Acquisitions and Dispositions - Schedule of Construction Projects (Details) - SOUTHERN POWER CO - MW
1 Months Ended 3 Months Ended 4 Months Ended 6 Months Ended 9 Months Ended
Sep. 30, 2021
Dec. 31, 2021
Dec. 31, 2021
Mar. 31, 2022
Sep. 30, 2021
Dec. 31, 2020
Garland Solar Storage            
Business Acquisition [Line Items]            
Nameplate capacity placed in service (in MWs) 45       45  
Garland Solar Storage | Scenario, Forecast            
Business Acquisition [Line Items]            
Nameplate capacity placed in service (in MWs)   43        
Garland Solar Storage | Scenario, Forecast | Subsequent Event            
Business Acquisition [Line Items]            
Approximate Nameplate Capacity (MW)   88 88      
PPA Contract Period     20 years      
Tranquillity Solar Storage | Scenario, Forecast | Subsequent Event            
Business Acquisition [Line Items]            
Approximate Nameplate Capacity (MW)       72    
PPA Contract Period       20 years    
Glass Sands | Scenario, Forecast | Subsequent Event            
Business Acquisition [Line Items]            
Approximate Nameplate Capacity (MW)   118 118      
PPA Contract Period   12 years        
Glass Sands | Glass Sands            
Business Acquisition [Line Items]            
Ownership percentage by parent           100.00%