XML 108 R92.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies (Lease Commitments) (Details) (USD $)
In Millions, unless otherwise specified
1 Months Ended 12 Months Ended
Jan. 02, 2013
Dec. 31, 2012
Dec. 31, 2011
Dec. 31, 2010
Commitments and Guarantees        
Capital Leased Assets, Gross   $ 4    
Future minimum payments for lease financing:        
Operating lease expense   108 110 112
Capital leases, accumulated amortization   (1)    
Midwest Generation LLC
       
Commitments and Guarantees        
Capital Leased Assets, Gross   4    
Future minimum payments for lease financing:        
Operating lease expense   14 16 17
Lease payments not paid 76      
Rent paid for sales leaseback transaction 7      
Capital leases, accumulated amortization   1    
Current portion of lease financings   6 116  
Lease financings, net of current portion   2 439  
Powerton and Joliet Power Stations
       
Future minimum payments for operating leases:        
Future minimum payments, 2013   151 [1]    
Future minimum payments, 2014   151 [1]    
Future minimum payments, 2015   67 [1]    
Future minimum payments, 2016   26 [1]    
Future minimum payments, 2017   1 [1]    
Future minimum payments, thereafter   240 [1]    
Total future commitments   636 [1]    
Other Operating Leases
       
Future minimum payments for operating leases:        
Future minimum payments, 2013   19    
Future minimum payments, 2014   17    
Future minimum payments, 2015   17    
Future minimum payments, 2016   13    
Future minimum payments, 2017   15    
Future minimum payments, thereafter   130    
Total future commitments   211    
Other Operating Leases | Midwest Generation LLC
       
Future minimum payments for operating leases:        
Future minimum payments, 2013   8    
Future minimum payments, 2014   7    
Future minimum payments, 2015   7    
Future minimum payments, 2016   5    
Future minimum payments, 2017   5    
Future minimum payments, thereafter   6    
Total future commitments   38    
LSTC
       
Future minimum payments for operating leases:        
Future minimum payments, 2013   10    
Future minimum payments, 2014   0    
Future minimum payments, 2015   0    
Future minimum payments, 2016   0    
Future minimum payments, 2017   0    
Future minimum payments, thereafter   0    
Total future commitments   10    
LSTC | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Future minimum payments, 2013   129    
Future minimum payments, 2014   133    
Future minimum payments, 2015   58    
Future minimum payments, 2016   23    
Future minimum payments, 2017   0    
Future minimum payments, thereafter   101    
Total future commitments   444    
Powerton and Joliet Power Stations | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Future minimum payments, 2013   7    
Future minimum payments, 2014   2    
Future minimum payments, 2015   0    
Future minimum payments, 2016   0    
Future minimum payments, 2017   0    
Future minimum payments, thereafter   0    
Total future commitments   9    
Amount representing interest   1    
Net commitments   8    
Railcars | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Number of units under operating lease   3,200    
Number of units under rejected operating lease contract   1,275    
Barges | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Number of units under rejected operating lease contract   11    
Accrued Liabilities and Other
       
Future minimum payments for lease financing:        
Current portion of lease financings   1    
Other Long-Term Liabilities
       
Future minimum payments for lease financing:        
Lease financings, net of current portion   2    
Current Portion of Lease Financings | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Current portion of lease financings   1    
Lease Financings, Net of Current Portion | Midwest Generation LLC
       
Future minimum payments for lease financing:        
Lease financings, net of current portion   $ 2    
[1] Reflects principal and interest payments related to the Powerton and Joliet Sale Leaseback.