REGULATORY MATTERS - GAS Schedule of Infrastructure Replacement Programs and Capital Projects (Details) - Southern Company Gas
$ in Millions
12 Months Ended
Dec. 31, 2022
USD ($)
mi
Dec. 31, 2021
USD ($)
Dec. 31, 2020
USD ($)
Public Utilities, General Disclosures [Line Items]      
Expenditures in 2022 $ 587    
Expenditures Since Project Inception $ 3,439    
Pipe Installed Since Project Inception (in miles) | mi 1,837    
Scope of Program (in miles) | mi 2,622    
Investing In Illinois      
Public Utilities, General Disclosures [Line Items]      
Expenditures in 2022 $ 437    
Expenditures Since Project Inception $ 2,945    
Pipe Installed Since Project Inception (in miles) | mi 1,297    
Scope of Program (in miles) | mi 1,854    
Program Duration 9 years    
Steps to Advance Virginia's Energy (SAVE)      
Public Utilities, General Disclosures [Line Items]      
Expenditures in 2022 $ 69 $ 51 $ 49
Expenditures Since Project Inception $ 411    
Pipe Installed Since Project Inception (in miles) | mi 525    
Scope of Program (in miles) | mi 695    
Program Duration 13 years    
System Reinforcement Rider      
Public Utilities, General Disclosures [Line Items]      
Expenditures in 2022 $ 76    
Expenditures Since Project Inception $ 76    
Pipe Installed Since Project Inception (in miles) | mi 10    
Program Duration 3 years    
Pipeline Replacement Program      
Public Utilities, General Disclosures [Line Items]      
Expenditures in 2022 $ 5    
Expenditures Since Project Inception $ 7    
Pipe Installed Since Project Inception (in miles) | mi 5    
Scope of Program (in miles) | mi 73    
Program Duration 7 years