REGULATORY MATTERS - Nuclear Construction (Details) - GEORGIA POWER CO
$ in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Jan. 01, 2021
Apr. 15, 2020
Feb. 19, 2020
USD ($)
Feb. 18, 2020
USD ($)
Jan. 01, 2020
Jan. 11, 2018
USD ($)
Jan. 01, 2016
Dec. 31, 2019
USD ($)
Dec. 31, 2018
appeal
Mar. 31, 2020
USD ($)
Dec. 31, 2022
USD ($)
Dec. 31, 2021
USD ($)
Dec. 31, 2020
USD ($)
Dec. 31, 2019
USD ($)
Dec. 31, 2012
utility
MW
Dec. 31, 2009
USD ($)
Jun. 30, 2019
report
Aug. 31, 2018
Jun. 30, 2018
USD ($)
Dec. 31, 2013
Loss Contingencies [Line Items]                                        
Number of construction units approved | utility                             2          
Electric generating capacity in mega watts under consortium agreement | MW                             1,100          
Estimated in-service capital cost                               $ 4,418        
Financing costs collected, net of tax                   $ 2,300                    
Increase (decrease) in NCCR tariff               $ (62)                        
Additional construction capital costs           $ 3,300                            
Amendment to estimated in-service capital cost           $ 5,680                            
Retail rate of return on common equity                                       10.95%
Number of appeals | appeal                 2                      
Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Proportionate ownership share                   45.70%                    
Construction contingency estimate, subject to rate recovery evaluation                   $ 66                 $ 366  
Construction contingency estimate, subject to rate recovery evaluation, cumulative amount allocated to base capital cost forecast                   206                    
Construction financing costs                   2,300                    
Base project capital cost forecast, monthly                   50                    
Monthly AFUDC                   $ 10                    
Percentage of ownership interest required for voting for continuing construction                                   90.00%    
Percentage of costs, disallowed for recovery                   6.00%                    
Costs disallowed for recovery, period                   6 months                    
Public utilities, extension project schedule, term                   1 year                    
Production tax credits, aggregate purchase price, maximum                   $ 300                    
Remaining share of construction costs, agreement to pay, percentage                   100.00%                    
Preliminary estimated cost to complete                   $ 8,400                    
Cost settlement agreement revised forecast, net of payments                   $ 7,300                    
Public utilities, approved return on equity percentage         8.30%   10.00%                          
Public utilities, approved return on equity, monthly percentage decrease                   0.10%                    
Return on equity reduction, negative impact on earnings                           $ 75            
Plant Vogtle Units 3 And 4 | Scenario, Forecast                                        
Loss Contingencies [Line Items]                                        
Construction financing costs                         $ 3,100              
Public utilities, approved return on equity percentage 5.30%                                      
Return on equity reduction, negative impact on earnings                     $ 200 $ 255 $ 145              
Plant Vogtle Units 3 And 4 | Vogtle Owners                                        
Loss Contingencies [Line Items]                                        
Period of notice required in the event letters of credit are not renewed                   30 days                    
Twenty First Vogtle Construction Monitoring Report | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Number of approved VCM reports | report                                 21      
Requested capital construction costs       $ 6,700                                
Guarantor obligations       1,700                                
Customer refund       $ 188                                
Twenty Second Vogtle Construction Monitoring Report | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Requested capital construction costs     $ 674                                  
Maximum | COVID-19                                        
Loss Contingencies [Line Items]                                        
Estimate of possible loss                   $ 20                    
Subsequent Event | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Expected percentage of positions eliminated   20.00%                                    
Category I | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Additional construction capital costs, threshold                   800                    
Preliminary estimated cost to complete                   $ 8,400                    
Category II | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Percentage of construction costs, responsibility to pay                   55.70%                    
Additional construction capital costs                   $ 80                    
Category II | Plant Vogtle Units 3 And 4 | Vogtle Owners                                        
Loss Contingencies [Line Items]                                        
Percentage of construction costs, responsibility to pay                   44.30%                    
Category II | Minimum | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Additional construction capital costs, threshold                   $ 800                    
Category II | Maximum | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Additional construction capital costs, threshold                   $ 1,600                    
Category III | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Percentage of construction costs, responsibility to pay                   65.70%                    
Additional construction capital costs                   $ 100                    
Category III | Plant Vogtle Units 3 And 4 | Vogtle Owners                                        
Loss Contingencies [Line Items]                                        
Percentage of construction costs, responsibility to pay                   34.30%                    
Category III | Maximum | Plant Vogtle Units 3 And 4                                        
Loss Contingencies [Line Items]                                        
Additional construction capital costs, threshold                   $ 2,100