BECHTEL POWER CORPORATION | |||
By: | /s/Brian Reilly | ||
Name: | Brian Reilly | ||
Title: | SVP & Project Manager | ||
GEORGIA POWER COMPANY, as an Owner and as agent for the other Owners | |||
By: | /s/David L. McKinney | ||
Name: | David L. McKinney | ||
Title: | Sr. VP, Nuclear Development |
Table 1. Work Package Division of Responsibility | |
Responsibility | Description |
1. Work Package Scoping and Planning | |
Owners | • Provide all engineering and procurement information as required to support Contractor Work Package Scoping and Planning. • Provide Owners’ Issued for Construction Documents (drawings, installation specifications, ASME weld data sheets, etc.) • Provide ITAAC requirements within applicable work packages • Provide Plant Equipment and Materials to resolve material holds on work packages • Prepare ASME material requests, and ASME Material Requisitions for Plant Equipment and Materials • Provide ITP System Scoping Boundaries |
Contractor | • Perform Work Package scoping and planning to support the Construction schedule, with support from Owner, including: - Define scope - Inclusion of design requirements and ITAAC requirements - Assemble Owners' Issued for Construction Documents (drawings, installation specifications, weld data sheets, etc.), Verification/Inspection Data Sheets, QCIs, etc., all as provided by Owners. - Evaluate status of Plant Equipment and Materials, prepare material take-offs/material requests for Plant Equipment and Materials (by initiating material reservations), close material holds on work packages, and prepare Material Requisitions for issuance by Owners to help ensure availability of material for Work Package execution. • Prepare Work Package Scoping Document, issue for field review, incorporate comments, issue final Work Package Scoping • Review Issued for Construction Documents focusing on constructability, perform constructability walk downs, resolve comments. • Evaluate status of non-permanent plant materials and, as appropriate, prepare Material Requisitions (by initiating material reservations) to help ensure availability of material for Work Package execution. |
2. Work Package Preparation | |
Contractor | • Based on the Work Package Scoping Document, prepare Work Package including construction work steps and sequencing, issue for Owners review, resolve Owners' comments, issue final Work Package. |
Owners | • Review Work Package prepared by Contractor for incorporation of ITAAC requirements |
3. Work Package Execution | |
Contractor | • Manage/control Work Package during installation. • Perform inspections and signoffs in accordance with the requirements in the Work Package (i.e., Field Engineering inspections). • Confirm that all work steps are completed and signed-off in the Work Package. • Complete ITAAC required activities |
Owners | • Perform any inspections and signoffs identified for Owners in the Work Package. • Provide support to Contractor as requested including review and approval of changes requested to Owners' Issued for Construction Documents. |
4. Work Package Closure | |
Contractor | • Close Work Package and enter into Owners' records management system. |
5. Owners' Oversight and Staffing | |
Owners | • Perform Owners' oversight of Contractor's Work Package activities. |
Table 1. To-Go Concrete Quantities (Cast in Place & Modular) (cubic yards) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 1,925 | |||
Auxiliary Building | 7,340 | |||
Annex Building | 4,123 | |||
Shield Building | 10,938 | |||
Turbine Building | 1,244 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 803 | |||
Radwaste Building | 1,636 | |||
Total Unit 3 | 28,011 | |||
Containment | 6,621 | |||
Auxiliary Building | 9,714 | |||
Annex Building | 6,743 | |||
Shield Building | 11,706 | |||
Turbine Building | 6,955 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 803 | |||
Radwaste Building | 1,636 | |||
Total Unit 4 | 44,178 | |||
Total Site | 26,501 | |||
Notes | ||||
Table 2. (Blank) |
Notes: See Table 1 for combined quantities of Cast in Place Concrete and Modular Concrete |
Table 3. To-Go Structural Steel Quantities (tons) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 611 | |||
Auxiliary Building | 790 | |||
Annex Building | 1,035 | |||
Shield Building | 49 | |||
Turbine Building | 790 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 215 | |||
Radwaste Building | 442 | |||
Total Unit 3 | 3,933 | |||
Containment | 611 | |||
Auxiliary Building | 843 | |||
Annex Building | 1,244 | |||
Shield Building | 49 | |||
Turbine Building | 4,200 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 215 | |||
Radwaste Building | 442 | |||
Total Unit 4 | 7,604 | |||
Total Site | 65 | |||
Notes | ||||
Table 4. To-Go Large Bore Pipe Quantities (linear feet) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 8,632 | |||
Auxiliary Building | 15,343 | |||
Annex Building | 10,046 | |||
Shield Building | 0 | |||
Turbine Building | 60,526 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 2,575 | |||
Radwaste Building | 2,618 | |||
