XML 104 R27.htm IDEA: XBRL DOCUMENT v3.19.3
Regulatory Matters (Tables)
9 Months Ended
Sep. 30, 2019
Regulated Operations [Abstract]  
Cost Recovery Clauses
The recovery balances for certain of Alabama Power's, Georgia Power's, and Mississippi Power's regulatory clauses at September 30, 2019 and December 31, 2018 were as follows:
Regulatory Clause
Balance Sheet Line Item
September 30,
2019
December 31,
2018
 
 
(in millions)
Alabama Power
 
 
 
Rate CNP Compliance
Deferred under recovered regulatory clause revenues
$

$
42

 
Other regulatory liabilities, deferred
55


Rate CNP PPA
Deferred under recovered regulatory clause revenues
45

25

Retail Energy Cost Recovery(*)
Deferred under recovered regulatory clause revenues

109

 
Other regulatory liabilities, deferred
21


Natural Disaster Reserve
Other regulatory liabilities, deferred
23

20

Georgia Power
 
 
 
Fuel Cost Recovery
Receivables – under recovered fuel clause revenues
$

$
115

 
Other deferred credits and liabilities
1


Mississippi Power
 
 
 
Fuel Cost Recovery
Over recovered regulatory clause liabilities
$
18

$
8

(*)
In accordance with an accounting order issued on February 5, 2019 by the Alabama PSC, Alabama Power utilized $75 million of the 2018 Rate RSE refund liability to reduce the Rate ECR under recovered balance. See Note 2 to the financial statements under "Alabama Power – Rate ECR" in Item 8 of the Form 10-K for additional information.
Requested Recovery of Proposed Increases
Georgia Power has requested recovery of the proposed increases through its existing base rate tariffs as follows:
Tariff
2020
2021
2022
 
(in millions)
Traditional base:
 
 
 
Levelized
$
210

$

$

CCR AROs
158

139

227

Environmental Compliance Cost Recovery
163



Demand-Side Management
12

1

1

Municipal Franchise Fee
17

3

5

Total(*)
$
560

$
144

$
233

(*)
Totals may not add due to rounding.
Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4 by the expected in-service dates of November 2021 and November 2022, respectively, is as follows:
 
(in billions)
Base project capital cost forecast(a)(b)
$
8.0

Construction contingency estimate
0.4

Total project capital cost forecast(a)(b)
8.4

Net investment as of September 30, 2019(b)
(5.5
)
Remaining estimate to complete(a)
$
2.9

(a)
Excludes financing costs expected to be capitalized through AFUDC of approximately $300 million.
(b)
Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related Customer Refunds.