Note 7. Commitments and Contingencies

Litigation

We are involved in various lawsuits, claims and regulatory proceedings incidental to our businesses.  We are also subject to audits for various taxes (income, sales and use, and severance) in the various states in which we operate, and from time to time receive assessments for potential taxes that we may owe. While we currently believe that the ultimate outcome of these proceedings, individually and in the aggregate, will not have a material adverse effect on our financial position, results of operations or cash flows, litigation is subject to inherent uncertainties.  We accrue for losses from litigation and claims if we determine that a loss is probable and the amount can be reasonably estimated.

Riley Ridge Helium Supply Contract Claim

As part of our 2010 and 2011 acquisitions of the Riley Ridge Unit and associated gas processing facility that was under construction, the Company assumed a 20-year helium supply contract under which we agreed to supply the helium separated from the full well stream by operation of the gas processing facility to a third-party purchaser, APMTG Helium, LLC (“APMTG”). The helium supply contract provides for the delivery of a minimum contracted quantity of helium, with liquidated damages payable if specified quantities of helium are not supplied in accordance with the terms of the contract. The liquidated damages are specified in the contract at up to $8.0 million per contract year and are capped at an aggregate of $46.0 million over the term of the contract.

As the gas processing facility has been shut-in since mid-2014 due to significant technical issues, we have not been able to supply helium under the helium supply contract. In a case filed in November 2014 in the Ninth Judicial District Court of Sublette County, Wyoming, APMTG claimed multiple years of liquidated damages for non-delivery of volumes of helium specified under the helium supply contract. The Company claimed that its contractual obligations were excused by virtue of events that fall within the force majeure provisions in the helium supply contract.

On March 11, 2019, the trial court entered a final judgment that a force majeure condition did exist, but the Company’s performance was excused by the force majeure provisions of the contract for only a 35-day period in 2014, and as a result the Company should pay APMTG liquidated damages and interest thereon for those time periods from contract commencement to the close of evidence (November 29, 2017) when the Company’s performance was not excused as provided in the contract. The Company has filed a notice of appeal of the trial court’s ruling to the Wyoming Supreme Court, the results of which cannot be predicted at this time.

The Company’s position continues to be that its contractual obligations have been and continue to be excused by events that fall within the force majeure provisions in the helium supply contract. The Company intends to continue to vigorously defend its position and pursue all of its rights.

Absent reversal of the trial court’s ruling on appeal, the Company anticipates total liquidated damages would equal the $46.0 million aggregate cap under the helium supply contract (including $14.2 million of liquidated damages for the contract years ending July 31, 2018 and July 31, 2019) plus $4.2 million of associated costs (through June 30, 2019), for a total of $50.2 million, included in “Other liabilities” in our Unaudited Condensed Consolidated Balance Sheets as of June 30, 2019.