CONTINGENCIES CONTINGENCIESSee Note 3 to the financial statements in Item 8 of the Form 10-K for information relating to various lawsuits and other contingencies.
General Litigation Matters
The Registrants are involved in various other matters being litigated and regulatory matters. The ultimate outcome of such pending or potential litigation or regulatory matters against each Registrant and any subsidiaries cannot be determined at this time; however, for current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on such Registrant's financial statements.
The Registrants believe the pending legal challenges discussed below have no merit; however, the ultimate outcome of these matters cannot be determined at this time.
Southern Company
In January 2017, a securities class action complaint was filed in the U.S. District Court for the Northern District of Georgia by Monroe County Employees' Retirement System on behalf of all persons who purchased shares of Southern Company's common stock between April 25, 2012 and October 29, 2013. The complaint names as defendants Southern Company, certain of its current and former officers, and certain former Mississippi Power officers and alleges that the defendants made materially false and misleading statements regarding the Kemper County energy facility in violation of certain provisions under the Securities Exchange Act of 1934, as amended. The complaint seeks, among other things, compensatory damages and litigation costs and attorneys' fees. In 2017, the plaintiffs filed an amended complaint that provided additional detail about their claims, increased the purported class period by one day, and added certain other former Mississippi Power officers as defendants. Also in 2017, the defendants filed a motion to dismiss the plaintiffs' amended complaint with prejudice, to which the plaintiffs filed an opposition. In 2018, the court issued an order dismissing certain claims against certain officers of Southern Company and Mississippi Power and dismissing the allegations related to a number of the statements that plaintiffs challenged as being false or misleading. In 2018, the court denied the defendants' motion for reconsideration and also denied a motion to certify the issue for interlocutory appeal. In the third quarter 2019, the court certified the plaintiffs' proposed class and the defendants filed a petition for interlocutory appeal of the class certification order with the U.S. Court of Appeals for the Eleventh Circuit. In December 2019, the U.S. District Court for the Northern
District of Georgia entered an order staying all deadlines in the case pending mediation. The stay automatically expired on March 31, 2020; however, in light of the COVID-19 pandemic, the U.S. District Court for the Northern District of Georgia vacated all existing discovery deadlines until June 15, 2020. On June 30, 2020, the court entered a revised scheduling order, which resumed discovery and set out remaining case deadlines. On August 15, 2020, the parties reached a settlement. On September 8, 2020, the plaintiffs filed a stipulation of settlement and motion for preliminary approval to resolve the case on a class-wide basis, which the court granted on October 1, 2020. The settlement amount will be paid entirely through existing insurance policies and is not expected to have a material impact on Southern Company's financial statements.
In February 2017, Jean Vineyard and Judy Mesirov each filed a shareholder derivative lawsuit in the U.S. District Court for the Northern District of Georgia. Each of these lawsuits names as defendants Southern Company, certain of its directors, certain of its current and former officers, and certain former Mississippi Power officers. In 2017, these two shareholder derivative lawsuits were consolidated in the U.S. District Court for the Northern District of Georgia. The complaints allege that the defendants caused Southern Company to make false or misleading statements regarding the Kemper County energy facility cost and schedule. Further, the complaints allege that the defendants were unjustly enriched and caused the waste of corporate assets and also allege that the individual defendants violated their fiduciary duties. Each plaintiff seeks to recover, on behalf of Southern Company, unspecified actual damages and, on each plaintiff's own behalf, attorneys' fees and costs in bringing the lawsuit. Each plaintiff also seeks certain changes to Southern Company's corporate governance and internal processes. In 2018, the court entered an order staying this lawsuit until 30 days after the resolution of any dispositive motions or any settlement, whichever is earlier, in the securities class action. On September 25, 2020, the plaintiffs filed a status report noting the settlement of the securities class action and informing the court that the parties have scheduled mediation of this case later in the fourth quarter 2020.
