Regulatory Matters - Schedule of Nuclear Construction Cost and Schedule (Details) - USD ($)
$ in Millions
12 Months Ended
Dec. 31, 2018
Dec. 31, 2017
Dec. 31, 2016
Commitments [Line Items]      
Total AFUDC and interest capitalized $ 210 $ 249 $ 327
Georgia Power      
Commitments [Line Items]      
Total AFUDC and interest capitalized 94 $ 63 $ 68
Maximum guarantee 30    
Customer refund 40    
Georgia Power | Plant Vogtle Units 3 And 4      
Commitments [Line Items]      
Base project capital cost forecast 8,000    
Construction contingency estimate 400    
Total project capital cost forecast 8,400    
Net investment (4,600)    
Remaining estimate to complete 3,800    
Total AFUDC and interest capitalized 315    
Maximum guarantee 1,700    
Customer refund $ 188