Contingencies and Regulatory Matters - Kemper County Energy Facility (Details) - MISSISSIPPI POWER CO - USD ($)
$ in Millions
3 Months Ended 6 Months Ended 12 Months Ended
Aug. 06, 2018
Jun. 30, 2018
Dec. 31, 2018
Jun. 30, 2018
Dec. 31, 2020
Dec. 31, 2019
Dec. 31, 2017
Loss Contingencies [Line Items]              
Accrued plant closure costs   $ 42   $ 42     $ 35
Kemper County Energy Facility              
Loss Contingencies [Line Items]              
Public utilities, property, plant and equipment, amount of loss (recovery) on plant abandonment   0   45      
Public utilities, property, plant and equipment, amount of loss (recovery) on plant abandonment after tax       33      
Accrued plant closure costs   $ 25   $ 25      
Scenario, Forecast | Kemper County Energy Facility              
Loss Contingencies [Line Items]              
Production costs, period cost     $ 4   $ 4 $ 7  
Subsequent Event | Reserve Margin Plan | Plant Watson, Unit 4              
Loss Contingencies [Line Items]              
Accelerated retirement period 2 years            
Subsequent Event | Reserve Margin Plan | Plant Watson, Unit 5              
Loss Contingencies [Line Items]              
Accelerated retirement period 7 years            
Subsequent Event | Reserve Margin Plan | Plant Greene County Units 1 and 2              
Loss Contingencies [Line Items]              
Accelerated retirement period 4 years