Contingencies and Regulatory Matters - Gulf Power (Details) - GULF POWER CO
$ in Millions
9 Months Ended 12 Months Ended
Nov. 05, 2018
USD ($)
Oct. 30, 2018
USD ($)
Oct. 10, 2018
USD ($)
Mar. 26, 2018
USD ($)
intervenor
Mar. 25, 2018
Sep. 30, 2018
USD ($)
Dec. 31, 2017
USD ($)
Loss Contingencies [Line Items]              
Property damage reserve           $ 48.0  
Property damage reserve replenishment           40.0  
Number of intervenors | intervenor       3      
Tax reform settlement agreement, annual reduction of revenue from base rates       $ 18.2      
Tax reform settlement agreement, annual reduction of revenue from environmental cost recovery rates       15.6      
Tax reform settlement agreement, refund       $ 69.4      
Customer refundable fees, refund payments           53.0  
Retail regulatory equity ratio       0.535 0.525    
Environmental Cost Recovery           21.0 $ 11.0
Projected environmental expenditures           8.0 13.0
Property Basis Differences              
Loss Contingencies [Line Items]              
Deferred tax asset, regulatory liability           7.0  
Subsequent Event              
Loss Contingencies [Line Items]              
Recovery from customers, period following the filing of cost recovery petition     60 days        
Tax reform settlement agreement, annual reduction of revenue from base rates   $ 9.6          
Decrease in annual revenues $ 38.0            
Under recovered regulatory clause revenues              
Loss Contingencies [Line Items]              
Fuel Cost Recovery           0.0 22.0
Purchased Power Capacity Recovery           0.0 2.0
Environmental Cost Recovery           0.0 2.0
Other regulatory liabilities, current              
Loss Contingencies [Line Items]              
Fuel Cost Recovery           23.0 0.0
Purchased Power Capacity Recovery           4.0 0.0
Environmental Cost Recovery           13.0 0.0
Energy Conservation Cost Recovery           $ 2.0 $ 0.0
Loss from Catastrophes | Subsequent Event | Minimum              
Loss Contingencies [Line Items]              
Estimated restoration costs     $ 350.0        
Loss from Catastrophes | Subsequent Event | Maximum              
Loss Contingencies [Line Items]              
Estimated restoration costs     $ 400.0