COMMITMENTS AND CONTINGENCIES
9 Months Ended
Sep. 30, 2015
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES
COMMITMENTS AND CONTINGENCIES

Fort Lauderdale-Hollywood International Airport
In December 2013, the Company entered into an agreement with Broward County, Florida, which owns and operates Fort Lauderdale-Hollywood International Airport, to oversee and manage the design and construction of the airport's Terminal 1 Modernization Project at a cost not to exceed $295 million. In addition to significant improvements to the existing Terminal 1, the project includes the design and construction of a new five-gate Concourse A with an international processing facility. Funding for the project will come directly from Broward County sources, but will flow through the Company in its capacity as manager of the project. Major construction on the project began during third quarter 2015 and is estimated to be completed during 2017. The Company believes that due to its agreed upon role in overseeing and managing the project, it is considered the owner of the project for accounting purposes. As such, during construction the Company records expenditures as Assets constructed for others in the unaudited Condensed Consolidated Balance Sheet, along with a corresponding outflow within Assets constructed for others in the unaudited Condensed Consolidated Statement of Cash Flows, and an increase to Construction obligation (with a corresponding cash inflow from Financing activities in the unaudited Condensed Consolidated Statement of Cash Flows) as reimbursements are received from Broward County. As of September 30, 2015, the Company had recorded construction costs related to the project of $17 million.
Houston William P. Hobby Airport
The Company entered into a Memorandum of Agreement (“MOA”) with the City of Houston (“City”), effective June 2012, to expand the existing Houston Hobby airport facility. As provided in the MOA, the Company and the City have entered into an Airport Use and Lease Agreement (“Lease”) to control the execution of this expansion and the financial terms thereof. Per the MOA and Lease, this project provides for a new five-gate international terminal with international passenger processing facilities, expansion of the existing security checkpoint, and upgrades to the Southwest Airlines ticket counter area. The project was estimated to cost $156 million, and the Company agreed to provide the funding for, as well as management over, the project. In return, the capital cost portion of the rent the Company pays for the international facility will be waived from the initial occupancy until the expiration of the Lease. However, after completion of the project, the City has the option to buy out the Company's investment at the then-unamortized cost of the facility. This purchase would trigger payment of the previously waived capital cost component of rents owed the City. Additionally, some portion of the project is expected to qualify for rental credits that would be utilized upon completion of the facility against the Company’s lease payments at the airport. Construction began during third quarter 2013 and was effectively completed in October 2015, on time and under budget, at which time the Company began operating from the new facility.

As a result of its significant involvement in the Houston Hobby project, the Company has evaluated its ongoing accounting requirements in consideration of accounting guidance provided for lessees involved in asset construction, and has determined that it is the owner of the facility for accounting purposes during the construction period. As such, during construction, the Company records expenditures as Assets constructed for others in the unaudited Condensed Consolidated Balance Sheet, along with a corresponding outflow within Assets constructed for others, in the unaudited Condensed Consolidated Statement of Cash Flows. As of September 30, 2015, the Company had recorded construction costs related to Houston Hobby of $128 million.