In May 2017, Helen E. Piper Survivor's Trust filed a shareholder derivative lawsuit in the Superior Court of Gwinnett County, Georgia that names as defendants Southern Company, certain of its directors, certain of its current and former officers, and certain former Mississippi Power officers. The complaint alleges that the individual defendants, among other things, breached their fiduciary duties in connection with schedule delays and cost overruns associated with the construction of the Kemper County energy facility. The complaint further alleges that the individual defendants authorized or failed to correct false and misleading statements regarding the Kemper County energy facility schedule and cost and failed to implement necessary internal controls to prevent harm to Southern Company. The plaintiff seeks to recover, on behalf of Southern Company, unspecified actual damages and disgorgement of profits and, on its behalf, attorneys' fees and costs in bringing the lawsuit. The plaintiff also seeks certain unspecified changes to Southern Company's corporate governance and internal processes. In 2018, the court entered an order staying this lawsuit until 30 days after the resolution of any dispositive motions or any settlement, whichever is earlier, in the securities class action. In August 2019, the court granted a motion filed by the plaintiff in July 2019 to substitute a new named plaintiff, Martin J. Kobuck, in place of Helen E. Piper Survivor's Trust. On September 30, 2020, the plaintiffs filed a status report noting the settlement of the securities class action and informing the court that the parties have scheduled mediation of this case later in the fourth quarter 2020.
Georgia Power
In 2011, plaintiffs filed a putative class action against Georgia Power in the Superior Court of Fulton County, Georgia alleging that Georgia Power's collection in rates of amounts for municipal franchise fees (which fees are paid to municipalities) exceeded the amounts allowed in orders of the Georgia PSC and alleging certain state law claims. This case has been ruled upon and appealed numerous times over the last several years. In one recent appeal, the Georgia Supreme Court remanded the case and noted that the trial court could refer the matter to the Georgia PSC to interpret its tariffs. Following a motion by Georgia Power, in February 2019, the Superior Court of Fulton County ordered the parties to submit petitions to the Georgia PSC for a declaratory ruling and also conditionally certified the proposed class. In March 2019, Georgia Power and the plaintiffs filed petitions with the Georgia PSC seeking confirmation of the proper application of the municipal franchise fee schedule pursuant to the Georgia PSC's orders. Also in March 2019, Georgia Power appealed the class certification decision to the Georgia Court of
Appeals. In October 2019, the Georgia PSC issued an order that found Georgia Power has appropriately implemented the municipal franchise fee schedule. On March 11, 2020, the Georgia Court of Appeals vacated the Superior Court of Fulton County's February 2019 order granting conditional class certification. The Court of Appeals remanded the case to the Superior Court of Fulton County for further proceedings. In September 2020, the plaintiffs and Georgia Power each filed motions for summary judgment on all claims and the plaintiffs renewed their motion for class certification. The amount of any possible losses cannot be calculated at this time because, among other factors, it is unknown whether a class will be certified, the ultimate composition of any class, and whether any losses would be subject to recovery from any municipalities.
On July 29, 2020, a group of individual plaintiffs filed a complaint in the Superior Court of Fulton County, Georgia against Georgia Power alleging that releases from Plant Scherer have impacted groundwater, surface water, and air, resulting in alleged personal injuries and property damage. The plaintiffs seek an unspecified amount of monetary damages including punitive damages, a medical monitoring fund, and injunctive relief.
Mississippi Power
In May 2018, Southern Company and Mississippi Power received a notice of dispute and arbitration demand filed by Martin Product Sales, LLC (Martin) based on two agreements, both related to Kemper IGCC byproducts for which Mississippi Power provided termination notices in 2017. Martin alleges breach of contract, breach of good faith and fair dealing, fraud and misrepresentation, and civil conspiracy and makes a claim for damages in the amount of approximately $143 million, as well as additional unspecified damages, attorney's fees, costs, and interest. A portion of the claim for damages was on behalf of Martin Transport, Inc. (Martin Transport), an affiliate of Martin. In May 2019, the arbitration panel denied Mississippi Power's and Southern Company's motions to dismiss. In September 2019, Martin Transport filed a separate complaint against Mississippi Power in the Circuit Court of Kemper County, Mississippi alleging claims of fraud, negligent misrepresentation, promissory estoppel, and equitable estoppel, each arising out of the same alleged facts and circumstances that underlie Martin's arbitration demand. Martin Transport seeks compensatory damages of $5 million and punitive damages of $50 million. In November 2019, Martin Transport's claim was combined with the Martin arbitration case and the separate court case was dismissed. In December 2019, Southern Company and Mississippi Power each filed motions for summary judgment on all claims. On February 17, 2020, the arbitration panel granted Southern Company's motion and dismissed Southern Company from the arbitration. On March 12, 2020, the arbitration panel denied Mississippi Power's motions for summary judgment. During the third quarter 2020, the plaintiffs reduced their claim for damages to approximately $76 million. On October 12, 2020, the arbitration panel issued a unanimous award in favor of Mississippi Power on all claims. This matter is now concluded.
