Commitments and Contingencies
3 Months Ended
Mar. 31, 2018
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Note 7. Commitments and Contingencies

Litigation

We are involved in various lawsuits, claims and regulatory proceedings incidental to our businesses.  We are also subject to audits for various taxes (income, sales and use, and severance) in the various states in which we operate, and from time to time receive assessments for potential taxes that we may owe. While we currently believe that the ultimate outcome of these proceedings, individually and in the aggregate, will not have a material adverse effect on our financial position, results of operations or cash flows, litigation is subject to inherent uncertainties.  Although a single or multiple adverse rulings or settlements could possibly have a material adverse effect on our finances, we only accrue for losses from litigation and claims if we determine that a loss is probable and the amount can be reasonably estimated.

Riley Ridge Helium Supply Contract Claim

As part of our 2010 and 2011 acquisitions of the Riley Ridge Unit and associated gas processing facility that was under construction, the Company assumed a 20-year helium supply contract under which we agreed to supply the helium separated from the full well stream by operation of the gas processing facility to a third-party purchaser, APMTG Helium, LLC.  The helium supply contract provides for the delivery of a minimum contracted quantity of helium, subject to adjustment after startup of the Riley Ridge gas processing facility, with liquidated damages payable if specified quantities of helium are not supplied in accordance with the terms of the contract. The liquidated damages are specified in the contract at up to $8.0 million per contract year and are capped at an aggregate of $46.0 million over the term of the contract. As the gas processing facility has been shut-in since mid-2014, we have not been able to supply helium under the helium supply contract.  APMTG Helium, LLC filed a case in November 2014 in the Ninth Judicial District Court of Sublette County, Wyoming, claiming multiple years of liquidated damages for non-delivery of volumes of helium specified under the helium supply contract. The Company’s position is that our contractual obligations are excused by virtue of events that fall within the force majeure provisions in the helium supply contract. The evidentiary phase of the trial closed on November 29, 2017. The parties submitted written closing briefs and rebuttal briefs to the District Court during February and April of 2018. We currently expect a ruling from the District Court to be made in the second or third quarter of 2018. The Company plans to continue to vigorously defend its position, but we are unable to predict at this time the outcome of this dispute.