Regulatory Matters - Nuclear Construction Joint Owner Contracts (Details) - Georgia Power - Plant Vogtle Units 3 And 4
12 Months Ended
Dec. 31, 2018
USD ($)
MW
Dec. 31, 2015
USD ($)
Aug. 31, 2018
Loss Contingencies [Line Items]      
Ownership interest percentage required for voting for continuing construction 90.00%   90.00%
Total project capital cost forecast $ 8,400,000,000    
Additional construction capital costs   $ 3,300,000,000  
Additional qualifying construction costs $ 2,100,000,000    
Percent of remaining share of total construction costs 100.00%    
Percentage of cost savings 60.70%    
Nonqualifying construction costs threshold $ 100,000    
Percentage of costs disallowed for recovery 6.00%    
Costs disallowed for recovery, period 6 months    
Public utilities extension project schedule term 1 year    
Percentage of approval required to change primary construction contractor 90.00%    
Percentage of approval required for material amendments 67.00%    
Continued construction voted in favor, period 30 days    
Percentage of continued construction voted in favor 50.00%    
Share of plants (mw) | MW 206    
Purchase rights to PTCs, period 30 days    
Aggregate purchase price of PTCs $ 300,000,000    
Maximum aggregate funding $ 250,000,000    
Vogtle Owners      
Loss Contingencies [Line Items]      
Percentage of cost savings 39.30%    
Category I      
Loss Contingencies [Line Items]      
Additional construction capital costs $ 800,000,000    
Category II      
Loss Contingencies [Line Items]      
Percentage of construction costs responsible to pay 55.70%    
Category II | Vogtle Owners      
Loss Contingencies [Line Items]      
Percentage of construction costs responsible to pay 44.30%    
Category II | Minimum      
Loss Contingencies [Line Items]      
Additional construction capital costs $ 80,000,000    
Additional qualifying construction costs 800,000,000    
Category II | Maximum      
Loss Contingencies [Line Items]      
Additional qualifying construction costs $ 1,600,000,000    
Category III      
Loss Contingencies [Line Items]      
Percentage of construction costs responsible to pay 65.70%    
Category III | Vogtle Owners      
Loss Contingencies [Line Items]      
Percentage of construction costs responsible to pay 34.30%    
Category III | Minimum      
Loss Contingencies [Line Items]      
Additional construction capital costs $ 100,000,000    
Additional qualifying construction costs 1,600,000,000    
Category III | Maximum      
Loss Contingencies [Line Items]      
Additional qualifying construction costs $ 2,100,000,000