Regulatory Matters - GPC Nuclear Construction (Details)
$ in Millions
3 Months Ended 12 Months Ended
Mar. 31, 2021
USD ($)
Mar. 31, 2020
USD ($)
Dec. 31, 2012
utility
MW
Aug. 31, 2018
Loss Contingencies [Line Items]        
Estimated loss on Plant Vogtle Units 3 and 4 $ 48 $ 0    
GEORGIA POWER CO        
Loss Contingencies [Line Items]        
Estimated loss on Plant Vogtle Units 3 and 4 48 $ 0    
Estimated loss on Plant Vogtle Units 3 and 4, net of tax $ 36      
GEORGIA POWER CO | Plant Vogtle Units 3 And 4        
Loss Contingencies [Line Items]        
Proportionate ownership share 45.70%      
Number of construction units approved | utility     2  
Electric generating capacity in mega watts under consortium agreement | MW     1,100  
Estimated cost to complete, construction contingency estimate, financing costs $ 3,000      
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date 2,700      
Construction contingency estimate 84      
Construction contingency estimate, additional amount 48      
Base project capital cost forecast, monthly 25      
Monthly AFUDC $ 15      
Percentage of ownership interest required for voting for continuing construction       90.00%
GEORGIA POWER CO | Plant Vogtle Units 3 And 4 | Vogtle Owners        
Loss Contingencies [Line Items]        
Period of notice required in the event letters of credit are not renewed 30 days      
Minimum | GEORGIA POWER CO | Plant Vogtle Units 3 And 4 | COVID-19        
Loss Contingencies [Line Items]        
Loss contingency, estimate of possible loss, loss of productivity, term 3 months      
Estimate of possible loss $ 150      
Maximum | GEORGIA POWER CO | Plant Vogtle Units 3 And 4 | COVID-19        
Loss Contingencies [Line Items]        
Loss contingency, estimate of possible loss, loss of productivity, term 4 months      
Estimate of possible loss $ 190