Total Unit 3 | 99,741 | |||
Containment | 9,286 | |||
Auxiliary Building | 18,074 | |||
Annex Building | 12,554 | |||
Shield Building | 0 | |||
Turbine Building | 64,788 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 2,575 | |||
Radwaste Building | 2,618 | |||
Total Unit 4 | 109,894 | |||
Total Site | 6,649 | |||
Notes | ||||
Table 5. To-Go Large Bore Pipe Hangers (each) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 824 | |||
Auxiliary Building | 1,020 | |||
Annex Building | 1,028 | |||
Shield Building | 0 | |||
Turbine Building | 3,786 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 185 | |||
Radwaste Building | 214 | |||
Total Unit 3 | 7,057 | |||
Containment | 845 | |||
Auxiliary Building | 1,089 | |||
Annex Building | 1,231 | |||
Shield Building | 0 | |||
Turbine Building | 4,486 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 185 | |||
Radwaste Building | 214 | |||
Total Unit 4 | 8,050 | |||
Total Site | 537 | |||
Notes | ||||
Table 6. To-Go Small Bore Pipe Quantities (linear feet) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 14,363 | |||
Auxiliary Building | 15,051 | |||
Annex Building | 13,129 | |||
Shield Building | 0 | |||
Turbine Building | 56,566 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 1,464 | |||
Radwaste Building | 2,069 | |||
Total Unit 3 | 102,642 | |||
Containment | 14,792 | |||
Auxiliary Building | 19,339 | |||
Annex Building | 14,837 | |||
Shield Building | 0 | |||
Turbine Building | 57,671 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 1,464 | |||
Radwaste Building | 2,069 | |||
Total Unit 4 | 110,172 | |||
Total Site | 1,502 | |||
Notes | ||||
Table 7. To-Go Small Bore Pipe Hangers (each) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 2,245 | |||
Auxiliary Building | 1,642 | |||
Annex Building | 1,779 | |||
Shield Building | 0 | |||
Turbine Building | 6,486 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 176 | |||
Radwaste Building | 280 | |||
Total Unit 3 | 12,608 | |||
Containment | 2,249 | |||
Auxiliary Building | 1,748 | |||
Annex Building | 1,940 | |||
Shield Building | 0 | |||
Turbine Building | 6,770 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 176 | |||
Radwaste Building | 280 | |||
Total Unit 4 | 13,163 | |||
Total Site | 938 | |||
Notes | ||||
Table 8. To-Go Scheduled Cable Quantities (linear feet) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 332,780 | |||
Auxiliary Building | 689,691 | |||
Annex Building | 552,942 | |||
Shield Building | 0 | |||
Turbine Building | 1,091,432 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 37,369 | |||
Radwaste Building | 26,454 | |||
Total Unit 3 | 2,730,668 | |||
Containment | 332,926 | |||
Auxiliary Building | 688,690 | |||
Annex Building | 553,725 | |||
Shield Building | 0 | |||
Turbine Building | 1,111,896 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 36,495 | |||
Radwaste Building | 26,472 | |||
Total Unit 4 | 2,750,204 | |||
Total Site | 1,577,660 | |||
Notes | ||||
Table 9. To-Go Scheduled Conduit Quantities (linear feet) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 31,484 | |||
Auxiliary Building | 60,530 | |||
Annex Building | 39,550 | |||
Shield Building | 0 | |||
Turbine Building | 77,649 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 6,922 | |||
Radwaste Building | 5,592 | |||
Total Unit 3 | 221,727 | |||
Containment | 31,484 | |||
Auxiliary Building | 60,530 | |||
Annex Building | 39,663 | |||
Shield Building | 0 | |||
Turbine Building | 77,271 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 6,784 | |||
Radwaste Building | 5,592 | |||
Total Unit 4 | 221,324 | |||
Total Site | 303,447 | |||
Notes | ||||
Table 10. To-Go Cable Tray Quantities (linear feet) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 6,314 | |||
Auxiliary Building | 9,920 | |||
Annex Building | 11,127 | |||
Shield Building | 0 | |||
Turbine Building | 18,445 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 480 | |||
Radwaste Building | 759 | |||
Total Unit 3 | 47,045 | |||
Containment | 6,314 | |||
Auxiliary Building | 9,920 | |||
Annex Building | 11,127 | |||
Shield Building | 0 | |||
Turbine Building | 18,432 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 480 | |||
Radwaste Building | 759 | |||
Total Unit 4 | 47,032 | |||
Total Site | 8,322 | |||
Notes | ||||
Table 11. To-Go Cable Terminations Quantities (each) | ||||
10/23/2017 Remaining | ||||
Building | To-Go | |||
Quantities (Revised) | ||||
Containment | 15,920 | |||
Auxiliary Building | 58,340 | |||
Annex Building | 35,689 | |||
Shield Building | 0 | |||
Turbine Building | 43,858 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 3,576 | |||
Radwaste Building | 1,642 | |||
Total Unit 3 | 159,025 | |||
Containment | 15,920 | |||
Auxiliary Building | 58,264 | |||
Annex Building | 35,577 | |||
Shield Building | 0 | |||
Turbine Building | 43,835 | |||
Turbine Building – 1st Bay | Included above | |||
Diesel Generator Building | 3,554 | |||
Radwaste Building | 1,642 | |||
Total Unit 4 | 158,792 | |||
Total Site | 13,707 | |||
Notes | ||||