May. 12, 2015
Jul. 31, 2015
Jun. 30, 2015
USD ($)
May. 31, 2015
USD ($)
Mar. 31, 2015
USD ($)
Jan. 31, 2015
Dec. 31, 2014
USD ($)
Oct. 31, 2014
Aug. 31, 2013
Factor
Jul. 31, 2013
Apr. 30, 2012
Jun. 30, 2015
USD ($)
Jun. 30, 2015
USD ($)
Public Utilities, General Disclosures [Line Items]                              
Other Liabilities, Current         $ 90,838       $ 80,211         $ 90,838 $ 90,838
Texas 2015 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Requested Rate Increase (Decrease), Amount                 $ 64,800            
Public Utilities, Requested Rate Increase (Decrease), Percentage                 6.70%            
Public Utilities, Requested Return on Equity, Percentage                 10.25%            
Public Utilities, Requested Rate Base, Amount                 $ 1,600,000            
Public Utilities, Requested Equity Capital Structure, Percentage                 53.97%            
Public Utilities, Revised requested rate increase (decrease)             $ 58,900                
Public Utilities, Additional capital investment                 $ 392,000            
FERC Proceeding - FERC Orders                              
Public Utilities, General Disclosures [Line Items]                              
Number of components included in regulatory proceeding | Factor                     2        
Other Liabilities, Current                 $ 50,400            
Current year increase (decrease) to pre-tax earnings resulting from regulatory proceedings                             $ 1,500
Number of customers for which a public utility proposes to revise formula rates               6              
Federal Energy Regulatory Commission (FERC) | FERC Proceeding - FERC Orders                              
Public Utilities, General Disclosures [Line Items]                              
Number of coincident peaks used as demand allocator, revised                     3        
Number of coincident peaks used as demand allocator, original                     12        
SPS | Wholesale Electric Rate Complaint, April 20, 2012 through July 18, 2013 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, First refund period                           1  
Public Utilities, Base return on equity requested charged to customers through production formula rates, Percentage                           10.25%  
Public Utilities, Base return on equity requested charged to customers through transmission formula rates, Percentage [1]                           10.39%  
SPS | Wholesale Electric Rate Complaints                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity charged to customers through production formula rates, Percentage                         10.25%    
Public Utilities, Base return on equity charged to customers through transmission formula rates, Percentage                         10.77%    
Public Utilities, Base return on equity requested charged to customers through production formula rates, Percentage                   8.61%   9.15% 9.15%    
Public Utilities, Base return on equity requested by customers to be charged through transmission formula rates, Percentage                   9.11%   9.65% 9.65%    
Public Utilities, Incremental ROE basis point increase (decrease) recommended by third parties                           50  
SPS | Wholesale Electric Rate Complaints, Refunds as of April 20, 2012 and July 19, 2013                              
Public Utilities, General Disclosures [Line Items]                              
FERC denied the rehearing request as it pertained to the first two rate complaints     2                        
Public Utilities, rehearing sought in FERC decision regarding number of consecutive month periods                           15 months  
Number of hearings scheduled that were canceled and parties agreed to file briefs based on pre-filed testimony                             2
Number of complaints where decision is expected by ALJ in the future                             2
SPS | Texas 2015 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Requested Rate Increase (Decrease), Amount         $ 42,000                    
Public Utilities, Requested Rate Increase (Decrease), Percentage         4.40%                    
Public Utilities, Revised requested rate increase (decrease)             58,900                
Public Utilities, Rate increase (decrease) recommended by rebuttal testimony         $ 46,400                    
Public Utilities, Post test year adjustment related to capital expenditures         0                    
Public Utilities, ROE         0                    
Rate base adjustments (largely the removal of the prepaid pension asset)         0                    
Public Utilities, Operating and maintenance expenses         (1,600)                    
Public Utilities, Depreciation expense         0                    
Public Utilities, Property taxes         (1,800)                    
Public Utilities, Revenue adjustments         0                    
Public Utilities, Wholesale load reductions         0                    
Public Utilities, SPP transmission expansion plan         (7,300)                    
Public Utilities, Other net         (1,800)                    
Public Utilities, Adjustment to move rate case expenses to separate docket         (4,300)                    
Public Utilities, Rate increase (decrease) recommended by rebuttal testimony, excluding rate case expenses         $ 42,100                    
