Commitments and Contingencies - PAC - Hydroelectric (Details)
$ in Millions
12 Months Ended
Dec. 31, 2021
USD ($)
Hydroelectric [Line Items]  
Capital expenditures required by hydroelectric licenses, period 10 years
PAC  
Hydroelectric [Line Items]  
Capital expenditures required by hydroelectric licenses $ 193
Klamath Hydroelectric System | PAC  
Hydroelectric [Line Items]  
Dam removal cost limit 200
Additional dam removal costs, California bond measure 250
Additional contingency funding 45
Hydroelectric dam removal cost funding 450
Klamath relicensing and settlement costs $ 14