Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO
$ in Millions
3 Months Ended
Mar. 31, 2022
USD ($)
Loss Contingencies [Line Items]  
Pre-tax charge to income $ 440
Plant Vogtle Units 3 And 4  
Loss Contingencies [Line Items]  
Base project capital cost forecast 10,294
Construction contingency estimate 107
Total project capital cost forecast 10,401
Net investment as of end of the period (8,715)
Remaining estimate to complete 1,686
Estimated cost to complete, costs not shared with other owners 590
Expected capitalized costs 377
Capitalized interest accrued 221
Plant Vogtle Units 3 And 4 | Twenty Fifth Vogtle Construction Monitoring Report  
Loss Contingencies [Line Items]  
Guarantor obligations 1,700
Customer refund $ 188