs for contamination attributable to low level radioactive residues at a former storage and reprocessing facility named Latty Avenue near St. Louis, Missouri. The Latty Avenue site is included in ComEd’s (now Generation's) indemnification responsibilities discussed above as part of the sale of Cotter. The radioactive residues had been generated initially in connection with the processing of uranium ores as part of the U.S. Government’s Manhattan Project. Cotter purchased the residues in 1969 for initial processing at the Latty Avenue facility for the subsequent extraction of uranium and metals. In 1976, the NRC found that the Latty Avenue site had radiation levels exceeding NRC criteria for decontamination of land areas. Latty Avenue was investigated and remediated by the United States Army Corps of Engineers pursuant to funding under FUSRAP. Pursuant to a series of annual agreements since 2011, the DOJ and the PRPs have tolled the statute of limitations until February 28, 2021 so that settlement discussions can proceed. On August 3, 2020, the DOJ advised Cotter and the other PRPs that it is seeking approximately $90 million from all the PRPs and that the PRPs must submit a good faith joint proposed settlement offer by December 1, 2020. Generation has determined that a loss associated with this matter is probable under its indemnification agreement with Cotter and has recorded an estimated liability, which is included in the table above.
Benning Road Site (Exelon, Generation, PHI, and Pepco). In September 2010, PHI received a letter from EPA identifying the Benning Road site as one of six land-based sites potentially contributing to contamination of the lower Anacostia River. A portion of the site was formerly the location of a Pepco Energy Services electric generating facility, which was deactivated in June 2012. The remaining portion of the site consists of a Pepco transmission and distribution service center that remains in operation. In December 2011, the U.S. District Court for the District of Columbia approved a Consent Decree entered into by Pepco and Pepco Energy Services with the DOEE, which requires Pepco and Pepco Energy Services to conduct a RI/FS for the Benning Road site and an approximately 10 to 15-acre portion of the adjacent Anacostia River.
Since 2013, Pepco and Pepco Energy Services (now Generation, pursuant to Exelon's 2016 acquisition of PHI) have been performing RI work and have submitted multiple draft RI reports to the DOEE. In September 2019, Pepco and Generation issued a draft “final” RI report which DOEE approved on February 3, 2020, following a 45-day public comment period and a public meeting. Pepco and Generation are developing a FS to evaluate possible remedial alternatives for submission to DOEE. The Court has established a schedule for completion of the FS, and approval by the DOEE, by September 16, 2021.
DOEE will then prepare a Proposed Plan and issue a Record of Decision identifying any further response actions determined to be necessary, after considering public comment on the Proposed Plan. PHI, Pepco, and Generation have determined that a loss associated with this matter is probable and have accrued an estimated liability, which is included in the table above.
Anacostia River Tidal Reach (Exelon, PHI, and Pepco). Contemporaneous with the Benning Road site RI/FS being performed by Pepco and Generation, DOEE and the National Park Service have been conducting a separate RI/FS focused on the entire tidal reach of the Anacostia River extending from just north of the Maryland-District of Columbia boundary line to the confluence of the Anacostia and Potomac Rivers. The river-wide RI incorporated the results of the river sampling performed by Pepco and Pepco Energy Services as part of the Benning RI/FS, as well as similar sampling efforts conducted by owners of other sites adjacent to this segment of the river and supplemental river sampling conducted by DOEE’s contractor. DOEE asked Pepco, along with parties responsible for other sites along the river, to participate in a "Consultative Working Group" to provide input into the process for future remedial actions and to ensure proper coordination with the other river cleanup efforts currently underway, including cleanup of the river segment adjacent to the Benning Road site resulting from the Benning Road site RI/FS. In addition, the District of Columbia Council directed DOEE to form an official advisory committee made up of members of federal, state, and local environmental regulators, community and
environmental groups, and various academic and technical experts to provide guidance and support to DOEE as the project progressed. This group, called the Anacostia Leadership Council, has met regularly since it was formed. Pepco has participated in the Consultative Working Group. In April 2018, DOEE released a draft RI report for public review and comment. Pepco submitted written comments to the draft RI and participated in a public hearing.
Pepco has determined that it is probable that costs for remediation will be incurred and recorded a liability in the third quarter 2019 for management’s best estimate of its share of those costs based on DOEE’s stated position following a series of meetings attended by representatives from the Anacostia Leadership Council and the Consultative Working Group. On December 27, 2019, DOEE released for review and comment by the public a Focused Feasibility Study (FFS) and a Proposed Plan (PP), and on September 30, 2020, DOEE released its Interim ROD. The Interim ROD reflects an adaptive management approach which will require several identified “hot spots” in the river to be addressed first while continuing to conduct studies and to monitor the river to evaluate improvements and determine potential future remediation plans. The adaptive management process chosen by DOEE is less intrusive, provides more long-term environmental certainty, is less costly, and allows for site specific remediation plans already underway, including the plan for the Benning Road site to proceed to conclusion. Pepco concluded that incremental exposure remains reasonably possible, however management cannot reasonably estimate a range of loss beyond the amounts recorded, which are included in the table above.