Los Angeles International Airport
In March 2013, the Company executed a lease agreement with Los Angeles World Airports (“LAWA”), which owns and operates Los Angeles International Airport. Under the lease agreement, which was amended in June 2014, the Company is overseeing and managing the design, development, financing, construction and commissioning of the airport's Terminal 1 Modernization Project (the “Project”) at a cost not to exceed $526 million. The Project is being funded primarily using the Regional Airports Improvement Corporation ("RAIC"), which is a quasi-governmental special purpose entity that acts as a conduit borrower under a syndicated credit facility provided by a group of lenders. Loans made under the credit facility are being used to fund the development of the Project, and the outstanding loans will be repaid with the proceeds of LAWA’s payments to purchase completed Project phases. The Company has guaranteed the obligations of the RAIC under the credit facility. Construction on the Project began during 2014 and is estimated to be completed during 2018. The Company believes that due to its agreed upon role in overseeing and managing the Project, it is considered the owner of the Project for accounting purposes. LAWA will reimburse the Company for the non-proprietary renovations, while the Company will not be reimbursed for proprietary renovations. As a result, all of the costs incurred to fund the Project are included within Assets constructed for others and all amounts that have been or will be reimbursed will be included within Construction obligation on the accompanying unaudited Condensed Consolidated Balance Sheet. As of September 30, 2015, the Company had recorded construction costs related to the Project of $151 million, which were classified and included in Assets constructed for others and as Construction obligation in the accompanying unaudited Condensed Consolidated Balance Sheet.
Dallas Love Field
During 2008, the City of Dallas approved the Love Field Modernization Program (“LFMP”), a project to reconstruct Dallas Love Field with modern, convenient air travel facilities. Pursuant to a Program Development Agreement with the City of Dallas and the Love Field Airport Modernization Corporation (or “LFAMC,” a Texas non-profit “local government corporation” established by the City of Dallas to act on the City of Dallas' behalf to facilitate the development of the LFMP), the Company managed this project. Major construction commenced during 2010, and the project was effectively completed by December 31, 2014. The project consists of the complete replacement of gate facilities with a new 20-gate facility, including infrastructure, systems and equipment, aircraft parking apron, fueling system, roadways and terminal curbside, baggage handling systems, passenger loading bridges and support systems, and other supporting infrastructure. New ticketing and check-in areas opened during fourth quarter 2012, 12 new gates and new concessions opened in 2013, and the remaining gates opened during October 2014.

Although the City of Dallas has received commitments from various sources that are helping to fund portions of the LFMP project, including the FAA, the Transportation Security Administration, and the City of Dallas' Aviation Fund, the majority of the funds used are from the issuance of bonds. During fourth quarter 2010, $310 million of such bonds were issued by the LFAMC, and the Company has guaranteed principal and interest payments on the bonds. An additional tranche of such bonds totaling $146 million was issued during second quarter 2012, and the Company has guaranteed the principal and interest payments on these bonds as well. The Company currently expects that as a result of the funding commitments from the above mentioned sources and the bonds that have been issued thus far, no further bond issuances and related guarantees from the Company will be required to complete the LFMP project.

In conjunction with the Company's significant presence at Dallas Love Field and other factors, the Company agreed to manage the LFMP project. Based on these facts, the Company has evaluated its ongoing accounting requirements in consideration of accounting guidance provided for lessees involved in asset construction. The Company has recorded and will continue to record an asset and corresponding obligation for the cost of the LFMP project as the construction of the facility occurs. As of September 30, 2015, the Company had recorded LFMP gross construction costs, including capitalized interest, of $527 million within Assets constructed for others and had recorded a net liability of $516 million within Construction obligation in its unaudited Condensed Consolidated Balance Sheet. Upon completion of different phases of the LFMP project, the Company has placed the associated assets in service and has begun depreciating the assets over their estimated useful lives. In addition, upon the effective completion of construction, the Company noted the project assets did not meet the qualifications for sale and leaseback accounting due to the Company's continuing involvement with the facility, as defined; therefore, for financial reporting purposes, these assets will remain on the Company's books until the bonds issued by the City of Dallas are repaid. The corresponding LFMP liabilities will be reduced primarily through the Company's airport rental payments to the City of Dallas as the construction costs of the project are passed through to the Company via recurring airport rates and charges. These payments are reflected as Repayment of construction obligation in the unaudited Condensed Consolidated Statement of Cash Flows.

Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business, including, but not limited to, examinations by the IRS. The Company's management does not expect that the outcome in any of its currently ongoing legal proceedings or the outcome of any adjustments presented by the IRS, individually or collectively, will have a material adverse effect on the Company's financial condition, results of operations, or cash flow.