SPS | New Mexico 2014 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Requested Return on Equity, Percentage 10.25%                            
Public Utilities, Jurisdictional electric rate base $ 777,900                            
Public Utilities, Requested Equity Capital Structure, Percentage 53.97%                            
Public Utilities, Non-fuel proposed base rate increase (decrease) $ 31,500                            
Public Utilities, Proposed base fuel rate increase (decrease) $ (30,100)                            
SPS | FERC Proceeding - FERC Orders                              
Public Utilities, General Disclosures [Line Items]                              
Number of coincident peaks used as demand allocator, original               12              
Golden Spread contract demand quantity subject to the formula rate change prior to June 1, 2015 | MW   500                          
Change in Golden Spread contract demand quantity subject to the formula rate change | MW   300                          
SPS | Wholesale Electric Rate Complaint, July 19, 2013 through Oct. 19, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested charged to customers through production formula rates, Percentage                           10.25%  
Public Utilities, Base return on equity requested charged to customers through transmission formula rates, Percentage [1]                           11.20%  
Public Utilities, Second refund period                           2  
SPS | Wholesale Electric Rate Complaint, Oct. 20, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested charged to customers through production formula rates, Percentage [2]                           10.40%  
Public Utilities, Base return on equity requested charged to customers through transmission formula rates, Percentage [1],[2]                           11.20%  
Public Utilities, Third refund period                           3  
SPS | Golden Spread [Member] | Wholesale Electric Rate Complaint, April 20, 2012 through July 18, 2013 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, First refund period [3]                           1  
Public Utilities, Base return on equity requested by customers to be charged through production formula rates, Percentage [3]                           8.78%  
Public Utilities, Base return on equity requested by customers to be charged through transmission formula rates, Percentage [1],[3]                           9.28%  
SPS | Golden Spread [Member] | Wholesale Electric Rate Complaint, July 19, 2013 through Oct. 19, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested by customers to be charged through production formula rates, Percentage [3]                           8.51%  
Public Utilities, Base return on equity requested by customers to be charged through transmission formula rates, Percentage [1],[3]                           9.01%  
Public Utilities, Second refund period [3]                           2  
SPS | Golden Spread [Member] | Wholesale Electric Rate Complaint, Oct. 20, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested by customers to be charged through production formula rates, Percentage [3]                           8.45%  
Public Utilities, Base return on equity requested by customers to be charged through transmission formula rates, Percentage [1],[3]                           8.95%  
Public Utilities, Third refund period [3]                           3  
SPS | Alliance of Xcel Municipalities [Member] | Texas 2015 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Revised requested rate increase (decrease)             58,900                
Public Utilities, Rate increase (decrease) recommended by third parties           $ (13,600)                  
Public utilities, ROE recommended by third parties           9.40%                  
Public Utilities, Equity capital structure recommended by third parties           53.97%                  
Public Utilities, Post test year adjustment related to capital expenditures           $ (11,300)                  
Public Utilities, ROE           (10,900)                  
Rate base adjustments (largely the removal of the prepaid pension asset)           (6,200)                  
Public Utilities, Operating and maintenance expenses           (13,700)                  
Public Utilities, Depreciation expense           (13,300)                  
Public Utilities, Property taxes           0                  
Public Utilities, Revenue adjustments           (2,200)                  
Public Utilities, Wholesale load reductions           (13,200)                  
Public Utilities, SPP transmission expansion plan           0                  
Public Utilities, Other net           (1,700)                  
Public Utilities, Adjustment to move rate case expenses to separate docket           0                  
Public Utilities, Rate increase (decrease) recommended by third parties excluding rate case expenses           (13,600)                  
SPS | Office of Public Utility Counsel [Member] | Texas 2015 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Revised requested rate increase (decrease)             58,900                
Public Utilities, Rate increase (decrease) recommended by third parties           $ 1,800                  
Public utilities, ROE recommended by third parties           9.20%                  
Public Utilities, Equity capital structure recommended by third parties           52.38%                  