In addition to the activities associated with the remedial process outlined above, CERCLA separately requires federal and state (here including Washington, D.C.) Natural Resource Trustees (federal or state agencies designated by the President or the relevant state, respectively, or Indian tribes) to conduct an assessment of any damages to natural resources within their jurisdiction as a result of the contamination that is being remediated. The Trustees can seek compensation from responsible parties for such damages, including restoration costs. The Natural Resource Damages (NRD) assessment typically takes place following cleanup because cleanups sometimes also effectively restore affected natural resources. During the second quarter of 2018, Pepco became aware that the Trustees are in the beginning stages of this process that often takes many years beyond the remedial decision to complete. Pepco has concluded that a loss associated with the eventual NRD assessment is reasonably possible. Due to the very early stage of the assessment process, Pepco cannot reasonably estimate the range of loss.
Litigation and Regulatory Matters
Asbestos Personal Injury Claims (Exelon and Generation). Generation maintains a reserve for claims associated with asbestos-related personal injury actions in certain facilities that are currently owned by Generation or were previously owned by ComEd and PECO. The estimated liabilities are recorded on an undiscounted basis and exclude the estimated legal costs associated with handling these matters, which could be material.
At September 30, 2020 and December 31, 2019, Exelon and Generation had recorded estimated liabilities of approximately $91 million and $83 million, respectively, in total for asbestos-related bodily injury claims. As of September 30, 2020, approximately $27 million of this amount related to 274 open claims presented to Generation, while the remaining $64 million is for estimated future asbestos-related bodily injury claims anticipated to arise through 2055, based on actuarial assumptions and analyses, which are updated on an annual basis. On a quarterly basis, Generation monitors actual experience against the number of forecasted claims to be received and expected claim payments and evaluates whether adjustments to the estimated liabilities are necessary.
It is reasonably possible that additional exposure to estimated future asbestos-related bodily injury claims in excess of the amount accrued could have a material, unfavorable impact on Exelon’s and Generation’s financial statements. However, management cannot reasonably estimate a range of loss beyond the amounts recorded.
City of Everett Tax Increment Financing Agreement (Exelon and Generation). On April 10, 2017, the City of Everett petitioned the Massachusetts Economic Assistance Coordinating Council (EACC) to revoke the 1999 tax increment financing agreement (TIF Agreement) relating to Mystic Units 8 and 9 on the grounds that the total investment in Mystic Units 8 and 9 materially deviates from the investment set forth in the TIF Agreement. On October 31, 2017, a three-member panel of the EACC conducted an administrative hearing on the City’s petition. On November 30, 2017, the hearing panel issued a tentative decision denying the City’s petition, finding that there was no material misrepresentation that would justify revocation of the TIF Agreement. On December 13,
2017, the tentative decision was adopted by the full EACC. On January 12, 2018, the City filed a complaint in Massachusetts Superior Court requesting, among other things, that the court set aside the EACC’s decision, grant the City’s request to decertify the Project and the TIF Agreement, and award the City damages for alleged underpaid taxes over the period of the TIF Agreement. On January 8, 2020, the Massachusetts Superior Court affirmed the decision of the EACC denying the City's petition. The City had until March 9, 2020 to appeal the decision and did not. As a result, the decision is final and the case is resolved. It is reasonably possible that property taxes assessed in future periods, including those following the expiration of the TIF Agreement on June 30, 2020, could be material to Generation’s financial statements.
