Regulatory Matters - GPC Nuclear Construction (Details) - GEORGIA POWER CO
$ in Millions
3 Months Ended 6 Months Ended 12 Months Ended
Jun. 30, 2022
USD ($)
Jun. 30, 2022
USD ($)
Dec. 31, 2012
utility
MW
Aug. 31, 2018
Loss Contingencies [Line Items]        
Estimated cost to complete, pre-tax charge to income $ 36      
Estimated cost to complete, pre-tax charge to income, net of tax $ 27      
Plant Vogtle Units 3 And 4        
Loss Contingencies [Line Items]        
Proportionate ownership share 45.70% 45.70%    
Number of construction units approved | utility     2  
Electric generating capacity in mega watts under consortium agreement | MW     1,100  
Estimated cost to complete, construction contingency estimate, financing costs $ 3,400 $ 3,400    
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date 3,000 3,000    
Construction contingency estimate 126 126    
Estimated cost to complete, additional construction contingency estimate 36 36    
Base project capital cost forecast, monthly   35    
Monthly AFUDC   $ 45    
Percentage of ownership interest required for voting for continuing construction       90.00%
Plant Vogtle Units 3 And 4 | Vogtle Owners        
Loss Contingencies [Line Items]        
Period of notice required in the event letters of credit are not renewed   30 days    
Minimum | Plant Vogtle Units 3 And 4 | COVID-19        
Loss Contingencies [Line Items]        
Loss contingency, estimate of possible loss, loss of productivity, term   3 months    
Estimate of possible loss 160 $ 160    
Maximum | Plant Vogtle Units 3 And 4 | COVID-19        
Loss Contingencies [Line Items]        
Loss contingency, estimate of possible loss, loss of productivity, term   4 months    
Estimate of possible loss $ 200 $ 200