REGULATORY MATTERS - Schedule of Nuclear Construction Cost and Schedule (Details) - USD ($) $ in Millions |
12 Months Ended | |||
---|---|---|---|---|
Feb. 18, 2020 |
Dec. 31, 2019 |
Dec. 31, 2018 |
Dec. 31, 2017 |
|
Commitments [Line Items] | ||||
Total AFUDC and interest capitalized | $ 202 | $ 210 | $ 249 | |
Georgia Power | ||||
Commitments [Line Items] | ||||
Total AFUDC and interest capitalized | 103 | $ 94 | $ 63 | |
Customer refund | 55 | |||
Georgia Power | Plant Vogtle Units 3 And 4 | ||||
Commitments [Line Items] | ||||
Base project capital cost forecast | 8,200 | |||
Construction contingency estimate | 200 | |||
Total project capital cost forecast | 8,400 | |||
Net investment | (5,900) | |||
Remaining estimate to complete | 2,500 | |||
Total AFUDC and interest capitalized | 300 | |||
Total AFUDC and interest capitalized, accrual amount | $ 23 | |||
Subsequent Event | Twenty First Vogtle Construction Monitoring Report | Georgia Power | Plant Vogtle Units 3 And 4 | ||||
Commitments [Line Items] | ||||
Maximum guarantee | $ 1,700 | |||
Customer refund | $ 188 |