XML 110 R81.htm IDEA: XBRL DOCUMENT v3.22.1
Regulatory Matters - GPC Amendments to the Vogtle Joint Ownership Agreements (Details) - Georgia Power - USD ($)
$ in Thousands
3 Months Ended
Jan. 11, 2018
Mar. 31, 2022
Aug. 31, 2018
Public Utilities, General Disclosures [Line Items]      
Pre-tax charge to income   $ 440,000  
After tax charge to income   328,000  
Plant Vogtle Units 3 And 4      
Public Utilities, General Disclosures [Line Items]      
Production tax credits, aggregate purchase price, maximum   300,000  
Preliminary estimated cost to complete   10,401,000  
Additional construction capital costs $ 3,300,000 $ 460,000  
Remaining share of construction costs, agreement to pay, percentage   100.00%  
Percentage of ownership interest required for voting for continuing construction     90.00%
Percentage of costs, disallowed for recovery   6.00%  
Costs disallowed for recovery, period   6 months  
Public utilities, extension project schedule, term   1 year  
Estimated cost to complete, starting dollar amount   $ 18,380,000  
Proportionate ownership share   45.70%  
Plant Vogtle Units 3 And 4 | Vogtle Owners      
Public Utilities, General Disclosures [Line Items]      
Additional construction capital costs   $ 100  
Plant Vogtle Units 3 And 4 | Category I      
Public Utilities, General Disclosures [Line Items]      
Preliminary estimated cost to complete   8,400,000  
Additional construction capital costs, threshold   $ 800,000  
Plant Vogtle Units 3 And 4 | Category II      
Public Utilities, General Disclosures [Line Items]      
Percentage of construction costs, responsibility to pay   55.70%  
Additional construction capital costs   $ 80,000  
Plant Vogtle Units 3 And 4 | Category II | Vogtle Owners      
Public Utilities, General Disclosures [Line Items]      
Percentage of construction costs, responsibility to pay   44.30%  
Plant Vogtle Units 3 And 4 | Category II | Minimum      
Public Utilities, General Disclosures [Line Items]      
Additional construction capital costs, threshold   $ 800,000  
Plant Vogtle Units 3 And 4 | Category II | Maximum      
Public Utilities, General Disclosures [Line Items]      
Additional construction capital costs, threshold   $ 1,600,000  
Plant Vogtle Units 3 And 4 | Category III      
Public Utilities, General Disclosures [Line Items]      
Percentage of construction costs, responsibility to pay   65.70%  
Additional construction capital costs   $ 100,000  
Plant Vogtle Units 3 And 4 | Category III | Vogtle Owners      
Public Utilities, General Disclosures [Line Items]      
Percentage of construction costs, responsibility to pay   34.30%  
Plant Vogtle Units 3 And 4 | Category III | Minimum      
Public Utilities, General Disclosures [Line Items]      
Additional construction capital costs, threshold   $ 1,600,000  
Plant Vogtle Units 3 And 4 | Category III | Maximum      
Public Utilities, General Disclosures [Line Items]      
Additional construction capital costs, threshold   $ 2,100,000