Commitments and Contingencies
12 Months Ended
Dec. 31, 2014
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments

Capital Commitments — SPS has made commitments in connection with a portion of its projected capital expenditures. SPS’ capital commitments primarily relate to transmission project plans.

Transmission NTC — SPS has accepted NTCs for several hundred miles of transmission line and related substation projects based on needs identified through SPP’s various planning processes, including those associated with economics, reliability, generator interconnection or the load addition processes. Most significant is the TUCO to Yoakum County to Hobbs Plant, a 345 KV transmission line. This line will connect the TUCO substation near Lubbock, Texas with the Yoakum County substation, continuing on to the Hobbs Plant substation near Hobbs, N.M.  SPS anticipates filing CCNs for this line in Texas and in New Mexico in mid-2015. The line is scheduled to be in service in 2020.

Fuel Contracts — SPS has entered into various long-term commitments for the purchase and delivery of a significant portion of its current coal and natural gas requirements. These contracts expire in various years between 2015 and 2033. SPS is required to pay additional amounts depending on actual quantities shipped under these agreements.

The estimated minimum purchases for SPS under these contracts as of Dec. 31, 2014, are as follows:
(Millions of Dollars)
 
Coal
 
Natural gas
supply
 
Natural gas
storage and
transportation
2015
 
$
258.0

 
$
3.3

 
$
31.0

2016
 
225.1

 

 
30.8

2017
 
114.9

 

 
22.1

2018
 

 

 
20.6

2019
 

 

 
21.5

Thereafter
 

 

 
95.9

Total
 
$
598.0

 
$
3.3

 
$
221.9



Additional expenditures for fuel and natural gas storage and transportation will be required to meet expected future electric generation needs. SPS’ risk of loss, in the form of increased costs from market price changes in fuel, is mitigated through the cost-rate adjustment mechanisms, which provide for pass-through of most fuel, storage and transportation costs to customers.

PPAs — SPS has entered into PPAs with other utilities and energy suppliers with expiration dates through 2033 for purchased power to meet system load and energy requirements and meet operating reserve obligations. In general, these contracts provide for energy payments, based on actual energy delivered and capacity payments. Capacity payments are typically contingent on the independent power producing entity meeting certain contract obligations, including plant availability requirements. Certain contractual payments are adjusted based on market indices. The effects of price adjustments on our financial results are mitigated through purchased energy cost recovery mechanisms.

Included in electric fuel and purchased power expenses for PPAs accounted for as executory contracts, were payments for capacity of $52.4 million, $38.4 million and $36.2 million in 2014, 2013 and 2012, respectively. At Dec. 31, 2014, the estimated future payments for capacity that SPS is obligated to purchase pursuant to these executory contracts, subject to availability, are as follows:
(Millions of Dollars)
 
 

2015
 
$
56.6

2016
 
57.1

2017
 
58.3

2018
 
59.6

2019
 
19.5

Thereafter
 
36.1

Total (a)
 
$
287.2


(a) 
Excludes contingent energy payments for renewable energy PPAs.

Additional energy payments under these PPAs and PPAs accounted for as operating leases will be required to meet expected future electric demand.

Leases — SPS leases a variety of equipment and facilities used in the normal course of business. These leases, primarily for office space, generating facilities, trucks, aircraft, cars and power-operated equipment, are accounted for as operating leases. Total expenses under operating lease obligations were approximately $63.1 million, $64.2 million and $59.9 million for 2014, 2013 and 2012, respectively. These expenses included capacity payments for PPAs accounted for as operating leases of $57.1 million, $59.0 million and $56.0 million in 2014, 2013 and 2012, respectively, recorded to electric fuel and purchased power expenses.

Included in the future commitments under operating leases are estimated future capacity payments under PPAs that have been accounted for as operating leases in accordance with the applicable accounting guidance. Future commitments under operating leases are:
(Millions of Dollars)
 
Operating
Leases
 
        PPA (a) (b)
Operating
Leases
 
Total
Operating
Leases
2015
 
$
3.3

 
$
52.0

 
$
55.3

2016
 
3.4

 
49.0

 
52.4

2017
 
2.4

 
49.0

 
51.4

2018
 
2.0

 
49.0

 
51.0

2019
 
1.9

 
49.0

 
50.9

Thereafter
 
11.4

 
671.8

 
683.2


(a) 
Amounts do not include PPAs accounted for as executory contracts.
(b) 
PPA operating leases contractually expire through 2033.

