XML 124 R15.htm IDEA: XBRL DOCUMENT v2.4.1.9
Asset Retirement Obligations (Notes)
12 Months Ended
Dec. 31, 2014
Asset Retirement Obligation Disclosure [Abstract]  
Asset Retirement Obligations
ASSET RETIREMENT OBLIGATIONS
The Company has a legal retirement obligation for the decommissioning costs for its Fermi 1 and Fermi 2 nuclear plants, dismantlement of facilities located on leased property and various other operations. The Company has conditional retirement obligations for gas pipelines, asbestos and PCB removal at certain of its power plants and various distribution equipment. The Company recognizes such obligations as liabilities at fair market value when they are incurred, which generally is at the time the associated assets are placed in service. Fair value is measured using expected future cash outflows discounted at our credit-adjusted risk-free rate. In its regulated operations, the Company recognizes regulatory assets or liabilities for timing differences in expense recognition for legal asset retirement costs that are currently recovered in rates.
If a reasonable estimate of fair value cannot be made in the period in which the retirement obligation is incurred, such as for assets with indeterminate lives, the liability is recognized when a reasonable estimate of fair value can be made. Natural gas storage system assets, substations, manholes and certain other distribution assets have an indeterminate life. Therefore, no liability has been recorded for these assets.
A reconciliation of the asset retirement obligations for 2014 follows:
 
(In millions)
Asset retirement obligations at December 31, 2013
$
1,827

Accretion
112

Liabilities incurred
11

Liabilities settled
(12
)
Revision in estimated cash flows
24

Asset retirement obligations at December 31, 2014
$
1,962


Approximately $1.7 billion of the asset retirement obligations represent nuclear decommissioning liabilities that are funded through a surcharge to electric customers over the life of the Fermi 2 nuclear plant. The NRC has jurisdiction over the decommissioning of nuclear power plants and requires minimum decommissioning funding based upon a formula. The MPSC and FERC regulate the recovery of costs of decommissioning nuclear power plants and both require the use of external trust funds to finance the decommissioning of Fermi 2. Rates approved by the MPSC provide for the recovery of decommissioning costs of Fermi 2 and the disposal of low-level radioactive waste. DTE Electric is continuing to fund FERC jurisdictional amounts for decommissioning even though explicit provisions are not included in FERC rates. The Company believes the MPSC and FERC collections will be adequate to fund the estimated cost of decommissioning. The decommissioning assets, anticipated earnings thereon and future revenues from decommissioning collections will be used to decommission Fermi 2. The Company expects the liabilities to be reduced to zero at the conclusion of the decommissioning activities. If amounts remain in the trust funds for Fermi 2 following the completion of the decommissioning activities, those amounts will be disbursed based on rulings by the MPSC and FERC.
A portion of the funds recovered through the Fermi 2 decommissioning surcharge and deposited in external trust accounts is designated for the removal of non-radioactive assets and returning the site to greenfield. This removal and greenfielding is not considered a legal liability. Therefore, it is not included in the asset retirement obligation, but is reflected as the Nuclear decommissioning liability. The decommissioning of Fermi 1 is funded by DTE Electric. Contributions to the Fermi 1 trust are discretionary. For additional discussion of Nuclear decommissioning trust fund assets see Note 11 to the Consolidated Financial Statements, "Fair Value".