Los Angeles International Airport
In October 2017, the Company executed a lease agreement with Los Angeles World Airports ("LAWA") (the "T1.5 Lease"). Under the T1.5 Lease, the Company is overseeing and managing the design, development, financing, construction, and commissioning of a passenger processing facility between Terminal 1 and 2 (the "Terminal 1.5 Project"). The Terminal 1.5 Project is expected to include ticketing, baggage claim, passenger screening, and a bus gate at a cost not to exceed $479 million for site improvements and non-proprietary improvements. Construction on the Terminal 1.5 Project began during third quarter 2017 and is estimated to be substantially completed in late 2020 or early 2021. The costs incurred to fund the Terminal 1.5 Project are included within Assets Constructed for Others ("ACFO") and all amounts that have been or will be reimbursed will be included within Construction obligation on the accompanying unaudited Condensed Consolidated Balance Sheet.
Funding for this project is primarily through the Regional Airports Improvement Corporation (the "RAIC"), which is a quasi-governmental special purpose entity that is acting as a conduit borrower under a syndicated credit facility provided by a group of lenders. A loan made under the credit facility for the Terminal 1.5 Project is being used to reimburse the Company for the site improvements and non-proprietary improvements of the Terminal 1.5 Project, and the outstanding loan will be repaid with the proceeds of LAWA’s payments to purchase completed construction phases. The Company guaranteed the obligation of the RAIC under the credit facility associated with the Terminal 1.5 Project. As of June 30, 2020, the Company's outstanding remaining guaranteed obligation under the credit facility for the Terminal 1.5 Project was $253 million.
Construction costs recorded in ACFO for the Terminal 1.5 Project were $239 million and $164 million, as of June 30, 2020, and December 31, 2019, respectively.

Dallas Love Field
During 2008, the City of Dallas approved the Love Field Modernization Project ("LFMP"), a project to reconstruct Dallas Love Field with modern, convenient air travel facilities. Pursuant to a Program Development Agreement with the City of Dallas and the Love Field Airport Modernization Corporation (or the "LFAMC," a Texas non-profit "local government corporation" established by the City of Dallas to act on the City of Dallas' behalf to facilitate the development of the LFMP), the Company managed this project. Major construction was effectively completed in 2014. During second quarter 2017, the City of Dallas approved using the remaining bond funds for additional terminal construction projects, which were effectively completed in 2018.

Although the City of Dallas received commitments from various sources that helped to fund portions of the LFMP project, including the Federal Aviation Administration ("FAA"), the Transportation Security Administration, and the City of Dallas' Aviation Fund, the majority of the funds used were from the issuance of bonds. The Company guaranteed principal and interest payments on bonds issued by the LFAMC. As of June 30, 2020, $407 million of principal remained outstanding. The net present value of the future principal and interest payments associated with the bonds was $443 million as of June 30, 2020, and was reflected as part of the Company's operating lease right–of–use assets and lease obligations in the unaudited Condensed Consolidated Balance Sheet.

Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business, including, but not limited to, examinations by the Internal Revenue Service (the "IRS"). The Company's management does not expect that the outcome of any of its currently ongoing legal proceedings or the outcome of any adjustments presented by the IRS, individually or collectively, will have a material adverse effect on the Company's financial condition, results of operations, or cash flow.