2016 Electric Rate Case Filing
DTE Electric filed a rate case with the MPSC on February 1, 2016 requesting an increase in base rates of $344 million based on a projected twelve-month period ending July 31, 2017. On August 1, 2016, DTE Electric self-implemented a base rate increase of $245 million. On January 31, 2017, the MPSC issued an order approving an annual revenue increase of $184 million for service rendered on or after February 7, 2017. The MPSC authorized a return on equity of 10.1%. On April 28, 2017, DTE Electric filed to refund its customers their pro-rata share of the revenue collected through the self-implementation surcharge in effect from August 1, 2016 through February 7, 2017. On September 15, 2017, the MPSC approved a settlement authorizing DTE Electric to refund its customers $38.5 million of the self-implementation surcharge during the months of October through December 2017. DTE has recorded a refund liability for the settlement as of September 30, 2017.
2017 Electric Rate Case Filing
DTE Electric filed a rate case with the MPSC on April 19, 2017 requesting an increase in base rates of $231 million based on a projected twelve-month period ending October 31, 2018. The requested increase in base rates is primarily due to an increase in net plant resulting from infrastructure investments, environmental compliance, and reliability improvement projects. The rate filing also includes projected changes in sales, operation and maintenance expenses, and working capital. The rate filing also requests an increase in return on equity from 10.1% to 10.5%. To mitigate the impact to its customers resulting from ASU No. 2017-07, Compensation Retirement Benefits (Topic 715), DTE Electric suggested regulatory accounting treatment for the pension and postretirement cost components previously included as capital overhead. If the MPSC adopts DTE Electric's suggestion, the rate request will be reduced. For further discussion of ASU No. 2017-07, see Note 3 to the Consolidated Financial Statements, "New Accounting Pronouncements." On September 8, 2017, DTE Electric filed an application with the MPSC for a $125 million self-implemented base rate increase effective November 1, 2017. A final MPSC order in this case is expected by April 2018.
PSCR Proceedings
The PSCR process is designed to allow DTE Electric to recover all of its power supply costs if incurred under reasonable and prudent policies and practices. DTE Electric's power supply costs include fuel and related transportation costs, purchased and net interchange power costs, NOx and SO2 emission allowances costs, urea costs, transmission costs, MISO, and other related costs. The MPSC reviews these costs, policies, and practices for prudence in annual plan and reconciliation filings.
2015 PSCR Year — In March 2016, DTE Electric filed its 2015 PSCR reconciliation that included the recovery of approximately $13 million of costs related to the pass through of a billing adjustment associated with a previous MPSC ordered customer refund. On July 12, 2017, the MPSC issued an order that disallowed recovery of this 2015 PSCR billing adjustment pass through of approximately $16 million, inclusive of interest. DTE Electric recorded the impact of the disallowance in the second quarter of 2017 and filed a claim of appeal with the Michigan Court of Appeals in August 2017.
Certificate of Necessity
On July 31, 2017, DTE Electric filed a request for authority to build a 1,100 megawatt natural gas fueled combined cycle generation facility at DTE Electric's Belle River Power Plant. DTE Electric requested the MPSC to issue three CONs for the following: (1) power supplied by the proposed project is needed, (2) the size, fuel type, and other design characteristics of the proposed project represent the most reasonable and prudent means of meeting the power need, and (3) the estimated capital costs of $989 million for the proposed project will be recoverable in rates from DTE Electric's customers. DTE Electric also reserved the right to revise, amend, or otherwise change the relief it is requesting in any way appropriate, including updating of the cost estimate within the 150 days of the filing date. DTE Electric expects an order in this proceeding from the MPSC by April 28, 2018.