In November 2018, Ray C. Turnage and 10 other individual plaintiffs filed a putative class action complaint against Mississippi Power and the three then-serving members of the Mississippi PSC in the U.S. District Court for the Southern District of Mississippi. Mississippi Power received Mississippi PSC approval in 2013 to charge a mirror CWIP rate premised upon including in its rate base pre-construction and construction costs for the Kemper IGCC prior to placing the Kemper IGCC into service. The Mississippi Supreme Court reversed that approval and ordered Mississippi Power to refund the amounts paid by customers under the previously-approved mirror CWIP rate. The plaintiffs allege that the initial approval process, and the amount approved, were improper. They also allege that Mississippi Power underpaid customers by up to $23.5 million in the refund process by applying an incorrect interest rate. The plaintiffs seek to recover, on behalf of themselves and their putative class, actual damages, punitive damages, pre-judgment interest, post-judgment interest, attorney's fees, and costs. In response to Mississippi Power and the Mississippi PSC each filing a motion to dismiss, the plaintiffs filed an amended complaint in March 2019. The amended complaint included four additional plaintiffs and additional claims for gross negligence, reckless conduct, and intentional wrongdoing. Mississippi Power and the Mississippi PSC have each filed a motion to dismiss the amended complaint. On March 27, 2020, the Mississippi PSC's motion to dismiss was granted. Also on March 27, 2020, the plaintiffs filed a motion seeking to name the new members of the Mississippi PSC, the Mississippi Development Authority, and Southern Company as additional defendants and add a cause of action against all defendants based on a dormant commerce clause theory under the U.S. Constitution. On April 9, 2020 and April 10, 2020, Mississippi Power and the Mississippi PSC, respectively, filed responses opposing the
motion for leave to file a second amended complaint. On May 26, 2020, the court granted Mississippi Power's motion to dismiss the first amended complaint filed in 2019. On July 6, 2020, the plaintiffs filed a motion for revision of the court's decision. The plaintiffs' motion for leave to file a second amended complaint also remains pending before the court. On July 28, 2020, the plaintiffs filed a motion for leave to file a third amended complaint, which includes the same federal claims as the proposed second amended complaint, as well as several additional state law claims based on the allegation that Mississippi Power failed to disclose the annual percentage rate of interest applicable to refunds. An adverse outcome in this proceeding could have a material impact on Mississippi Power's financial statements.
See Note 2 to the financial statements under "Mississippi Power – Kemper County Energy Facility" in Item 8 of the Form 10-K for additional information.
Environmental Remediation
The Southern Company system must comply with environmental laws and regulations governing the handling and disposal of waste and releases of hazardous substances. Under these various laws and regulations, the Southern Company system could incur substantial costs to clean up affected sites. The traditional electric operating companies and the natural gas distribution utilities in Illinois and Georgia have each received authority from their respective state PSCs or other applicable state regulatory agencies to recover approved environmental compliance costs through regulatory mechanisms. These regulatory mechanisms are adjusted annually or as necessary within limits approved by the state PSCs or other applicable state regulatory agencies.
Georgia Power's environmental remediation liability was $15 million at both September 30, 2020 and December 31, 2019. Georgia Power has been designated or identified as a potentially responsible party at sites governed by the Georgia Hazardous Site Response Act and/or by the federal Comprehensive Environmental Response, Compensation, and Liability Act, and assessment and potential cleanup of such sites is expected.
In December 2019, Mississippi Power entered into an agreement with the Mississippi Commission on Environmental Quality related to groundwater conditions arising from the closed ash pond at Plant Watson. Mississippi Power will complete an assessment and remediation consistent with the requirements of the agreement and the CCR Rule. Potential remediation activities and related cost estimates are pending the result of further site assessment and cannot be determined at this time. Mississippi Power expects to recover the retail portion of remedial costs through the ECO Plan and the wholesale portion through MRA rates.
Southern Company Gas' environmental remediation liability was $252 million and $269 million as of September 30, 2020 and December 31, 2019, respectively, based on the estimated cost of environmental investigation and remediation associated with known current and former manufactured gas plant operating sites. These environmental remediation expenditures are generally recoverable from customers through rate mechanisms approved by the applicable state regulatory agencies of the natural gas distribution utilities.
The ultimate outcome of these matters cannot be determined at this time; however, as a result of the regulatory treatment for environmental remediation expenses described above, the final disposition of these matters is not expected to have a material impact on the financial statements of the applicable Registrants.
Nuclear Fuel Disposal Costs
On August 13, 2020, Alabama Power and Georgia Power filed amended complaints in each of the lawsuits against the U.S. government in the Court of Federal Claims for the costs of continuing to store spent nuclear fuel at Plants Farley, Hatch, and Vogtle Units 1 and 2. The amended complaints add damages from January 1, 2018 to December 31, 2019 to the claim period. Damages will continue to accumulate until the issue is resolved, the U.S. government disposes of Alabama Power's and Georgia Power's spent nuclear fuel pursuant to its contractual obligations, or alternative storage is otherwise provided. No amounts have been recognized in the financial statements as of September 30, 2020 for any potential recoveries from the pending lawsuits. The final outcome of these matters cannot be determined at this time. However, Alabama Power and Georgia Power expect to credit any recoveries for
the benefit of customers in accordance with direction from their respective PSC; therefore, no material impact on Southern Company's, Alabama Power's, or Georgia Power's net income is expected.
Other Matters
Southern Company
See Notes 1 and 3 under "Leveraged Leases" and "Other Matters – Southern Company," respectively, in Item 8 of the Form 10-K for discussion of challenges associated with a leveraged lease agreement with a subsidiary of Southern Holdings. While all required lease payments through September 30, 2020 have been paid in full, the operational and remarketing risks and the resulting cash liquidity challenges persist and significant concerns continue regarding the lessee's ability to make the remaining required semi-annual lease payments to the Southern Holdings subsidiary through the term of the lease.
In its annual impairment analysis of the expected residual value of the generation assets and the overall collectability of the related lease receivable, Southern Company uses multiple scenarios of long-term market energy prices to estimate the cash flows expected to be received from remarketing the generation assets following the expiration of the existing PPA in 2032 and the residual value of the generation assets at the end of the lease in 2047. Southern Company received the latest annual forecasts of natural gas prices during the second quarter 2020 and considered the significant decline in forecasted prices to be an indicator of potential impairment that required an interim impairment assessment. Accordingly, consistent with prior years, Southern Company evaluated the recoverability of the lease receivable and the expected residual value of the generation assets under various natural gas price scenarios. Based on the current forecasts of energy prices in the years following the expiration of the existing PPA, Southern Company concluded that it is no longer probable that any of the associated rental payments will be received, because it is no longer probable the generation assets will be successfully remarketed and continue to operate after that date. During the second quarter 2020, Southern Company revised the estimated cash flows to be received under the leveraged lease to reflect this conclusion, which resulted in a full impairment of the lease investment and a pre-tax charge to earnings of $154 million ($74 million after tax).
If any future lease payment due prior to the expiration of the associated PPA is not paid in full, the Southern Holdings subsidiary may be unable to make its corresponding payment to the holders of the underlying non-recourse debt related to the generation assets. Failure to make the required payment to the debtholders could represent an event of default that would give the debtholders the right to foreclose on, and take ownership of, the generation assets, in effect terminating the lease. As the remaining amount of the lease investment was charged against earnings in the second quarter 2020, termination would not be expected to result in additional charges. Southern Company will continue to monitor the operational performance of the underlying assets and evaluate the ability of the lessee to continue to make the required lease payments and meet its obligations associated with a future closure or retirement of the generation assets and associated properties, including the dry ash landfill.
Mississippi Power
Kemper County Energy Facility
See Note 2 to the financial statements under "Mississippi Power – Kemper County Energy Facility" in Item 8 of the Form 10-K for additional information.
As the mining permit holder, Liberty Fuels Company, LLC has a legal obligation to perform mine reclamation and Mississippi Power has a contractual obligation to fund all reclamation activities related to the lignite mine and equipment and mineral reserves located around the Kemper County energy facility site. As a result of the abandonment of the Kemper IGCC, final mine reclamation began in 2018 and is expected to be substantially completed in 2020, with monitoring expected to continue through 2027. See Note 6 to the financial statements in Item 8 of the Form 10-K for additional information.
For year-to-date 2020, Mississippi Power recorded pre-tax (and after-tax) charges to income totaling $2 million primarily associated with abandonment and related closure costs and ongoing period costs, net of salvage proceeds,
for the mine and gasifier-related assets at the Kemper County energy facility. Dismantlement of the abandoned gasifier-related assets and site restoration activities are expected to be completed in 2025. The additional pre-tax period costs associated with dismantlement and site restoration activities, including related costs for compliance and safety, ARO accretion, and property taxes, net of salvage, are estimated to total $3 million for the remainder of 2020 and $10 million to $15 million annually for 2021 through 2025.
In December 2019, Mississippi Power transferred ownership of the CO2 pipeline to an unrelated gas pipeline company, with no resulting impact on income. In conjunction with the transfer of the CO2 pipeline, the parties agreed to enter into a 15-year firm transportation agreement, which is expected to be signed by the end of 2020, providing for the conversion by the pipeline company of the CO2 pipeline to a natural gas pipeline to be used for the delivery of natural gas to Plant Ratcliffe. The agreement is expected to be treated as a finance lease for accounting purposes upon commencement.
On September 3, 2020, Mississippi Power and Southern Company executed an agreement with the DOE completing Mississippi Power's request for property closeout certification under the contract related to the DOE grants received for the Kemper County energy facility, which enables Mississippi Power to proceed with full dismantlement of the abandoned gasifier-related assets and site restoration activities. The execution of the agreement had no material impact on Mississippi Power's financial statements. In connection with the DOE closeout discussions, in April 2019, the Civil Division of the Department of Justice informed Southern Company and Mississippi Power of an investigation related to the $387 million of DOE grants received. The ultimate outcome of this matter cannot be determined at this time; however, it could have a material impact on Southern Company's and Mississippi Power's financial statements.
Plant Daniel
In conjunction with Southern Company's sale of Gulf Power, Mississippi Power and Gulf Power agreed to seek a restructuring of their 50% undivided ownership interests in Plant Daniel such that each of them would, after the restructuring, own 100% of a generating unit. On April 24, 2020, Mississippi Power and Gulf Power amended the terms of the agreement to extend the deadline from May 1, 2020 to August 1, 2020 for Mississippi Power to notify Gulf Power of which generating unit it has selected for 100% ownership. The parties agreed not to select a specific unit by August 1, 2020 and are continuing negotiations on a mutually acceptable revised operating agreement. The impacts of operating the units on an individual basis continue to be evaluated by Mississippi Power and any transfer of ownership would be subject to approval by the FERC and the Mississippi PSC. The ultimate outcome of this matter cannot be determined at this time.
Southern Company Gas
See Notes 3 and 7 to the financial statements in Item 8 of the Form 10-K under "Other Matters – Southern Company Gas" and "Southern Company Gas," respectively, and Note (E) under "Southern Company Gas" for additional information.
On March 24, 2020, Southern Company Gas completed the sale of its interest in Atlantic Coast Pipeline. See Note (K) under "Southern Company Gas" for additional information.
On February 20, 2020, the FERC approved a two-year extension for PennEast Pipeline to complete the project by January 19, 2022.
In September 2019, an appellate court ruled that the PennEast Pipeline does not have federal eminent domain authority over lands in which a state has property rights interests. On June 29, 2020, the U.S. Supreme Court requested the U.S. Solicitor General to provide an opinion on PennEast Pipeline's petition for a writ of certiorari seeking its review of the appellate court's decision.
Expected project costs related to the PennEast Pipeline for Southern Company Gas total approximately $300 million, excluding financing costs. The ultimate outcome of the PennEast Pipeline construction project cannot be determined at this time; however, any work delays, whether caused by judicial or regulatory action, abnormal weather, or other conditions, may result in additional cost or schedule modifications or, ultimately, in project
cancellation, any of which could result in impairment of Southern Company Gas' investment and could have a significant impact on Southern Company's financial statements and a material impact on Southern Company Gas' financial statements.