Variable Interest Entities — The accounting guidance for consolidation of variable interest entities requires enterprises to consider the activities that most significantly impact an entity’s financial performance, and power to direct those activities, when determining whether an enterprise is a variable interest entity’s primary beneficiary.

PPAs — Under certain PPAs, SPS purchases power from independent power producing entities for which SPS is required to reimburse natural gas fuel costs, or to participate in tolling arrangements under which SPS procures the natural gas required to produce the energy that it purchases. These specific PPAs create a variable interest in the associated independent power producing entity.

SPS has determined that certain independent power producing entities are variable interest entities. SPS is not subject to risk of loss from the operations of these entities, and no significant financial support has been, or is in the future required to be provided other than contractual payments for energy and capacity set forth in the PPAs.

SPS has evaluated each of these variable interest entities for possible consolidation, including review of qualitative factors such as the length and terms of the contract, control over O&M, control over dispatch of electricity, historical and estimated future fuel and electricity prices, and financing activities. SPS has concluded that these entities are not required to be consolidated in its financial statements because it does not have the power to direct the activities that most significantly impact the entities’ economic performance. SPS had approximately 827 MW of capacity under long-term PPAs as of Dec. 31, 2014 and 2013, with entities that have been determined to be variable interest entities. These agreements have expiration dates through the year 2033.

Fuel Contracts — SPS purchases all of its coal requirements for its Harrington and Tolk electric generating stations from TUCO under contracts for those facilities that expire in 2016 and 2017, respectively. TUCO arranges for the purchase, receiving, transporting, unloading, handling, crushing, weighing, and delivery of coal to meet SPS’ requirements. TUCO is responsible for negotiating and administering contracts with coal suppliers, transporters and handlers.

No significant financial support has been, or is in the future, required to be provided to TUCO by SPS, other than contractual payments for delivered coal. However, the fuel contracts create a variable interest in TUCO due to SPS’ reimbursement of certain fuel procurement costs. SPS has determined that TUCO is a variable interest entity. SPS has concluded that it is not the primary beneficiary of TUCO because SPS does not have the power to direct the activities that most significantly impact TUCO’s economic performance.

Environmental Contingencies

SPS has been or is currently involved with the cleanup of contamination from certain hazardous substances at several sites. In many situations, SPS believes it will recover some portion of these costs through insurance claims. Additionally, where applicable, SPS is pursuing, or intends to pursue, recovery from other PRPs and through the regulated rate process. New and changing federal and state environmental mandates can also create added financial liabilities for SPS, which are normally recovered through the regulated rate process. To the extent any costs are not recovered through the options listed above, SPS would be required to recognize an expense.

Site Remediation — Various federal and state environmental laws impose liability, without regard to the legality of the original conduct, where hazardous substances or other regulated materials have been released to the environment. SPS may sometimes pay all or a portion of the cost to remediate sites where past activities of SPS or other parties have caused environmental contamination. Environmental contingencies could arise from various situations, including sites of former manufactured gas plants operated by SPS, its predecessors, or other entities; and third-party sites, such as landfills, for which SPS is alleged to be a PRP that sent hazardous materials and wastes to that site.

Environmental Requirements

Water and Waste
Asbestos Removal — Some of SPS’ facilities contain asbestos. Most asbestos will remain undisturbed until the facilities that contain it are demolished or removed. SPS has recorded an estimate for final removal of the asbestos as an ARO. It may be necessary to remove some asbestos to perform maintenance or make improvements to other equipment. The cost of removing asbestos as part of other work is not expected to be material and is recorded as incurred as operating expenses for maintenance projects, capital expenditures for construction projects or removal costs for demolition projects.

Federal Clean Water Act (CWA) Effluent Limitations Guidelines (ELG) — In June 2013, the EPA published a proposed ELG rule for power plants that use coal, natural gas, oil or nuclear materials as fuel and discharge treated effluent to surface waters as well as utility-owned landfills that receive coal combustion residuals. The final rule is now expected in September 2015. Under the current proposed rule, facilities would need to comply as soon as possible after July 2017, but no later than July 2022. The impact of this rule on SPS is uncertain at this time.

Federal CWA Waters of the United States Rule In April 2014, the EPA and the U.S. Army Corps of Engineers issued a proposed rule that significantly expands the types of water bodies regulated under the CWA. If finalized as proposed, this rule could delay the siting of new pipelines, transmission lines and distribution lines, increase project costs and expand permitting and reporting requirements. The ultimate impact of the proposed rule will depend on the specific requirements of the final rule and cannot be determined at this time. A final rule is not anticipated before the second quarter of 2015.

