In March 2013, we entered into an operating lease for a new digital print and distribution center. The term of the lease is seven years but includes an exit right after five years with payment of an exit fee. Payments under the lease are approximately $1,400 per year and began April 1, 2013.
Contingencies
The Company has participated with other Potentially Responsible Parties (“PRPs”) in the investigation, study, and remediation of the Pasco Sanitary Landfill Superfund Site (the “Pasco Site”) in eastern Washington State since 1998. The Company is a member of a PRP Group known as the Industrial Waste Area Generators Group III (the “IWAG Group”). The IWAG Group and several other PRP groups have entered into agreed orders with the Department of Ecology for implementation of interim remedial actions and expansion of groundwater monitoring. At this time, an agreement has not yet been reached on the final remediation approach. We have accrued our best estimate of our obligation and have an undiscounted long-term liability of $1,272 that we currently believe is adequate to cover our portion of the total future potential costs of remediation. We expect the costs to be incurred over a period of 60 years; however, the current proposed remediation approach could require monitoring for a longer period of time. This estimate is contingent upon the final remedy agreed upon, the participation of other PRPs not currently in the IWAG Group III, the length of monitoring required, and the final agreed upon allocation. Until a final remediation approach is approved and a final agreement is reached among all PRPs, it is reasonably possible that one or more of these factors could change our estimate; however, we are unable to determine the impact at this time.
The Company participates with other PRPs in the investigation, study, and remediation of the Valleycrest Landfill Site (the “Valleycrest Site”) in western Ohio. The Company is a member of a PRP Group known as the Valleycrest Landfill Site Group (the “VLSG”). A remedial investigation and feasibility study was conducted by the VLSG which indicated a range of viable remedial approaches. At this time, a final remediation approach has not been selected, and we have accrued the estimate of our obligation based on the most likely approach being considered by the U.S. Environmental Protection Agency. We have an undiscounted long-term liability of $2,382 that we currently believe is adequate to cover our portion of the total future potential costs of remediation, which are expected to be incurred over a period of 30 years. This estimate is contingent upon the final remedy agreed upon, the participation of other PRPs not currently in the VLSG, and the final agreed upon allocation. Until a final remediation approach is approved and a final agreement is reached among all PRPs, it is reasonably possible that one or more of these factors could change our estimate; however, we are unable to determine the impact at this time.
Commitments Related to the WorkflowOne Acquisition
As a result of the Acquisition, additional commitments were assumed that were not previously disclosed. WorkflowOne leases various types of warehouse and office facilities, equipment, and furniture and fixtures under non-cancelable lease agreements that expire through 2020. Future minimum lease payments under operating leases, as disclosed in the WorkflowOne 2012 audited financial statements included as an exhibit to the 8/K-A for Standard Register filed on October 15, 2013, are as follows:
2013
$
16,136

2014
13,406

2015
10,067

2016
4,442

2017
1,602

Later years
3,317

Total
$
48,970