XML 89 R61.htm IDEA: XBRL DOCUMENT v3.23.1
Regulatory Matters (Tables)
3 Months Ended
Mar. 31, 2023
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at March 31, 2023 and December 31, 2022 were as follows:
Regulatory ClauseBalance Sheet Line ItemMarch 31,
2023
December 31, 2022
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory assets, current$23 $47 
Other regulatory assets, deferred18 — 
Rate CNP PPAOther regulatory assets, current17 18 
Other regulatory assets, deferred100 102 
Retail Energy Cost Recovery
Other regulatory assets, current
101 102 
Other regulatory assets, deferred420 520 
Georgia Power
Fuel Cost Recovery(*)
Receivables – under recovered fuel clause revenues
$447 $— 
Deferred under recovered fuel clause revenues1,702 2,056 
Mississippi Power
Fuel Cost Recovery
Receivables – customer accounts, net
$25 $
Ad Valorem Tax
Other regulatory assets, current
9 12 
Other regulatory assets, deferred
19 19 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost under recovery$ $108 
Natural gas cost over recovery117 — 
(*)See "Georgia Power – Fuel Cost Recovery" herein for additional information.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through the end of the second quarter 2023 and the first quarter 2024, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$10,553 
Construction contingency estimate40 
Total project capital cost forecast(a)(b)
10,593 
Net investment at March 31, 2023(b)
(9,747)
Remaining estimate to complete$846 
(a)Includes approximately $610 million of costs that are not shared with the other Vogtle Owners, including $33 million of construction monitoring costs approved for recovery by the Georgia PSC in its nineteenth VCM order, and approximately $407 million of incremental costs under the cost-sharing and tender provisions of the joint ownership agreements described below. Excludes financing costs expected to be capitalized through AFUDC of approximately $418 million, of which $334 million had been accrued through March 31, 2023.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs and capital projects during the first three months of 2023 were as follows:
UtilityProgram
Three Months
Ended
March 31, 2023
(in millions)
Nicor GasInvesting in Illinois$62 
Virginia Natural GasSAVE20 
Atlanta Gas LightSystem Reinforcement Rider32 
Chattanooga GasPipeline Replacement Program
Total$115