Coal Ash Regulation — SPS’ operations are subject to federal and state laws that impose requirements for handling, storage, treatment and disposal of solid waste. In 2010, the EPA published a proposed rule on the regulation of coal combustion byproducts (coal ash) as hazardous or nonhazardous waste. The EPA issued a pre-publication version of the final rule in December 2014, which once promulgated will impose new rules to regulate coal ash as a nonhazardous solid waste. SPS’ costs for the management and disposal of coal ash will not significantly increase under the new rule.

Air
GHG Emission Standard for Existing Sources — In June 2014, the EPA published its proposed rule on GHG emission standards for existing power plants. Comments were due to the EPA on Dec. 1, 2014 and a final rule is anticipated in mid-summer 2015. Following adoption of the final rule, states must develop implementation plans by June 2016, with the possibility of an extension to June 2017 (June 2018 if submitting a joint plan with other states). Among other things, the proposed rule would require that state plans include enforceable measures to ensure emissions from existing power plants in the state achieve the EPA’s state-specific interim (2020-2029) and final (2030 and thereafter) emission performance targets. The plan will likely require additional emission reductions in states in which SPS operates. It is not possible to evaluate the impact of existing source standards until the EPA promulgates a final rule and states have adopted their applicable state plans.

GHG NSPS Proposal — In January 2014, the EPA re-proposed a GHG NSPS for newly constructed power plants which would set performance standards (maximum carbon dioxide emission rates) for coal- and natural gas-fired power plants. For coal power plants, the NSPS requires an emissions level equivalent to partial carbon capture and storage (CCS) technology; for gas-fired power plants, the NSPS reflects emissions levels from combined cycle technology with no CCS. The EPA continues to propose that the NSPS not apply to modified or reconstructed existing power plants. In addition, installation of control equipment on existing plants would not constitute a “modification” to those plants under the NSPS program. A final rule is anticipated in mid-summer 2015. It is not possible to evaluate the impact of the re-proposed NSPS until its final requirements are known.

GHG NSPS for Modified and Reconstructed Power Plants — In June 2014, the EPA published a proposed NSPS that would apply to GHG emissions from power plants that are modified or reconstructed. A final rule is anticipated in mid-summer 2015. A modification is a change to an existing source that increases the maximum achievable hourly rate of emissions. A reconstruction involves the replacement of components at a unit to the extent that the capital cost of the new components exceeds 50 percent of the capital cost of an entirely new comparable unit. The proposed standards would not require installation of CCS technology. Instead, the proposed standard for coal-fired power plants would require a combination of best operating practices and equipment upgrades. The proposal for gas-fired power plants would require emissions standards based on efficient combined cycle technology. It is not possible to evaluate the impact of these proposed standards until the final requirements are known. In addition, it is not clear whether these requirements, once adopted, would apply to future changes at SPS’ power plants.

CSAPR — CSAPR addresses long range transport of PM and ozone by requiring reductions in SO2 and NOx from utilities in the eastern half of the United States, including Texas, using an emissions trading program.

In August 2012, the D.C. Circuit vacated the CSAPR and remanded it back to the EPA. The D.C. Circuit stated the EPA must continue administering CSAPR’s predecessor rule pending adoption of a valid replacement. In April 2014, the U.S. Supreme Court reversed and remanded the case to the D.C. Circuit. The Supreme Court held that the EPA’s rule design did not violate the CAA and that states had received adequate opportunity to develop their own plans. Because the D.C. Circuit overturned the CSAPR on two over-arching issues, there are many other issues the D.C. Circuit did not rule on that will now need to be considered on remand. In October 2014, the D.C. Circuit granted the EPA’s request to begin to implement CSAPR by imposing its 2012 compliance obligations starting in January 2015. In addition, the D.C. Circuit set a briefing schedule and plans to hear arguments on the remaining issues in the case in February 2015. While the litigation continues, the EPA will begin to administer the CSAPR in 2015.

Multiple changes to the SPS system since 2011 will substantially reduce estimated costs of complying with the CSAPR. These include the addition of 700 MW of wind power, the construction of Jones Units 3 and 4 to meet reserve requirements and provide quick start capability, reduced wholesale load and new PPAs, installation of NOx combustion controls on Tolk Units 1 and 2 and completion of certain transmission projects. As a result, SPS estimates compliance with the CSAPR in 2015 will cost approximately $7 million.