Public Utilities, Post test year adjustment related to capital expenditures           $ (23,800)                  
Public Utilities, ROE           (13,500)                  
Rate base adjustments (largely the removal of the prepaid pension asset)           (6,800)                  
Public Utilities, Operating and maintenance expenses           (11,000)                  
Public Utilities, Depreciation expense           0                  
Public Utilities, Property taxes           (1,200)                  
Public Utilities, Revenue adjustments           (200)                  
Public Utilities, Wholesale load reductions           0                  
Public Utilities, SPP transmission expansion plan           0                  
Public Utilities, Other net           (600)                  
Public Utilities, Adjustment to move rate case expenses to separate docket           0                  
Public Utilities, Rate increase (decrease) recommended by third parties excluding rate case expenses           1,800                  
SPS | Public Utility Commission of Texas Staff [Member] | Texas 2015 Electric Rate Case                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Revised requested rate increase (decrease)             $ 58,900                
Public Utilities, Rate increase (decrease) recommended by third parties           $ (2,600)                  
Public utilities, ROE recommended by third parties           9.30%                  
Public Utilities, Equity capital structure recommended by third parties           53.97%                  
Public Utilities, Post test year adjustment related to capital expenditures           $ (23,800)                  
Public Utilities, ROE           (12,100)                  
Rate base adjustments (largely the removal of the prepaid pension asset)           0                  
Public Utilities, Operating and maintenance expenses           (7,900)                  
Public Utilities, Depreciation expense           0                  
Public Utilities, Property taxes           (4,400)                  
Public Utilities, Revenue adjustments           0                  
Public Utilities, Wholesale load reductions           (11,100)                  
Public Utilities, SPP transmission expansion plan           0                  
Public Utilities, Other net           (2,200)                  
Public Utilities, Adjustment to move rate case expenses to separate docket           0                  
Public Utilities, Rate increase (decrease) recommended by third parties excluding rate case expenses           $ (2,600)                  
SPS | FERC Staff [Member] | Wholesale Electric Rate Complaint, April 20, 2012 through July 18, 2013 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, First refund period                           1  
Public Utilities, Base return on equity requested by the FERC through production formula rates, Percentage                           8.97%  
Public Utilities, Base return on equity requested by the FERC through transmission formula rates, Percentage [1]                           9.47%  
SPS | FERC Staff [Member] | Wholesale Electric Rate Complaint, July 19, 2013 through Oct. 19, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested by the FERC through production formula rates, Percentage                           8.64%  
Public Utilities, Base return on equity requested by the FERC through transmission formula rates, Percentage [1]                           9.14%  
Public Utilities, Second refund period                           2  
SPS | FERC Staff [Member] | Wholesale Electric Rate Complaint, Oct. 20, 2014 Impact                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Base return on equity requested by the FERC through production formula rates, Percentage                           8.53%  
Public Utilities, Base return on equity requested by the FERC through transmission formula rates, Percentage [1]                           9.03%  
Public Utilities, Third refund period                           3  
Minimum | SPS | Wholesale Electric Rate Complaints                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Increase (Decrease) of transmission and production revenues, net of expense due to potential ROE adjustments                             $ (4,000)
Maximum | SPS | Wholesale Electric Rate Complaints                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Increase (Decrease) of transmission and production revenues, net of expense due to potential ROE adjustments                             $ (6,000)
Subsequent Event | SPS | Wholesale Electric Rate Complaints, Refunds as of April 20, 2012 and July 19, 2013                              
Public Utilities, General Disclosures [Line Items]                              
Public Utilities, Number of rate complaints where appeal was filed with the D.C. Circuit Court of Appeals due to the FERC orders to allow back-to-back complaints for consecutive month refund periods       2                      
Public Utilities, appeal of the number of months refund period       15 months                      
[1] Includes a SPP RTO membership adder up to 50 basis points.
[2] In addition to the recommended ROEs, SPS also filed testimony recommending the ROEs remain unchanged.
[3] For the third refund period, the recommended production and transmission ROEs are supported by Golden Spread, certain New Mexico cooperatives and the West Texas Municipal Power Agency (transmission ROE only).