Deferred Prosecution Agreement (DPA) and Related Matters (Exelon and ComEd). Exelon and ComEd received a grand jury subpoena in the second quarter of 2019 from the U.S. Attorney’s Office for the Northern District of Illinois (USAO) requiring production of information concerning their lobbying activities in the State of Illinois. On October 4, 2019, Exelon and ComEd received a second grand jury subpoena from the USAO requiring production of records of any communications with certain individuals and entities. On October 22, 2019, the SEC notified Exelon and ComEd that it had also opened an investigation into their lobbying activities. On July 17, 2020, ComEd entered into a DPA with the USAO to resolve the USAO investigation. Under the DPA, the USAO filed a single charge alleging that ComEd improperly gave and offered to give jobs, vendor subcontracts, and payments associated with those jobs and subcontracts for the benefit of the Speaker of the Illinois House of Representatives and the Speaker’s associates, with the intent to influence the Speaker’s action regarding legislation affecting ComEd’s interests. The DPA provides that the USAO will defer any prosecution of such charge and any other criminal or civil case against ComEd in connection with the matters identified therein for a three-year period subject to certain obligations of ComEd, including payment to the U.S. Treasury of $200 million, with $100 million payable within thirty days of the filing of the DPA with the United States District Court for the Northern District of Illinois and an additional $100 million within ninety days of such filing date. The payments were recorded within Operating and maintenance expense in Exelon’s and ComEd’s Consolidated Statements of Operations and Comprehensive Income in the second quarter of 2020. The payments will not be recovered in rates or charged to customers and ComEd will not seek or accept reimbursement or indemnification from any source other than Exelon. Exelon made equity contributions to ComEd of $100 million in August 2020 and $100 million in October 2020. On August 13, 2020, a motion was filed in the U.S. District Court for the Northern District of Illinois by and on behalf of ComEd customers seeking to enjoin ComEd from paying these funds to the U.S. Treasury and requiring the U.S. government to establish a victims’ restitution fund from which the $200 million would be disbursed to ComEd customers. The U.S. government and ComEd filed briefs in opposition to this motion. The motion remains pending, and at the U.S. government's direction, the $200 million payment will not be transferred to the U.S. Treasury until the court rules on the motion. $100 million was recorded as Restricted cash and cash equivalents on Exelon’s and ComEd’s Consolidated Balance Sheets as of September 30, 2020 and $100 million was recorded as restricted cash in October 2020.
Exelon was not made a party to the DPA, and therefore the investigation by the USAO into Exelon’s activities ends with no charges being brought against Exelon.
The SEC’s investigation remains ongoing and Exelon and ComEd have cooperated fully and intend to continue to cooperate fully with the SEC. Exelon and ComEd cannot predict the outcome of the SEC investigation. No loss contingency has been reflected in Exelon's and ComEd's consolidated financial statements with respect to the SEC investigation, as this contingency is neither probable nor reasonably estimable at this time.
Subsequent to Exelon announcing the receipt of the subpoenas, various lawsuits have been filed and two demand letters have been received related to the subject of the subpoenas, the conduct described in the DPA and the SEC's investigation, including:
A putative class action lawsuit against Exelon and certain officers of Exelon and ComEd was filed in federal court in December 2019 alleging misrepresentations and omissions in Exelon’s SEC filings related to ComEd’s lobbying activities and the related investigations. The complaint was amended on September 16, 2020, to dismiss two of the original defendants and add other defendants, including ComEd.
A derivative shareholder lawsuit was filed against Exelon, its directors and certain officers of Exelon and ComEd in April 2020 alleging, among other things, breaches of fiduciary duties also purporting to relate to matters that are the subject of the subpoenas and the SEC investigation. The plaintiff voluntarily dismissed this derivative action without prejudice to refile on July 28, 2020.
Three putative class action lawsuits against ComEd and Exelon were filed in Illinois state court in the third quarter of 2020 seeking restitution and compensatory damages on behalf of ComEd customers. These three state cases were consolidated into a single action in October of 2020. In addition, on November 2, 2020, the Citizens Utility Board (CUB) filed a motion to intervene in the state cases pursuant to an Illinois statute allowing the CUB to intervene as a party or otherwise participate on behalf of utility consumers in any proceeding which affects the interest of utility consumers. The CUB has requested that the court stay the state cases pending the resolution of the federal cases, described below.
Four putative class action lawsuits against ComEd and Exelon were filed in federal court in the third quarter of 2020 alleging, among other things, civil violations of federal racketeering laws. In addition, the CUB filed a motion to intervene in these cases on October 22, 2020 and filed a proposed complaint against ComEd in conjunction with that motion alleging Racketeer Influenced and Corrupt Organization Act (RICO) and other causes of action on October 29, 2020.
Two shareholders sent letters to the Exelon Board of Directors in the third quarter of 2020 demanding, among other things, that the Exelon Board of Directors investigate and address alleged breaches of fiduciary duties and other alleged violations by Exelon and ComEd officers and directors related to the conduct described in the DPA.
No loss contingencies have been reflected in Exelon’s and ComEd’s consolidated financial statements with respect to these matters, as such contingencies are neither probable nor reasonably estimable at this time.
General (All Registrants). The Registrants are involved in various other litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or reasonably possible, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. The Registrants maintain accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of reasonably possible loss, particularly where (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss.