Debt
Debt with recourse to EME totaled $3.7 billion and is classified as part of liabilities subject to compromise (LSTC) as of December 31, 2013 and December 31, 2012. Nonrecourse debt, as summarized below, is debt whereby lenders rely on specific project assets to repay such obligations. The following table summarizes long-term debt (rates and terms as of December 31, 2013), excluding LSTC:
(in millions)
Current Rate1
 
Effective Interest Rate2
 
Maturity Date
 
December 31, 2013
 
December 31, 2012
Walnut Creek Energy
   Term Loan
2.50%
LIBOR+2.25%
 
5.46%
 
May 2023
 
$
417

 
$
330

WCEP Holdings, LLC Term Loan
4.24%
LIBOR+4.00%
 
7.63%
 
May 2023
 
53

 
52

Big Sky Wind, LLC
Vendor financing loan
3.87%
LIBOR+3.50%
 
3.87%
 
October 2014
 
231

 
222

High Lonesome Mesa, LLC 
   Bonds
6.85%
Fixed
 
6.85%
 
November 2017
 
65

 
69

American Bituminous Power Partners, L.P.3 
Bonds
0.05%
Floating
 
0.05%
 
October 2017
 
39

 
46

Viento Funding II, Inc.
Term Loan
3.10%
LIBOR+2.75%
 
5.61%
 
July 2023
 
200

 
191

Tapestry Wind, LLC
Term Loan
2.75%
LIBOR+2.50%
 
4.51%
 
December 2021
 
201

 
210

Cedro Hill Wind, LLC
Term Loan
3.38%
LIBOR+3.13%
 
7.01%
 
December 2025
 
118

 
125

Laredo Ridge
Term Loan
3.00%
LIBOR+2.75%
 
5.90%
 
March 2026
 
69

 
71

Crofton Bluffs Wind, LLC
Term Loan
4
3.12%
LIBOR+2.88%
 
5.37%
 
December 2027
 
26

 
27

Broken Bow Wind, LLC
Term Loan
4
3.12%
LIBOR+2.88%
 
5.56%
 
December 2027
 
50

 
52

Others
Various
 
Various
 
Various
 
29

 
43

Total debt
 
 
 
 
 
 
$
1,498

 
$
1,438

Less: Short-term debt
 
 
 
 
 
 
4

 
382

Total long-term debt
 
 
 
 
 
 
1,494

 
1,056

Less: Current maturities of long-term debt
 
 
 
 
 
 
323

 
307

Long-term debt, net of current portion
 
 
 
 
 
 
$
1,171

 
$
749

1 
London Interbank Offered Rate (LIBOR)
2 
The effective rate at which interest expense is reflected in the financial statements after the consideration of the current rate of debt and any amounts subject to interest rate swaps. For further discussion, see Note 6—Derivative Instruments and Hedging Activities—Interest Rate Risk Management.
3 
Principal payments are due annually through October 1, 2017. Interest rates are reset weekly based on current bond yields for similar securities. On October 1, 2013, American Bituminous Power Partners, L.P. (Ambit) made the required annual principal payment to bondholders by drawing on its line of credit. The current interest rate on this short-term debt is 5.25%. Ambit was unable to fully reimburse the draw down which is a potential event of default. However, Ambit and various counterparties, including the line of credit issuer, executed an agreement effective October 1, 2013 to waive any event of default.
4 
The interest rate swaps for this obligation expired in December 2013 and forward starting rate swaps became effective. For additional information, see Note 6—Derivative Instruments and Hedging Activities.
Long-term debt maturities at December 31, 2013, for the next five years are summarized as follows: $323 million in 2014, $93 million in 2015, $91 million in 2016, $141 million in 2017, and $91 million in 2018.
Chapter 11 Cases
The filing of the Chapter 11 Cases constitutes an event of default under various financing documents as summarized below.
Senior Notes
The filing of the Chapter 11 Cases may constitute an event of default under EME's senior notes and, as a result, the principal and interest due under these debt instruments are immediately due and payable. The creditors are stayed from taking any action as a result of the default under Section 362 of the Bankruptcy Code and the obligations related to the senior notes are recorded as part of LSTC. For additional information, see Note 16—Restructuring Activities.
Viento II Financing
In July 2013, EME completed, through its subsidiary, Viento Funding II, Inc., an amendment of its Viento II Financing, a nonrecourse financing of its interests in the Wildorado, San Juan Mesa and Elkhorn Ridge wind projects. The amendment increased the financing amount to $238 million, which included a $202 million 10-year partially amortizing term loan, a $27 million 7-year letter of credit facility and a $9 million 7-year working capital facility. Interest under the term loan accrues at LIBOR plus 2.75% initially with the rate increasing 0.25% on every fourth anniversary. EME reaffirmed the pledge of its interest in Viento Funding II, Inc. in connection with the amendment but is not a borrower or a guarantor. The amendment cured any possible event of default, and therefore the Viento Funding II debt was classified as a long-term liability on the consolidated balance sheets.
Viento Funding II terminated $78 million amortizing notional amount 3.415% interest rate swap agreements and entered into several tranches of new interest rate swap agreements to hedge the majority of exposure to fluctuations in interest rates. As a result of the termination, EME wrote off $4 million of unamortized deferred financing costs as a loss on early extinguishment of debt in the consolidated statements of operations. For additional information, see Note 6—Derivative Instruments and Hedging Activities—Interest Rate Risk Management.
High Lonesome Financing
The filing of the Chapter 11 Cases constitutes an event of default under the documents governing the issuance of the Series 2010A and 2010B Bonds (the Bonds). In July 2013, the applicable bondholders granted a permanent waiver of default, subject to EME assuming the state production tax credit agreement in the Chapter 11 Cases. Pursuant to assumption and rejection procedures previously approved by the Bankruptcy Court, EME assumed the agreement effective as of July 15, 2013. As of December 31, 2013, there were $40 million and $25 million outstanding under the Series 2010A and Series 2010B Bonds, respectively, and $7 million of outstanding letters of credit.
Credit Facilities and Letters of Credit
During 2013, EME terminated its letter of credit facility with DNB Bank and, through its subsidiaries, completed new letter of credit facilities totaling $101 million. The new letter of credit facilities consist of $75 million at Edison Mission Wind, expiring April 30, 2016, $10 million at Mountain Wind Power LLC, expiring September 17, 2020 and $16 million at Mountain Wind Power II, LLC, expiring September 17, 2020. Through its subsidiaries, EME has a total letter of credit capacity of $292 million.
At December 31, 2013, EME's subsidiaries' had issued letters of credit aggregating $163 million supported by $22 million of cash collateral. The outstanding letters of credit were scheduled to expire as follows: $59 million in 2014, $17 million in 2017, $9 million in 2018, $27 million in 2020, $18 million in 2021, $13 million in 2022 and $20 million in 2023. Certain letters of credit are subject to automatic renewal provisions. Included in the outstanding letters of credit were $22 million issued in connection with the power purchase agreement with Southern California Edison Company (SCE), an affiliate of EME, under the Walnut Creek credit facility.
2012 Financings
Broken Bow I and Crofton Bluffs
Effective March 30, 2012, EME, through its subsidiaries, Broken Bow Wind, LLC (Broken Bow I) and Crofton Bluffs Wind, LLC (Crofton Bluffs), completed two nonrecourse financings of its interests in the Broken Bow I and Crofton Bluffs wind projects. The financings included construction loans totaling $79 million that were converted to 15-year amortizing term loans on December 21, 2012 and December 14, 2012 for Broken Bow I and Crofton Bluffs, respectively, $13 million of letter of credit facilities and $6 million of working capital facilities.
Interest under the term loans will accrue at LIBOR plus 2.88%, with the term loan rate increasing 0.13% after the third, sixth, ninth, and twelfth years. As of December 31, 2013, Broken Bow I and Crofton Bluffs have $50 million and $26 million outstanding under the term loans, respectively, and $10 million and $3 million of outstanding letters of credit, respectively.
2011 Financings
Tapestry Wind
In December 2011, EME, through its subsidiary, Tapestry Wind, LLC, completed a nonrecourse financing of its interests in the Taloga, Buffalo Bear and Pinnacle wind projects. The financing included a $214 million 10-year partially amortizing term loan, a $12 million 10-year debt service reserve letter of credit facility, an $8 million 10-year project letter of credit facility and an $8 million 10-year working capital facility. Interest under the term loans accrues at LIBOR plus 2.5% initially, with the rate increasing 0.13% on the fourth and eighth anniversary of the closing date.
A total of $97 million of cash proceeds received from the 10-year term loan was deposited into an escrow account as of December 2011 pending completion of the Pinnacle wind project. During 2012, certain neighbors of the Pinnacle wind project filed civil complaints alleging, among other things, that the noise emissions and shadow flicker from the Pinnacle wind farm constituted a nuisance and seeking compensatory damages, punitive damages and other equitable relief. During the fourth quarter of 2012, all of the civil complaints were settled and the escrowed loan proceeds were released to Tapestry Wind, LLC. At December 31, 2013, there was $201 million outstanding under the loan and $20 million of outstanding letters of credit.
Walnut Creek
In July 2011, EME completed, through two wholly owned subsidiaries, Walnut Creek Energy and WCEP Holdings, LLC, nonrecourse financings to fund construction of the Walnut Creek gas-fired project. The financings included floating rate construction loans totaling $495 million that converted to 10-year amortizing term loans in June 2013, which is when Walnut Creek started earning revenues under its long-term purchase power agreement.
Big Sky Turbine Financing
In October 2009, EME's subsidiary, Big Sky Wind, LLC (Big Sky), entered into turbine financing arrangements with the turbine manufacturer Suzlon Wind Energy Corporation (Suzlon) for wind turbine purchase obligations related to the 240 MW Big Sky wind project. The loan associated with the financing agreement has a five-year final maturity. However, the satisfaction of certain criteria, including project performance and absence of serial defects, may trigger earlier repayment. In September 2012, Suzlon sued Big Sky in New York federal court seeking a declaratory judgment that the early repayment provisions had been satisfied and that Big Sky should be required to repay the loan in full in February 2013. Big Sky answered Suzlon's complaint, denied the allegations and counterclaimed. The counterclaim alleged that certain serial defects existing in the turbine equipment supplied by Suzlon precluded application of the early repayment provisions. The litigation is still pending in New York federal court. The Big Sky loan is secured by a leasehold mortgage on the project's real property assets, a pledge of all other collateral of the Big Sky wind project, as well as a cash reserve account into which one-third of distributable cash flow, if any, of the Big Sky wind project is to be deposited on a monthly basis. The loan is also secured by pledges of Big Sky's direct and indirect ownership interests in the project, but is nonrecourse to EME. For further details regarding consolidated assets pledged as security for debt obligations, see Note 3—Variable Interest Entities.
As of December 31, 2013, there was $231 million outstanding under the vendor financing loan at an effective interest rate of 3.87%. EME has been in discussions with Suzlon regarding a potential sale of EME's interest in the Big Sky wind project in exchange for forgiveness of debt and other consideration. These discussions are ongoing and EME has not made any decisions with respect to a potential sale. As a result, Big Sky's long-lived assets, consisting of property, plant and equipment and deferred revenue, were evaluated for impairment under the Held for Use model of Accounting Standards Codification 360 Property, Plant, and Equipment (ASC 360). The probability weighted future undiscounted cash flows associated with this asset group exceeded its carrying value at December 31, 2013 and consequently no impairment has been recognized. If EME and Suzlon do agree upon a sale transaction under terms similar to those currently under discussion, EME would record a material loss. If EME and Suzlon do not agree upon a sale transaction, Big Sky will need to arrange alternative financing, if available, to repay the loan at maturity or reach agreement with the lender to extend the maturity date of the loan. EME does not intend to make an investment in the project and is under no obligation to do so. If a restructuring of the loan or a sale effort is unsuccessful, Suzlon may foreclose on the project resulting in a write-off of the entire investment in the project. At December 31, 2013, EME's investment in the Big Sky wind project consisted of assets of $447 million and liabilities of $369 million.
Debt Covenants
Certain project financings contain covenants and restriction requirements to meet certain financial ratios and reporting requirements. Distributions from projects are typically restricted if covenant requirements are not met. Key existing covenants of EME's non-debtor subsidiaries include:
Debt Service Coverage Ratio1
Covenant Level
 
Actual Performance as of December 31, 2013
 
High Lonesome
1.20 to 1.00
 
 
1.88
2 
 
Viento II
1.40 to 1.00
 
 
2.75
 
 
Tapestry Wind
1.20 to 1.00
 
 
1.48
 
 
Laredo Ridge
1.20 to 1.00
 
 
1.79
 
 
Cedro Hill
1.20 to 1.00
 
 
1.53
 
 
Broken Bow
1.20 to 1.00
 
 
1.67
 
 
Crofton Bluffs
1.20 to 1.00
 
 
2.23
 
 
Walnut Creek Energy3
1.20 to 1.00
 
 
N/A
 
 
WCEP Holdings, LLC3
2.50 to 1.00
 
 
N/A
 
 
Required reserve account balance4
 
 
 
 
 
 
Ambit
Twenty million
 
 
Four million
 
1 
The Debt Service Coverage Ratio (DSCR) is typically calculated over a 12-month historical period and is individually defined for each borrowing in the applicable financing agreement, credit agreement, trust indenture, or other document governing the financing requirements.
2 
Calculated at October 31, 2013, the last payment date.
3 
Commercial operations started in the second quarter of 2013.
4 
Ambit is required to maintain funded reserve accounts primarily for debt servicing and maintenance costs. The underfunded reserve does not create an event of default under the loan but does restrict distributions from Ambit.
EME's non-debtor subsidiaries were in compliance with all of their debt covenants at December 31, 2013 except for the required reserve amount at Ambit. Accordingly, the net assets of Ambit are considered restricted. Restricted net assets are those that cannot be transferred to EME in the form of loans, advances, or cash dividends without the consent of third parties, typically lenders or partners. In addition to Ambit, EME also has partnership agreements which require partners' approval for distributions and financing agreements which require the minimum reserve or operating account funding levels. Net assets are considered restricted if distributions are dependent upon approval by EME's unaffiliated partners. At December 31, 2013, restricted net assets of EME's subsidiaries was $1.7 billion.