Commitments
During 2008, the City of Dallas approved the Love Field Modernization Program (“LFMP”), a project to reconstruct Dallas Love Field (“Airport”) with modern, convenient air travel facilities. Pursuant to a Program Development Agreement (“PDA”) with the City of Dallas and the Love Field Airport Modernization Corporation (or “LFAMC,” a Texas non-profit “local government corporation” established by the City to act on the City's behalf to facilitate the development of the LFMP), the Company is managing this project. Major construction commenced during 2010. New ticketing and checkin areas opened during fourth quarter 2012, and 11 new gates and new concessions opened on April 16, 2013. Another new gate is scheduled to open in third quarter 2013, and full completion of the project is scheduled for second half of 2014. The project will include the renovation of the Airport airline terminals and complete replacement of gate facilities with a new 20-gate facility, including infrastructure, systems and equipment, aircraft parking apron, fueling system, roadways and terminal curbside, baggage handling systems, passenger loading bridges and support systems, and other supporting infrastructure.

It is currently expected that the total amount spent on the LFMP project will be approximately $519 million. Although the City of Dallas has received commitments from various sources that are expected to fund portions of the LFMP project, including the Federal Aviation Administration (“FAA”), the Transportation Security Administration, and the City's Aviation Fund, the majority of the funds used are expected to be from the issuance of bonds. During fourth quarter 2010, $310 million of such bonds were issued by the LFAMC, and the Company has guaranteed principal and interest payments on the bonds. An additional tranche of such bonds totaling $146 million was issued during second quarter 2012, and the Company has guaranteed the principal and interest payments on these bonds as well. The Company currently expects that as a result of the funding commitments from the above mentioned sources and the bonds that have been issued thus far, no further bond issuances and related guarantees from the Company will be required to complete the LFMP project.

In conjunction with the Company's significant presence at Dallas Love Field, its rights to occupy 16 of the available gates upon completion of the facility, and other factors, the Company agreed to manage the majority of the LFMP project. Based on these facts, the Company has evaluated its ongoing accounting requirements in consideration of accounting guidance provided for lessees involved in asset construction. The Company has recorded and will continue to record an asset and corresponding obligation for the cost of the LFMP project as the construction of the facility occurs. As of March 31, 2013, the Company had recorded LFMP construction costs of $359 million classified as both an asset as a component of Ground property and equipment and a corresponding liability as a component of Other non-current liabilities, respectively, in its unaudited Condensed Consolidated Balance Sheet. Upon completion of different phases of the LFMP project, the Company has placed the associated assets in service and has begun depreciating the assets over their estimated useful lives. The amount of depreciation recorded during first quarter 2013 associated with the LFMP project was not material. The corresponding LFMP liabilities will be reduced primarily through the Company's airport rental payments to the City of Dallas once the entire project is completed.

Contingencies
The Company is from time to time subject to various legal proceedings and claims arising in the ordinary course of business, including, but not limited to, examinations by the IRS. The Company's management does not expect that the outcome in any of its currently ongoing legal proceedings or the outcome of any adjustments presented by the IRS, individually or collectively, will have a material adverse effect on the Company's financial condition, results of operations, or cash flow.