Regulatory Matters - Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - Plant Vogtle Units 3 And 4
$ in Millions
6 Months Ended
Jun. 30, 2019
USD ($)
Loss Contingencies [Line Items]  
Base project capital cost forecast $ 8,000
Construction contingency estimate 400
Total project capital cost forecast 8,400
Net investment as of June 30, 2019 (5,200)
Remaining estimate to complete 3,200
Expected capitalized costs 315
Guarantor obligations 1,700
Customer refund $ 188