Contingencies and Regulatory Matters - Nuclear Construction Cost and Schedule (Details) - GEORGIA POWER CO - USD ($)
$ in Millions
6 Months Ended 12 Months Ended
Apr. 03, 2018
Jun. 30, 2018
Dec. 31, 2017
Loss Contingencies [Line Items]      
Customer refund $ 330    
Plant Vogtle Units 3 And 4      
Loss Contingencies [Line Items]      
Base project capital cost forecast   $ 8,000  
Construction contingency estimate   400  
Project capital cost forecast   8,400  
Net investment as of June 30, 2018   (4,000)  
Remaining estimate to complete   4,400  
Expected capitalized costs   $ 350  
Guarantor obligations     $ 1,700
Customer refund     $ 188