XML 136 R90.htm IDEA: XBRL DOCUMENT v3.3.1.900
Summary of Significant Accounting Policies - SPPC - Property, Plant and Equipment, Net (Details) - Sierra Pacific Power Company [Member]
12 Months Ended
Dec. 31, 2015
Dec. 31, 2014
Electricity Generation Plant, Non-Nuclear [Member]    
Property, Plant and Equipment [Line Items]    
Public Utilities, Allowance for Funds Used During Construction, Rate 7.62% 7.58%
Natural Gas Processing Plant [Member]    
Property, Plant and Equipment [Line Items]    
Public Utilities, Allowance for Funds Used During Construction, Rate 5.97% 4.96%
Common Facilities [Member]    
Property, Plant and Equipment [Line Items]    
Public Utilities, Allowance for Funds Used During Construction, Rate 7.44% 7.28%