Electric Generating Unit (EGU) Mercury and Air Toxics Standards (MATS) Rule — The final EGU MATS rule became effective in April 2012. The EGU MATS rule sets emission limits for acid gases, mercury and other hazardous air pollutants and requires coal-fired utility facilities greater than 25 MW to demonstrate compliance within three to four years of the effective date. SPS expects to comply with the EGU MATS rule through a combination of mercury and other emission control projects. In 2014, the U.S. Supreme Court decided to review the D.C. Circuit’s decision that upheld the MATS standard. It is not yet known what impact the Supreme Court’s decision may have on the MATS standard or its implementation schedule. SPS believes EGU MATS costs will be recoverable through regulatory mechanisms and does not expect a material impact on results of operations, financial position or cash flows.

Regional Haze Rules — The regional haze program is designed to address widespread, regionally homogeneous haze that results from emissions from a multitude of sources. In 2005, the EPA amended the BART requirements of its regional haze rules, which require the installation and operation of emission controls for industrial facilities emitting air pollutants that reduce visibility in certain national parks and wilderness areas. In its first regional haze SIP, Texas identified the SPS facilities that will have to reduce SO2, NOx and PM emissions under BART and set emissions limits for those facilities.

Harrington Units 1 and 2 are potentially subject to BART. Texas developed a SIP that finds the CAIR equal to BART for EGUs. As a result, no additional controls beyond CAIR compliance would be required. In May 2012, the EPA deferred its review of the SIP in its final rule allowing states to find that CSAPR compliance meets BART requirements for EGUs. In December 2014, the EPA proposed to approve the BART portion of the SIP, with the exception that the EPA would substitute CSAPR compliance for Texas’ reliance on CAIR. The EPA currently plans to issue its final rule in August 2015.

In May 2014, the EPA issued a request for information under the CAA related to SO2 control equipment at Tolk Units 1 and 2. In its December 2014 proposal, the EPA plans to disapprove the reasonable progress portions of the SIP and instead adopt a Federal Implementation Plan. For SPS, the EPA proposed to require dry scrubbers on both Tolk units to reduce SO2 emissions to help achieve reasonable progress goals the EPA would establish for Texas and Oklahoma national parks and wilderness areas. As proposed, the dry scrubbers would need to be installed and operating within five years of the EPA’s final action, currently expected in August 2015. SPS plans to file comments objecting to the installation of dry scrubbers on the units. Whether dry scrubbers are required is dependent on the EPA’s final decision. If required, they would cost approximately $600 million, with an annual operating cost of approximately $10.4 million.

Revisions to the National Ambient Air Quality Standards (NAAQS) for PM — In December 2012, the EPA lowered the primary health-based NAAQS for annual average fine PM and retained the current daily standard for fine PM. In areas where SPS operates power plants, current monitored air concentrations are below the level of the final annual primary standard. In December 2014, the EPA issued its final designations, which did not include areas in any states in which SPS operates.

Revisions to the NAAQS for Ozone — In December 2014, the EPA proposed to revise the NAAQS for ozone by lowering the eight-hour standard from 0.075 parts per million (ppm) to a level within the range of 0.065-0.070 ppm. The EPA is also taking comment on a level for the standard as low as 0.060 ppm. In areas where SPS operates, current monitored air quality concentrations are above the proposed level of 0.070 ppm in the Texas panhandle. The EPA is expected to adopt a new ozone standard in a final rule to be issued in October 2015. Depending on the level of the standard, impacted states would study the sources of the nonattainment and make emission reduction plans to attain the standards. These plans would be due to the EPA in 2020 or 2021. Such plans could include installation of further NOx controls on power plants. It is not possible to evaluate the impact of this proposal until the final standard is adopted, the designation of nonattainment areas is made in late 2017 based on air quality data years 2014-2016, and any required state plans are developed.

Asset Retirement Obligations

Recorded AROs — AROs have been recorded for property related to the following: electric steam production, electric distribution and transmission, and general property. The electric production obligations include asbestos, ash-containment facilities, storage tanks and control panels. The asbestos recognition associated with the electric production includes certain plants. This asbestos abatement removal obligation originated in 1973 with the CAA, which applied to the demolition of buildings or removal of equipment containing asbestos that can become airborne on removal. AROs also have been recorded for steam production related to ash-containment facilities such as bottom ash ponds, evaporation ponds and solid waste landfills. The origination dates on the ARO recognition for ash-containment facilities at steam plants were the in-service dates of the various facilities.

An ARO was recognized for the removal of electric transmission and distribution equipment, which consists of many small potential obligations associated with PCBs, mineral oil, storage tanks, treated poles, lithium batteries, mercury and street lighting lamps. The electric general AROs include small obligations related to storage tanks, radiation sources and office buildings. These assets have numerous in-service dates for which it is difficult to assign the obligation to a particular year. Therefore, the obligation was measured using an average service life.

