XML 55 R12.htm IDEA: XBRL DOCUMENT v3.20.2
Nuclear Decommissioning (Exelon and Generation)
9 Months Ended
Sep. 30, 2020
Asset Retirement Obligation Disclosure [Abstract]  
Nuclear Decommissioning (Exelon and Generation) Nuclear Decommissioning (Exelon and Generation)
Nuclear Decommissioning Asset Retirement Obligations
Generation has a legal obligation to decommission its nuclear power plants following the expiration of their operating licenses. To estimate its decommissioning obligation related to its nuclear generating stations for financial accounting and reporting purposes, Generation uses a probability-weighted, discounted cash flow model which, on a unit-by-unit basis, considers multiple outcome scenarios that include significant estimates and assumptions, and are based on decommissioning cost studies, cost escalation rates, probabilistic cash flow models, and discount rates. Generation updates its ARO annually, unless circumstances warrant more frequent updates, based on its review of updated cost studies and its annual evaluation of cost escalation factors and probabilities assigned to various scenarios.
The financial statement impact for changes in the ARO, on an individual unit basis, due to the changes in and timing of estimated cash flows generally result in a corresponding change in the unit’s ARC within Property, plant, and equipment on Exelon’s and Generation’s Consolidated Balance Sheets. If the ARO decreases for a Non-Regulatory Agreement Unit without any remaining ARC, the corresponding change is recorded as decrease in Operating and maintenance expense within Exelon’s and Generation’s Consolidated Statements of Operations and Comprehensive Income.
The following table provides a rollforward of the nuclear decommissioning ARO reflected in Exelon’s and Generation’s Consolidated Balance Sheets from December 31, 2019 to September 30, 2020:
Nuclear decommissioning ARO at December 31, 2019 (a)
$10,504 
Accretion expense 367 
Net increase due to changes in, and timing of, estimated future cash flows 806 
Costs incurred related to decommissioning plants(59)
Nuclear decommissioning ARO at September 30, 2020 (a)
$11,618 
_________
(a)Includes $93 million and $112 million as the current portion of the ARO at September 30, 2020 and December 31, 2019, respectively, which is included in Other current liabilities in Exelon’s and Generation’s Consolidated Balance Sheets.

During the nine months ended September 30, 2020, the net $806 million increase in the ARO for the changes in the amounts and timing of estimated decommissioning cash flows was driven by updates to Byron and Dresden reflecting changes in assumed retirement dates and assumed methods of decommissioning as a result of the announcement to early retire these plants in 2021. Refer to Note 6 — Early Plant Retirements for additional information.
NDT Funds
Exelon and Generation had NDT funds totaling $13,547 million and $13,353 million at September 30, 2020 and December 31, 2019, respectively. The NDT funds also include $115 million and $163 million for the current portion of the NDT funds at September 30, 2020 and December 31, 2019, respectively, which are included in Other current assets in Exelon's and Generation's Consolidated Balance Sheets. See Note 17 — Supplemental Financial Information for additional information on activities of the NDT funds.
NRC Minimum Funding Requirements
NRC regulations require that licensees of nuclear generating facilities demonstrate reasonable assurance that funds will be available in specified minimum amounts to decommission the facility at the end of its life.
Generation filed its biennial decommissioning funding status report with the NRC on April 1, 2019 for all units, including its shutdown units, except for Zion Station which is included in a separate report to the NRC submitted by ZionSolutions, LLC. The status report demonstrated adequate decommissioning funding assurance as of December 31, 2018 for all units except for Clinton and Peach Bottom Unit 1. As of February 28, 2019, Clinton demonstrated adequate minimum funding assurance due to market recovery and no further action is required. This demonstration was also included in the April 1, 2019 submittal. On March 31, 2020, Generation filed its annual decommissioning funding status report with the NRC for Generation’s shutdown units (excluding Zion
Station for the reason noted above). The annual status report demonstrated adequate decommissioning funding assurance as of December 31, 2019, for all of its shutdown reactors except for Peach Bottom Unit 1. As a former PECO plant, financial assurance for decommissioning Peach Bottom Unit 1 is provided by the NDT fund, collections from PECO ratepayers, and the ability to adjust those collections in accordance with the approved PAPUC tariff. No additional actions are required aside from the PAPUC filing in accordance with the tariff.  See Note 9 — Asset Retirement Obligations of the Exelon 2019 Form 10-K for information regarding the amount collected from PECO ratepayers for decommissioning cost.
Generation will file its next decommissioning funding status report with the NRC by March 31, 2021. This report will reflect the status of decommissioning funding assurance as of December 31, 2020 and will include the impact of the announced early retirement of Byron and Dresden. A shortfall could require Exelon to post parental guarantee for Generation’s share of the funding assurance. However, the amount of any required guarantee will ultimately depend on the decommissioning approach adopted at Byron and Dresden, the associated level of costs, and the decommissioning trust fund investment performance going forward.