Contractual Obligation, Fiscal Year Maturity Schedule
The Company has the following firm commitments that are not reflected on the Consolidated Balance Sheet. Minimum payments as of December 31, 2019 are as follows (in millions):
 
 
 
 
 
 
 
 
 
 
 
 
2025 and
 
 
 
 
2020
 
2021
 
2022
 
2023
 
2024
 
Thereafter
 
Total
Contract type:
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Fuel, capacity and transmission contract commitments
 
$
2,218

 
$
1,527

 
$
1,193

 
$
1,093

 
$
1,088

 
$
13,584

 
$
20,703

Construction commitments
 
1,682

 
521

 
27

 
2

 
8

 

 
2,240

Easements
 
62

 
68

 
70

 
72

 
70

 
2,259

 
2,601

Maintenance, service and other contracts
 
669

 
342

 
324

 
300

 
255

 
1,624

 
3,514

 
 
$
4,631

 
$
2,458

 
$
1,614

 
$
1,467

 
$
1,421

 
$
17,467

 
$
29,058

PacifiCorp [Member]  
Contractual Obligation [Line Items]  
Contractual Obligation, Fiscal Year Maturity Schedule
PacifiCorp has the following firm commitments that are not reflected on the Consolidated Balance Sheet. Minimum payments as of December 31, 2019 are as follows (in millions):

 
2020
 
2021
 
2022
 
2023
 
2024
 
2025 and Thereafter
 
Total
Contract type:
 
 
 
 
 
 
 
 
 
 
 
 
 
Purchased electricity contracts -
 
 
 
 
 
 
 
 
 
 
 
 
 
commercially operable
$
279

 
$
177

 
$
174

 
$
168

 
$
164

 
$
1,810

 
$
2,772

Purchased electricity contracts -
 
 
 
 
 
 
 
 
 
 
 
 
 
non-commercially operable
7

 
52

 
52

 
53

 
53

 
987

 
1,204

Fuel contracts
832

 
519

 
316

 
245

 
248

 
775

 
2,935

Construction commitments
844

 
6

 

 

 
4

 

 
854

Transmission
101

 
86

 
77

 
71

 
56

 
429

 
820

Easements
10

 
12

 
12

 
12

 
11

 
349

 
406

Maintenance, service and
 
 
 
 
 
 
 
 
 
 
 
 
 
other contracts
329

 
49

 
41

 
34

 
32

 
204

 
689

Total commitments
$
2,402

 
$
901

 
$
672

 
$
583

 
$
568

 
$
4,554

 
$
9,680

MidAmerican Energy Company [Member]  
Contractual Obligation [Line Items]  
Contractual Obligation, Fiscal Year Maturity Schedule
MidAmerican Energy had the following firm commitments that are not reflected on the Balance Sheet. Minimum payments as of December 31, 2019, are as follows (in millions):
 
 
 
 
 
 
 
 
 
 
 
 
2025 and
 
 
 
 
2020
 
2021
 
2022
 
2023
 
2024
 
Thereafter
 
Total
Contract type:
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Coal and natural gas for generation
 
$
114

 
$
52

 
$
48

 
$
39

 
$

 
$

 
$
253

Electric capacity and transmission
 
28

 
24

 
14

 
8

 
7

 
29

 
110

Natural gas contracts for gas operations
 
102

 
61

 
47

 
24

 
8

 
23

 
265

Construction commitments
 
670

 
515

 
27

 
2

 
4

 

 
1,218

Easements
 
32

 
36

 
37

 
38

 
39

 
1,492

 
1,674

Maintenance, services and other
 
198

 
156

 
154

 
155

 
120

 
432

 
1,215

 
 
$
1,144

 
$
844

 
$
327

 
$
266

 
$
178

 
$
1,976

 
$
4,735

Nevada Power Company [Member]  
Contractual Obligation [Line Items]  
Contractual Obligation, Fiscal Year Maturity Schedule
Nevada Power has the following firm commitments that are not reflected on the Consolidated Balance Sheet. Minimum payments as of December 31, 2019 are as follows (in millions):
 
2020
 
2021
 
2022
 
2023
 
2024
 
2025 and Thereafter
 
Total
Contract type:
 
 
 
 
 
 
 
 
 
 
 
 
 
Fuel, capacity and transmission contract commitments
$
539

 
$
390

 
$
319

 
$
321

 
$
324

 
$
3,432

 
$
5,325

Fuel and capacity contract commitments (not commercially operable)
1

 
6

 
41

 
92

 
157

 
4,677

 
4,974

Construction commitments
23

 

 

 

 

 

 
23

Easements
4

 
4

 
5

 
5

 
3

 
43

 
64

Maintenance, service and other contracts
51

 
48

 
43

 
34

 
25

 
18

 
219

Total commitments
$
618

 
$
448

 
$
408

 
$
452

 
$
509

 
$
8,170

 
$
10,605

Sierra Pacific Power Company [Member]  
Contractual Obligation [Line Items]  
Contractual Obligation, Fiscal Year Maturity Schedule
Sierra Pacific has the following firm commitments that are not reflected on the Balance Sheet. Minimum payments as of December 31, 2019 are as follows (in millions):
 
 
 
 
 
 
 
 
 
 
 
2025 and
 
 
 
2020
 
2021
 
2022
 
2023
 
2024
 
Thereafter
 
Total
Contract type:
 
 
 
 
 
 
 
 
 
 
 
 
 
Fuel, capacity and transmission contract commitments
$
260

 
$
198

 
$
114

 
$
84

 
$
83

 
$
863

 
$
1,602

Fuel and capacity contract commitments (not commercially operable)
1

 
11

 
41

 
41

 
42

 
921

 
1,057

Easements
2

 
2

 
2

 
2

 
2

 
30

 
40

Maintenance, service and other contracts
11

 
8

 
7

 
2

 
1

 
9

 
38

Total commitments
$
274

 
$
219

 
$
164

 
$
129

 
$
128

 
$
1,823

 
$
2,737