In December 2014, the EPA issued a pre-publication version of a final rule imposing requirements for activities involving coal ash waste. The ruling, once effective, will not result in the creation of a new legal obligation and SPS’ estimated cash flows for the closure of coal ash landfills and impoundments are not expected to significantly increase as a result of the ruling.

A reconciliation of SPS’ AROs for the years ended Dec. 31, 2014 and 2013 is as follows:
(Thousands of Dollars)
 
Beginning Balance Jan. 1, 2014
 
Liabilities
Recognized
 
Accretion
 
Cash Flow Revisions
 
Ending Balance Dec. 31, 2014 (a)
Electric plant
 
 
 
 
 
 
 
 
 
 
Steam production asbestos
 
$
11,608

 
$

 
$
795

 
$
4,554

 
$
16,957

Steam production ash containment
 
809

 

 
51

 
749

 
1,609

Electric distribution
 
6,104

 

 
223

 

 
6,327

Other
 
854

 
136

 
31

 
117

 
1,138

Total liability
 
$
19,375

 
$
136

 
$
1,100

 
$
5,420

 
$
26,031

(a) 
There were no ARO liabilities settled during the year ended Dec. 31, 2014.
(Thousands of Dollars)
 
Beginning Balance Jan. 1, 2013
 
Liabilities
Settled
 
Accretion
 
Cash Flow Revisions
 
Ending Balance Dec. 31, 2013 (a)
Electric plant
 
 
 
 
 
 
 
 
 
 
Steam production asbestos
 
$
10,979

 
$
(118
)
 
$
747

 
$

 
$
11,608

Steam production ash containment
 
764

 

 
48

 
(3
)
 
809

Electric distribution
 
5,303

 

 
171

 
630

 
6,104

Other
 
561

 

 
42

 
251

 
854

Total liability
 
$
17,607

 
$
(118
)
 
$
1,008

 
$
878

 
$
19,375


(a) 
There were no new ARO liabilities recognized during the year ended Dec. 31, 2013.

Removal Costs — SPS records a regulatory liability for the plant removal costs of generation, transmission and distribution facilities that are recovered currently in rates. Generally, the accrual of future non-ARO removal obligations is not required. However, long-standing ratemaking practices approved by applicable state and federal regulatory commissions have allowed provisions for such costs in historical depreciation rates. These removal costs have accumulated over a number of years based on varying rates as authorized by the appropriate regulatory entities. Given the long time periods over which the amounts were accrued and the changing of rates over time, SPS has estimated the amount of removal costs accumulated through historic depreciation expense based on current factors used in the existing depreciation rates. Accordingly, the recorded amounts of estimated future removal costs are considered regulatory liabilities. Removal costs as of Dec. 31, 2014 and 2013 were $68 million and $53 million, respectively.

Legal Contingencies

SPS is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss. For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on SPS’ financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.

Employment, Tort and Commercial Litigation

Exelon Wind (formerly John Deere Wind) Complaint  Several lawsuits in Texas state and federal courts and regulatory proceedings have arisen out of a dispute concerning SPS’ payments for energy and capacity produced from the Exelon Wind subsidiaries’ projects. There are two main areas of dispute. First, Exelon Wind claims that it established legally enforceable obligations (LEOs) for each of its 12 wind facilities in 2005 through 2008 that require SPS to buy power based on SPS’ forecasted avoided cost as determined in 2005 through 2008. Although SPS has refused to accept Exelon Wind’s LEOs, SPS accepts that it must take energy from Exelon Wind under SPS’ PUCT-approved QF Tariff. Second, Exelon Wind has raised various challenges to SPS’ PUCT-approved QF Tariff, which became effective in August 2010. On Jan.16, 2015, Exelon Wind filed motions to dismiss or notices of non-suits for its state and federal lawsuits regarding the QF tariff, and for its state and federal lawsuits and regulatory proceedings regarding the LEOs. Later in January, the PUCT and state and federal courts issued orders dismissing the cases. The only remaining proceedings are pending before the FERC (one regarding the QF Tariff and the other regarding the LEOs).

SPS believes the likelihood of loss in these proceedings is remote based primarily on existing case law and while it is not possible to estimate the amount or range of reasonably possible loss in the event of an adverse outcome, SPS believes such loss would not be material based upon its belief that it would be permitted to recover such costs, if needed, through its various fuel clause mechanisms. No accrual has been recorded for this matter.

Other Contingencies

See Note 10 for further discussion.