Contingencies and Regulatory Matters - Kemper County Energy Facility (Details) - MISSISSIPPI POWER CO - USD ($)
$ in Millions
3 Months Ended 9 Months Ended 12 Months Ended
Aug. 06, 2018
Dec. 31, 2018
Sep. 30, 2018
Sep. 30, 2018
Dec. 31, 2020
Dec. 31, 2019
Dec. 31, 2017
Loss Contingencies [Line Items]              
Accrued plant closure costs     $ 30 $ 30     $ 35
Kemper County Energy Facility              
Loss Contingencies [Line Items]              
Public utilities, charges to income     0 45      
Public utilities, charges to income, after tax       34      
Accrued plant closure costs     $ 20 $ 20      
Reserve Margin Plan | Plant Watson, Unit 4              
Loss Contingencies [Line Items]              
Accelerated retirement period 2 years            
Reserve Margin Plan | Plant Watson, Unit 5              
Loss Contingencies [Line Items]              
Accelerated retirement period 7 years            
Reserve Margin Plan | Plant Greene County Units 1 and 2              
Loss Contingencies [Line Items]              
Accelerated retirement period 4 years            
Scenario, Forecast | Kemper County Energy Facility              
Loss Contingencies [Line Items]              
Production costs, period cost   $ 2     $ 4 $ 8