Contingencies and Regulatory Matters - Table - Current And Actual Cost Estimate (Details) - Mississippi Power [Member] - USD ($)
$ in Millions
1 Months Ended 12 Months Ended 84 Months Ended
Nov. 17, 2016
Apr. 08, 2016
Apr. 01, 2015
Jan. 31, 2013
Dec. 31, 2016
Dec. 31, 2013
Dec. 31, 2012
Dec. 31, 2016
Loss Contingencies [Line Items]                
AFUDC Cost     $ 14          
Grants received from Department of Energy               $ (382)
Total Kemper IGCC             $ 2,880  
Electricity Generation Plant, Non-Nuclear [Member]                
Loss Contingencies [Line Items]                
Plant Subject to Cost Cap       $ 2,400   $ 2,400    
Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         $ 3,310      
Plant Subject to Cost Cap $ 68       5,440      
Cost Of Lignite Mine And Equipment         230      
Cost Of CO2 Pipeline Facilities         110      
Cost Of AFUDC         750      
Combined Cycle And Related Assets Placed In Service, Incremental         40      
AFUDC Cost     $ 11          
Plant General Exceptions         90      
Plant Regulatory Asset         210      
Grants received from Department of Energy   $ (137)     (140)     $ (245)
Total Kemper IGCC         $ 6,730      
Purchase of Interest         100.00%     100.00%
Costs Subject to Cost Cap         $ 1,990      
Kemper IGCC [Member] | Project Estimate [Member]                
Loss Contingencies [Line Items]                
Plant Subject to Cost Cap         2,400      
Cost Of Lignite Mine And Equipment         210      
Cost Of CO2 Pipeline Facilities         140      
Cost Of AFUDC         170      
Combined Cycle And Related Assets Placed In Service, Incremental         0      
Plant General Exceptions         50      
Plant Regulatory Asset         0      
Grants received from Department of Energy         0      
Total Kemper IGCC         2,970      
Kemper IGCC [Member] | Current Estimate [Member]                
Loss Contingencies [Line Items]                
Plant Subject to Cost Cap         5,640      
Cost Of Lignite Mine And Equipment         230      
Cost Of CO2 Pipeline Facilities         110      
Cost Of AFUDC         790      
Combined Cycle And Related Assets Placed In Service, Incremental         40      
Plant General Exceptions         100      
Plant Regulatory Asset         220      
Grants received from Department of Energy         (140)      
Total Kemper IGCC         6,990      
Costs for Combined Cycle and Related Assets In Service Expensed [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Total Kemper IGCC         830      
Current Estimate [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Total Kemper IGCC         250      
Gasifiers and Gas Clean-up Facilities [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         1,880      
Lignite Mine Facility [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         310      
CO2 Pipeline Facilities [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         110      
Combined Cycle and Common Facilities [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         160      
AFUDC [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         690      
General Exceptions [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         70      
Plant Inventory [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         30      
Lignite Inventory [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         80      
Regulatory and Other Deferred Assets [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         120      
All Costs [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Recoverable Cost Above Maximum Cap Construction Cost         3,450      
Costs Previously Expensed and Related Assets In Service [Member] | Kemper IGCC [Member]                
Loss Contingencies [Line Items]                
Total Kemper IGCC         $ 80