Regulatory Matters - GPC Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4 - USD ($)
$ in Millions
6 Months Ended
Jun. 30, 2021
Jun. 30, 2020
Loss Contingencies [Line Items]    
Base project capital cost forecast $ 9,096  
Construction contingency estimate 119  
Total project capital cost forecast 9,215  
Net investment as of end of the period (7,856)  
Remaining estimate to complete 1,359  
Estimated cost to complete, costs not shared with other owners 570  
Expected capitalized costs 290  
Capitalized interest accrued 143  
Twenty Third Vogtle Construction Monitoring Report    
Loss Contingencies [Line Items]    
Guarantor obligations 1,700 $ 1,700
Customer refund $ 188 $ 188