XML 52 R26.htm IDEA: XBRL DOCUMENT v3.21.1
Regulatory Matters (Tables)
3 Months Ended
Mar. 31, 2021
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at March 31, 2021 and December 31, 2020 were as follows:
Regulatory ClauseBalance Sheet Line ItemMarch 31,
2021
December 31, 2020
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory liabilities, current$33 $28 
Rate CNP PPAOther regulatory assets, deferred58 58 
Retail Energy Cost RecoveryOther regulatory liabilities, current 18 
Other regulatory assets, deferred15 — 
Natural Disaster ReserveOther regulatory liabilities, deferred52 77 
Georgia Power
Fuel Cost Recovery
Over recovered fuel clause revenues
$83 $113 
Mississippi Power
Fuel Cost Recovery
Over recovered regulatory clause liabilities
$18 $24 
Ad Valorem Tax
Other regulatory assets, current
12 11 
Other regulatory assets, deferred
45 41 
Property Damage Reserve
Other regulatory liabilities, deferred
 
Other regulatory assets, deferred
1 — 
Southern Company Gas
Natural Gas Cost Recovery(*)
Other regulatory liabilities
$12 $88 
Natural gas cost under recovery487 — 
Other regulatory assets, deferred185 — 
(*)The significant change during the three months ended March 31, 2021 was primarily driven by an increase in the cost of gas purchased in February 2021 resulting from Winter Storm Uri.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4 by December 2021 and November 2022, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$8,619 
Construction contingency estimate136 
Total project capital cost forecast(a)(b)
8,755 
Net investment as of March 31, 2021(b)
(7,560)
Remaining estimate to complete(a)
$1,195 
(a)    Excludes financing costs expected to be capitalized through AFUDC of approximately $250 million, of which $118 million had been accrued through March 31, 2021.
(b)    Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs during the first three months of 2021 were as follows:
UtilityProgramThree Months Ended
March 31, 2021
(in millions)
Nicor GasInvesting in Illinois$45 
Virginia Natural GasSteps to Advance Virginia's Energy
Total$54